African Rainbow Minerals Ltd v Tam Holdings (Pty) Ltd and Others (2023-097235) [2024] ZAGPPHC 1332 (19 December 2024)
- Citation
- [2024] ZAGPPHC 1332
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- North Gauteng High Court, Pretoria
- Panel
- Meaden
- Case number
- 2023-097235
More details
- Court
- North Gauteng High Court, Pretoria
- Panel
- Meaden
- Case number
- 2023-097235
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the parties expressly agreed to waive the statutory time limits for delivery of the arbitral award during the pre-arbitration meeting, and this waiver was binding. The respondents did not object to the timing of the award or its validity until their answering affidavit, which the court described as a late and disingenuous afterthought. The chronology of the arbitration proceedings and the conduct of the parties demonstrated that the award was delivered within a reasonable period and in accordance with the parties' agreement. The respondents' opposition based on nullity and public policy was unsupported by facts or law. No review application was brought, and even if one had been, it would not have stayed enforcement. The court concluded that the arbitral award was valid and enforceable and should be made an order of court. The respondents' conduct in failing to honour the award and attempting to delay enforcement warranted a punitive costs order.
Court disposition
Application granted. The arbitral award is made an order of court. Costs awarded against the first to third respondents on attorney and own client scale, including costs of counsel on Scale C.
Orders
- The arbitral award delivered by Jenny Cane SC is made an order of court in terms of section 31(1) of the Arbitration Act 42 of 1965.
- The first to third respondents are to pay the costs of this application, including costs of counsel on Scale C, on attorney and own client scale.
02
Material facts
Parties
African Rainbow Minerals Ltd
Applicant Counsel: LG MinnéTam Holdings (Pty) Ltd
Respondent Counsel: R RaubenheimerTechnology and Mineral Holdings (Pty) Ltd
Respondent Counsel: R RaubenheimerPieter Gideon van der Merwe
Respondent Counsel: R RaubenheimerPretorius Chemical Consultation (Pty) Ltd
RespondentDr Gerard Pretorius
RespondentAmounts and remedies
- Arbitrator's Fee Per Party (excluding Vat): ZAR 75,000
- Total Arbitrator's Fee (excluding Vat): ZAR 225,000
- Award Amount Demanded (principal): ZAR 55,336,369
03
Procedural history
Posture
Urgent Application / Application to Make Arbitral Award an Order of Court
04
Questions and positions
Legal issues
- 01
Whether the arbitral award dated 16 August 2023 should be made an order of court under section 31(1) of the Arbitration Act 42 of 1965.
- 02
Whether the respondents' opposition based on alleged nullity and lapse of arbitration proceedings is sustainable.
- 03
Whether the respondents waived time limits for delivery of the arbitral award.
- 04
Whether public policy precludes enforcement of the arbitral award.
Party arguments
- Applicant
- The applicant contended that the arbitral award was validly delivered by the agreed arbitrator, Ms Jenny Cane SC, in accordance with the parties' joint venture agreement and the UNCITRAL Arbitration Rules. The parties expressly waived the time limits under the Arbitration Act during the pre-arbitration meeting. No objections were raised by the respondents regarding timing or validity prior to the answering affidavit. The respondents failed to honour the award and did not pursue a review application. The applicant argued that there is no factual or legal impediment to making the award an order of court.
- Respondent
- The first to third respondents argued that the applicant failed to make out a case for the relief sought, alleging that the arbitral award was a nullity because the arbitration proceedings had lapsed before the award was delivered. Alternatively, they contended that the award should be reviewed and set aside under section 33 of the Arbitration Act. They also asserted, without elaboration, that making the award an order of court would be against public policy.
05
Court’s reasoning
Legal principles
- 01
Arbitration Act 42 of 1965, section 31(1)
An arbitral award may be made an order of court under section 31(1) of the Arbitration Act 42 of 1965, provided the award is valid and enforceable.
- 02
Arbitration Act 42 of 1965, section 23; UNCITRAL Arbitration Rules
Parties may expressly waive statutory time limits for delivery of an arbitral award, and such waiver is binding if agreed in writing or recorded in pre-arbitration minutes.
- 03
Arbitration Act 42 of 1965, section 33
A review application does not automatically stay enforcement of an arbitral award unless a court orders otherwise.
- 04
South African common law; case law
Bald assertions of public policy are insufficient to defeat enforcement of an arbitral award absent substantiated facts or legal grounds.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the parties expressly agreed to waive the statutory time limits for delivery of the arbitral award during the pre-arbitration meeting, and this waiver was binding. The respondents did not object to the timing of the award or its validity until their answering affidavit, which the court described as a late and disingenuous afterthought. The chronology of the arbitration proceedings and the conduct of the parties demonstrated that the award was delivered within a reasonable period and in accordance with the parties' agreement. The respondents' opposition based on nullity and public policy was unsupported by facts or law. No review application was brought, and even if one had been, it would not have stayed enforcement. The court concluded that the arbitral award was valid and enforceable and should be made an order of court. The respondents' conduct in failing to honour the award and attempting to delay enforcement warranted a punitive costs order.
