Download PDF

South Africa Judgment

North Gauteng High Court, Pretoria

Akani Building Solutions (Pty) Limited v Lebo Tebo Trading and Projects CC (2024-033125) [2025] ZAGPPHC 781 (1 August 2025)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the respondent's indebtedness to the applicant was disputed on bona fide and reasonable grounds. The respondent provided sufficient factual allegations that, if proved at trial, would constitute a good defence to the applicant's claim. The applicant impermissibly attempted to broaden its claim in reply, which was not the case the respondent was called to meet. The Badenhorst rule applies, and winding-up proceedings are not appropriate for enforcing a debt that is genuinely disputed. There was no evidence of lack of bona fides on the respondent's part. The application for liquidation was therefore dismissed, and costs were awarded to the respondent, including the costs of two counsel, given the seriousness of the matter.

Court disposition

Application for liquidation dismissed; costs awarded to respondent, including costs of two counsel.

Orders

  • The liquidation application is dismissed.
  • The applicant is ordered to pay the costs occasioned by the application on scale C, including those occasioned by the employment of two counsel.

02

Material facts

Parties

Akani Building Solutions (Pty) Limited

Applicant Counsel: C Shongwe

Lebo Tebo Trading and Projects CC

Respondent Counsel: E Mokutu SC

Amounts and remedies

  • Contract Value (incl. Vat): ZAR 1,959,222.32
  • Applicant's Claim (final Amount): ZAR 759,249.76

03

Procedural history

  1. Posture

    Liquidation Application / Hearing and Judgment

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant contended that it was appointed as a sub-contractor by the respondent to provide sanitation facilities at Mosesane Baloyi Primary School for a contract value of R1,959,222.32. It alleged that it completed the works and issued two invoices, which remain unpaid, amounting to R759,249.76. The applicant relied on certificates of practical completion, progress reports, and email correspondence to support its claim. In reply, the applicant attempted to broaden its claim to include additional site instructions, arguing that these accounted for the total amount owed.
Respondent
The respondent admitted the contractual relationship but denied that the applicant completed the works, alleging abandonment or incomplete performance. It stated that other sub-contractors were appointed to finish the work. The respondent conceded practical completion but attributed it to the efforts of other sub-contractors. It referred to a snag list and correspondence with the project funder highlighting the applicant's failure. The respondent argued that the applicant's claim was disputed on bona fide and reasonable grounds.

05

Court’s reasoning

  1. 01

    Freshvest Investments (Pty) Ltd v Marabeng (Pty) Ltd (1030/2015) [2016] ZASCA 168 (24 November 2016); Badenhorst v Northern Construction Enterprises (Pty) Ltd 1956 (2) SA 346 (T); Kalil v Decotex (Pty) Ltd and another 1998 (1) SA 943 (A)

    Winding-up proceedings are not appropriate for enforcing a debt that is disputed on bona fide and reasonable grounds (the Badenhorst rule).

  2. 02

    Hülse-Reutter and Another v HEG Consulting Enterprises (Pty) Ltd (Lane and Fey NNO Intervening) 1998 (2) SA 208 (C)

    A respondent in liquidation proceedings need only allege facts which, if proved at trial, would constitute a good defence to the claim; it is not required to prove its defence on affidavit.

  3. 03

    Swissborough Diamond Mines (Pty) Ltd and Others v Government of the Republic of South Africa and Others 1992 (2) SA 279 (T); Lipschitz and Schwartz NNO v Markowitz 1976 (3) SA 772 (W)

    A party cannot broaden its claim in reply beyond what was pleaded in the founding affidavit; reliance on annexures without identifying relevant portions is impermissible.

  4. 04

    Pride Milling Co (Pty) Ltd v Bekker NO and Another 2022 (2) SA 410 (SCA)

    Costs of two counsel may be awarded where the matter has far-reaching commercial consequences and such employment is reasonable.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the respondent's indebtedness to the applicant was disputed on bona fide and reasonable grounds. The respondent provided sufficient factual allegations that, if proved at trial, would constitute a good defence to the applicant's claim. The applicant impermissibly attempted to broaden its claim in reply, which was not the case the respondent was called to meet. The Badenhorst rule applies, and winding-up proceedings are not appropriate for enforcing a debt that is genuinely disputed. There was no evidence of lack of bona fides on the respondent's part. The application for liquidation was therefore dismissed, and costs were awarded to the respondent, including the costs of two counsel, given the seriousness of the matter.