Obiter and limits
- The respondents' late challenge to the validity of the award is an attempt to evade accountability and frustrate the applicant's enforcement rights.
- The delivery of the award three months after closing arguments is reasonable given the complexity and duration of the arbitration proceedings.
- Special costs orders may be warranted where parties act in bad faith or seek to delay justice without substantive grounds.
Court disposition
Application granted. The arbitral award is made an order of court. Costs awarded against the first to third respondents on attorney and own client scale, including costs of counsel on Scale C.
- The arbitral award delivered by Jenny Cane SC is made an order of court in terms of section 31(1) of the Arbitration Act 42 of 1965.
- The first to third respondents are to pay the costs of this application, including costs of counsel on Scale C, on attorney and own client scale.
Source and reliance status
North Gauteng High Court, Pretoria
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
North Gauteng High Court, Pretoria
Judgment
REPUBLIC
OF SOUTH AFRICA
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG DIVISION,
PRETORIA
CASE NO: 2023-097235
1. REPORTABLE: YES/ NO
2. OF INTEREST TO OTHER JUDGES: YES/NO
3. REVISED: YES / NO
DATE: 19 December 2024
SIGNATURE OF JUDGE:
In the matter between:
AFRICAN RAINBOW
MINERALS LTD
Applicant
and
TAM HOLDINGS (PTY) LTD
First Respondent
TECHNOLOGY AND MINERAL HOLDINGS (PTY) LTD Second Respondent
PIETER
GIDEO VAN DER MERWE
Third Respondent
PRETORIUS CHEMICAL CONSULTATION (PTY) LTD Fourth Respondent
DR
GERARD
PRETORIUS
Fifth Respondent
JUDGMENT
MEADEN A J
On 06 NOVEMBER 2024 upon hearing counsel for the parties and considering the papers, I handed down the following Order:
[1] “The Arbitral Award attached to the Notice of Motion, marked “X,” which was delivered by Jenny Cane SC in the arbitration between the Applicant (the Claimant in the arbitration) and the Respondents (the Respondents in the arbitration), is made an Order of Court in terms of Section 31(1) of the Arbitration Act 42 of 1965;
[2] the First to Third Respondents are to pay the costs of this application, including costs of counsel on Scale C, on attorney and own client scale.”
The above Order was handed down, taking consideration of the undermentioned:
[1] This is an application to have an arbitral award dated 13 August 2023, duly delivered by a single arbitrator - Ms Jenny Cane SC, made an order of court and as provided for in section 31 of the Arbitration Act 42 of 1965.[1] The arbitration award itself was annexed to the Notice of Motion as Annexure 1[2] thereto.
[2] The chronology of this matter is of relevance and in arriving at the above Court Order.
[3] On 28 February 2019, the applicant entered into and concluded a “SECOND AMENDED AND RESTATED LETTER AGREEMENT REGARDING POWDER-TECH PRODUCTS, THERMO POWER PILOT PLANT, WITBANK PRODUCTS AND THE TAM TECHNOLOGY” (“the letter agreement”) with the 1st, 3rd, and 5th respondents. In concluding this letter agreement, the above parties pooled resources and entered into a joint venture as between the applicant and the 1st respondent for purposes of purchasing vanadium and titanium rich ores, raw materials and products to process and beneficiate these ores for sale and for the benefit of the joint venture.
[4] Also on 28 February 2019, the 3rd and 4th respondents in conjunction with Gideotech (the guarantors) executed a guarantee in favour of the applicant and in terms of which, the guarantors jointly and severally guaranteed all of the 1st respondent’s obligations arising in terms of the above agreement.
[5] Per clause 13.9 of the letter agreement - “Governing law and dispute resolution” and at clause 13.9.2.1[3] thereof, the parties agreed when presented with disputes to attempt to negotiate with each other in good faith in resolving these
disputes and failing this; to proceed by way of binding arbitration and on the basis premised on clause 13.9.2.3 of the letter
agreement.[4] The content of 13.9.2.3 is recorded below:
“13.9.2.3 Unless other agreed in writing by the Parties; (i) the appointing authority in terms of the UNCITRAL Arbitration Rules shall be the Association of Arbitrators (Southern Africa), (ii) the arbitration shall be administered by the Parties, (iii) the number of arbitrators shall be 1 (one); (iv) the governing substantive law of the arbitration shall be the law of South Africa, (v) the arbitrator shall have the same remedial powers as the court of law in South Africa would have were it adjudicating the dispute, and (vi) the arbitrator shall deliver an award, which award shall be final and binding on the Parties and not subject to appeal, together with written reasons within 20 (twenty) days from the date on which the arbitration ends.”