Obiter and limits

  • A lack of bona fides is not readily inferred, and the respondent raised its disputes long before the liquidation application was issued.
  • The attempt to rely on annexures to broaden the scope of the applicant's claim without identifying relevant portions is impermissible.
  • The employment of two counsel by the respondent was reasonable given the potential commercial consequences of liquidation.

Court disposition

Application for liquidation dismissed; costs awarded to respondent, including costs of two counsel.

  • The liquidation application is dismissed.
  • The applicant is ordered to pay the costs occasioned by the application on scale C, including those occasioned by the employment of two counsel.

Source and reliance status

North Gauteng High Court, Pretoria

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North Gauteng High Court, Pretoria

Judgment

[2025] ZAGPPHC 781

REPUBLIC OF SOUTH

AFRICA

IN THE HIGH COURT OF

SOUTH AFRICA

GAUTENG DIVISION,

PRETORIA

Case Number: 2024 – 033125

(1) REPORTABLE: NO

(2) OF INTEREST TO OTHER JUDGES: NO

(3) REVISED: YES

DATE 1 August 2025

SIGNATURE

In the matter between:

AKANI BUILDING SOLUTIONS (PTY) LIMITED

Applicant

and

LEBO

TEBO TRADING AND PROJECTS CC

Respondent

[ Registration number: 2008/237123/23 ]

[ For its liquidation ]

JUDGMENT

J Vorster, AJ.

[1] The applicant seeks an order for the respondent’s liquidation. It relies on the provisions of section 69 of the Close Corporations Act, 69 of 1984, read with Schedule 3 to the Companies Act, 71 of 2008, and section 344 of the Companies Act, 61 of 1973.

[2] The relationship between the parties is contractual in nature. It is common cause that the respondent was appointed by the Department of Education in the Limpopo Province to render services at the Mosesane Baloyi Primary School, and that it appointed the applicant as its sub-contractor in terms of a written appointment letter dated 14 October 2022, for the provision of sanitation facilities. The contract value was R1,959,222.32 (incl. VAT), and works were expected to be completed by 31 January 2023.

[3] According to the applicant, the works assigned to it were completed, but the respondent failed to pay an amount of R759,249.76.[1]

[4] When the application was argued, I raised a concern about the fact that the Certificate of Tendered Security was issued on 30 April 2025, a date more than 10 days before the application came before me. In this regard, section 346(3), in relevant part, provides:

“every application to the Court referred to in subsection (1), … shall be accompanied by a certificate by the Master, issued not more than ten days before the date of the application, to the effect that sufficient security has been given for the payment of all fees and charges necessary for the prosecution of all winding-up proceedings and of all costs of administering the company in liquidation until a provisional liquidator has been appointed, or, if no provisional liquidator is appointed, of all fees and charges necessary for the discharge of the company from the winding-up.”

[5] However, having considered the judgments in De Wet NO v Mandelie (Edms) Bpk,[2] and Mafeking Creamery Bpk v Mamba Boerdery (Edms) Bpk,[3] I conclude that: (i.) the date of the application is the date on which the application is issued; and (ii.) it is not essential that the certificate be dated before the date of the application. In fact, it need not, at that date, actually exist. All that is required is that security must have been given before the matter is heard and that the security certificate must accompany the application when it is heard.[4]

[6] Turning to the merits of the application, the case advanced in the applicant’s founding affidavit, where all the essential evidence to support its case must appear,[5] is fairly straightforward. It alleges that subsequent to its common cause appointment as the respondent’s sub-contractor, it completed the works and issued two invoices respectively dated 5 and 13 June 2023, which remain unpaid. It further claims that evidence of its completion of the sub-contracted works is to be found in: (i.) a certificate of practical completion issued by the Limpopo Provincial Department of Education on 3 May 2023; (ii.) a progress report dated 10 May 2023; and (ii.) email correspondence from the project manager, Mr Khuzwayo of TKQ Consulting, dated 2 November 2023, which inter alia refers to the fact that the works were completed.

[7] In its answering affidavit, the respondent admits its contractual relationship with the applicant, but denies that the applicant completed the works. The respondent explains that the applicant failed to complete the works, or abandoned the works. The result was that the respondent had to appoint other sub-contractors to complete the works. The answering affidavit specifically refers to the appointment of the following sub-contractors who, according to the respondent, had to complete work for which the applicant was responsible: (i.) Dusta General Services; (ii.) Rand Industrial and Mining Supplies; (iii.) Mapitsana Logistics and Projects; (iv.) BWT; and (v.) Dominium Safety.

[8] Further, the respondent concedes that the project achieved practical completion, but it says that it was as a result of work performed by other sub-contractors, and not due to the applicant’s efforts. It refers to a snag list of outstanding work that the applicant failed to complete, and to an email addressed to the funder of the project, the Development Bank of Southern Africa, dated 2 November 2023, in which it made mention of the applicant’s failure.

[9] In reply, the applicant contends that the work undertaken by the sub-contractors referred to in paragraph [7] above had nothing to do with the work contractually assigned to it. It also refers to the so-called snag list and claims, with reference to colour photos, that the work on the snag list was completed.

[10] In respect of the scope of the work to be undertaken, in its replying affidavit the applicant impermissibly attempts to broaden the ambit of its claim. Whereas in the founding affidavit the applicant simply relied on the terms of the appointment letter, the replying affidavit suggests that the scope of work was extended “through site instructions”. Paragraph 12 of the replying affidavit explains the position as follows:

“As it would appear clearer below, the applicant was given several site instructions to carry out while it was performing in terms of the contract on site. These instructions are indicated as such on page 7 of the progress report attached as annexure ‘’A3’’

to the applicant’s founding affidavit. I will attach further written confirmation of these instructions later in this affidavit.

Resultantly, it is the carrying out of these site instructions that accounts for the total amount that the respondent is indebted to the applicant.”

[11] First, this is not the case the respondent was called to meet when it filed its answering affidavit. The founding affidavit contains no express reference to site instructions or an increase to the value of the contract.

[12] Second, to the extent that the progress report, which is an annexure to the founding affidavit, refers to site instructions, the founding affidavit itself makes no mention of these site instructions. The stated purpose for which the progress report was annexed to the founding affidavit was to confirm that the works had been completed. In this regard, the court in Swissborough Diamond Mines (Pty) Ltd and Others v Government of the Republic of South Africa and Others,[6] made the following apposite remarks concerning annexures to an affidavit:

“Regard being had to the function of affidavits, it is not open to an applicant or a respondent to simply annex to its affidavit

documentation and to request the Court to have regard to it. What is required is the identification of the portions thereon on which reliance is placed and an indication of the case which is sought to be made out on the strength thereof. If this were not so the essence of our established practice would be destroyed. A party would not know which case must be met.”

[13] Similarly, in Lipschitz and Schwartz NNO v Markowitz,[7] the court made the following comment concerning this issue:

“A litigant cannot, as it were, throw a mass of material contained in the record of an enquiry at the Court and his opponent, and merely invite them to read it so as to discover for themselves some cause of action which might lurk therein, without identifying it. If this were permissible, the essence of our established practice which is designed and which still evolves as a means of accurately identifying issues and conflicts so that the Court and the litigants should be properly apprised of the relevant conflicts, would be destroyed.”

[14] I align myself with the quoted findings, and conclude that the attempt to rely on the progress report to broaden the scope of the applicant’s claim is in my view impermissible.

[15] When asked during argument whether the applicant could have dealt with the issues raised in its replying affidavit, in its founding affidavit (so as to afford the respondent an opportunity to engage with the issues), Mr Shongwe, who appeared for the applicant, submitted that the issues were unforeseen when the founding affidavit was prepared. Although this submission may be correct in respect of the appointment of other contractors (on which I express no firm view), it is not correct in respect of the site instructions as the applicant was clearly aware that its claim was, at least in part, based on additional work.