[6] On 01 December 2020, the applicant referred a dispute that had arisen between it and the respondents to arbitration and in terms of the above clause 13 of the letter agreement read with clause 8 of the guarantee. The parties jointly agreed to the appointment of Adv. Jenny Cane SC - a member of the Johannesburg Bar and as sole arbitrator in the dispute.[5]
[7] Prior to the actual conduct of the arbitration, a First Pre-Arbitration Meeting was convened and held on 14 January 2021 and in which the Parties were represented as follows:
Claimant - Adv. T Bruinders SC, R Shein, T Herholdt, K Chaisaka, and M Cramer,
1st, 4th, and 5th respondents – W Niedinger,
2nd & 3rd respondents – Dr. G Pretorius,
Arbitrator – Adv. Jenny Cane SC.[6]
[8] Per the written minutes of this Pre-Arbitration Meeting and specifically in relation to Rules and Conduct of Arbitration, the parties, inter alia, agreed that:
(i) The arbitration be conducted in terms of clause 13.9.2.1 to 13.9.2.3 as set out in Second Amended and Restated Letter Agreement (“letter agreement”) concluded between the claimant and respondents on
28 February 2019,
(ii) the arbitrator be Jenny Cane SC, duly appointed by agreement of the parties;
(iii) the rules of the conduct of the arbitration will be in accordance with the UNCITRAL rules, as supplemented by such directions as the arbitrator may issue and such agreement as may be recorded in the minute of the and Pre-Arbitration meeting;
(iv) the Arbitrator has all the powers provided by the UNCITRAL rules to determine how the arbitration will proceed, including the power to determine procedural principles by which the arbitration is to be conducted as envisaged in article 17; and,
(v) the provisions of Sections 20, 23, and 25 of the Arbitration Act 42 of 1965 be waived. This included waiving time limits associated with the conduct of an arbitration.
[9] Following hereon, the hearing of the arbitration commenced on 04 July 2022 and closing arguments were delivered just short of the year later on 02 June 2023 and whereupon the Arbitrator reserved her award.
[10] On 05 July 2023, the applicant’s legal representative (T. Hoerholdt) per electronic email wrote to the Arbitrator requesting an indication on when the parties may expect to receive the Arbitrator’s award.[7] This correspondence was also simultaneously addressed to WWB Botha Attorneys – then representing the 1st - 3rd respondents and Anderson-Kriel Attorneys representing the 4th and 5th respondents.
[11] On 05 July 2023, Adv. Cane SC electronically responded to all the above referenced addressees advising anticipating giving an award during August 2023.[8] No issue was taken nor objection raised by any of the parties to this arbitration regarding the aforesaid advices received from Adv. Cane SC.
[12] Then on 10 August 2023, Adv. Cane SC emailed the above parties’ legal representatives advising that she will be in a position to make her award “early next week”. With this, Adv. Cane SC requested that the parties’ attorneys confirm that they hold sufficient funds with which to make payment of her fees – R 225 000 plus VAT and which will then require the each of the parties to contribute R 75 000 plus VAT on these fees.
[13] On 10 August 2023 Bowman Gilfillan for the Claimant undertook to effect payment in favour of Adv Cane SC.[9] On 14 August 2023, WWB Botha Attorneys for the 1st – 3rd respondents confirmed in writing being placed in funds sufficient to settle Adv. Cane’s account.[10]
[14] Again, no issue was raised by any of the parties on when Adv. Cane SC envisaged presenting her award and further in paying the arbitrator’s account and no reference was made by the respondents to such award being a nullity. The parties to this application awaited production of the award.
[15] On 16 August 2023, the award was published. This was then followed up by the applicant’s attorneys on 25 August and again on 11 September 2023 with letters of demand then addressed to the 1st – 3rd respondents’ attorneys demanding payment in the sum of R55,336,369 together with interest accruing thereon. The above correspondence was acknowledged by WWB Botha Attorneys on 19 September 2023 and in so doing WWB Botha Attorneys recorded that the 1st – 3rd respondents were considering their options and were afforded a period of 6 weeks post the award in which to launch an application for review of the arbitration award. Crucially, no reference was made here to the award being out of time, a nullity or otherwise.
[16] In the absence of payment being made on the award, alternatively; arrangements put in place to settle the award over an extended period of time or otherwise in compromising on the award, the applicant on 26 September 2023 launched the above application to have the above award made an order of court. This application was set down for hearing in the ordinary course on the unopposed motion roll for 14 May 2024. On 09 May 2024, the respondents delivered a Notice of Intention to Oppose the above application and on 20 May 2024, the 1st – 3rd respondents filed their answering affidavit.
[17] The 1st – 3rd respondents premised their opposition to this application on the following:
(i) The applicant failing to make out a case for the relief sought;
(ii) the award that the applicant sought to make an order of court being a nullity. This is averred in circumstances where the respondents submited that the arbitration proceedings lapsed prior to the purported award having been made;
(iii) the award if not a nullity falling to be reviewed and set aside in terms of Section 33 of the Arbitration Act.[11]
[18] The aforesaid allegations raised on behalf of the 1st – 3rd respondents and in alleging that the award made on 16 August 2023 is unenforceable are when reconciled with the above factual circumstances and chronology, irreconcilable and unsustainable. In this regard, upon resorting to and convening the arbitration and with that, agreeing the modus operandi of the arbitration process in the minuted First Pre-Arbitration meeting held on 14 January 2021, the parties expressly agreed to waive the requirements of Section 23 of the Arbitration Act and with that, the enforcement of specific time limits attributed to the arbitration.
[19] Further and as evinced in the above chronology, prior to the service of the 1st – 3rd respondents’ answering affidavit; no reference was ever made on the part of the 1st – 3rd respondents regarding the award being a nullity and delivered out of time. This allegation on the part of the 1st – 3rd respondents is actually a very late afterthought creatively conceived of in attempting evading accountability vis-à-vis the arbitration award and is best described as being disingenuous and unsustainable. When presented with the proposed time limits in which the Arbitrator envisaged delivering her award and as summarized in the chronology above, the respondents raised no objection. Further, the respondents assured the Arbitrator that they had sufficient funds to pay the Arbitrator’s fees upon delivery of the award and this then begs the question, if the award was void ab initio, why then would the respondents pay the Arbitrator for the production of the award?
[20] On the issue of the intended review of the award made, this was initially referenced on the part of the respondents back on 19 September 2023. However, no review application has in the interim been resorted to. In any event, a review of an arbitral award does not stay the actual enforcement of the award.
[21] Reference was also made on behalf of the respondents regarding the making of the arbitrator’s award an order of court, being against public policy. The respondents do not elaborate hereon and in the process adduce reasons and facts in support of this bald assertion. I construe there being no factual and legal impediment to the arbitrator’s above award being made an order of court and nothing contained in the 1st – 3rd respondents’ Answering Affidavit convinces me to the contrary. What is clearly apparent from the respondents’ above conduct is that there is a deliberate attempt afoot to evade accountability, including in effecting payment of the award and with that, in attempting to delay and frustrate the applicant in enforcing the award and making it an order of this Honourable Court. The allegations made on behalf of the respondents and as summarized in paragraph 17 above are best described as being creative and completely out of sync with the above chronology of the matter and arbitration.
[22] Bearing in mind that the dispute was declared on 01 December 2020, the First Pre-Arbitration meeting held on 14 January 2021 and whereupon the actual arbitration proceedings were ongoing over the period 04 July 2022 - 02 June 2023; the ensuing delivery of an award three months hence and on 16 August 2023 is certainly not unreasonable and is consistent with that agreed in the above First Pre-Arbitration meeting and again per the chronology duly accepted by the parties.
[23] The award is valid and stands to be made an Order of Court and thereupon duly enforced.
[24] Post the publication of the award, the 1st – 3rd respondents enjoyed ample time in which to consider their legal and commercial options, constructively engage with the applicant and with that, put in place arrangements on the payment of the award. What is disconcerting here is that the 1st – 3rd respondents have not chosen to proceed on a mature basis and as above. Instead, they have failed to honour the award, thus placing
themselves in breach and with that engaged in an attrition, forcing the applicant to have to resort in bringing this application. I accordingly and in noting this Court’s disapproval of the above conduct, award a special order as to costs against the 1st – 3rd respondents on the attorney and own client scale and including the costs of legal counsel on Scale C.
ORDER
Accordingly. I make the following order:
MEADEN
J R
ACTING
JUDGE OF THE HIGH COURT
This Judgment was handed down electronically by circulation to the parties’ and or parties’ representatives by email and by being uploaded to CaseLines. The date and time for the hand down is deemed to be 13h00 on this 19th day of December 2024
Appearances
For Applicant: Adv. LG Minné Instructed by: Bowmans Gilfillan Inc. For 1st – 3rd Respondents: Adv. R Raubenheimer Instructed by: Willemse Potgieter & Babinszky Inc. For 4th & 5th Respondents: No Appearance Instructed by: Anderson-Kriel Attorneys Date of Hearing: 04 November 2024 Date of Judgment: 19 December 2024
[1] 02-52.
[2] 02-6-48. The actual award is set out at 02-47-48 of the Court Bundle.
[3] 02-150.
[4] 02-151.
[5] Annexure RZS3 02-108/109.
[6] 02-203.
[7] RZS14 02-211.
[8] RZS15 02-214.
[9] RZS18 02-223.
[10] RZS19 02-227.
[11] 02-120.
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.