[16] In argument the applicant urged me to “go deeper” and to critically evaluate the defences advanced by the respondent. It further suggested that the defences were unreasonable.

[17] It is, however, not open for me to critically interrogate the respondent’s defence. The respondent simply had to allege facts which, if proved at a trial would constitute a good defence to the claims made against the company.

[18] I am in all the circumstances satisfied that the respondent succeeded in establishing that its indebtedness to the applicant is disputed on bona fide and reasonable grounds. In Freshvest Investments (Pty) Ltd v Marabeng (Pty) Ltd,[8] the Supreme Court of Appeal found:

‘This is an appeal, with the leave of the court a quo, against the dismissal of an application for the winding-up of the respondent,

Marabeng (Pty) Ltd. in essence, the matter serves as a stark reminder that winding-up proceedings are not designed for the enforcement of a debt that the debtor-company disputes on bona fide and reasonable grounds. This has become known as the “Badenhorst rule” after Badenhorst v Northern Construction Enterprises (Pty) Ltd 1956 (2) SA 346 (T) at 347-348. See also Kalil v Decotex (Pty) Ltd and another 1998 (1) SA 943 (A) at 980B-D, as well as the authorities referred to in Kalil at 980D-F. A collection of more recent authorities on the application of the Badenhorst rule is found in PM Meskin et el Henochsberg on the Companies Act 5 ed Vol 1 at 693—694.’

[19] I further respectfully agree with the below passage in ABSA Bank Ltd v Erf 1252 Marine Drive (Pty) Ltd.[9] There, Binns-Ward J, said the following:

“I am hesitant to accept the notion that the Badenhorst rule goes to standing. After all, as Corbett JA observed in Kalil v Decotex supra, at 980, it is conceivable that a creditor could establish on a balance of probabilities that it had a claim against the respondent company in winding-up proceedings, while the respondent at the same time was able to establish that the claim was disputed on bona fide and reasonable grounds. The applicant in such a case would have established its standing, while the respondent would have established, irrespective of the merits of the claim or its defence to it, that the remedy sought by the applicant should not be granted. The Badenhorst rule would thus seem to constitute a selfstanding (and possibly flexible) principle that winding-up proceedings are not an appropriate procedure for a creditor to use when the debt is bona fide disputed. Availment of the procedure in circumstances in which the Badenhorst rule applies can be an abuse of process. It is so, however, only when the creditor knew, or should reasonably have foreseen that the debt was disputed on bona fide and reasonable grounds at the time of the institution of the proceedings.”

[20] In Hülse - Reutter and Another v HEG Consulting Enterprises (Pty) Ltd (Lane and Fey NNO Intervening),[10] Thring, J. said the following with regard to what a respondent must show to demonstrate in winding-up proceedings that a creditor-applicant’s claim is reasonably disputed:

“Apart from the fact that they dispute the applicant’s claims, and do so bona fide, ... what they must establish is no more and no less than that the grounds on which they do so are reasonable. They do not have to establish, even on the probabilities, that the company, under their direction, will, as a matter of fact, succeed in any action which might be brought against it by the applicants to enforce their disputed claims. They do not ... have to prove the company’s defence in any such proceedings. All they have to satisfy me of is that the grounds which they advance for their claims and the company’s disputing these claims are not unreasonable. To do that, I do not think that it is necessary for them to adduce on affidavit, or otherwise, the actual evidence on which they would rely at such trial. This is not an application for summary judgment in which ... a defendant who resists such an application by delivering an affidavit or affidavits must not only satisfy the Court that he has a bona fide defence to the action, but in terms of the Rule must also disclose fully in his affidavit or affidavits “the material facts relied upon therefor”... It seems to me to be sufficient for the [respondents] in the present application, as long as they do so bona fide, ... to allege facts which, if proved at a trial would constitute a good defence to the claims made against the

company.”

[21] A lack of bona fides is not readily inferred (see: Robsen v Wax Works (Pty) Ltd and Others[11]), and there is nothing on the papers which leads me to conclude that the respondent does not genuinely dispute the applicant’s

claim. It raised the disputes it is now relying on in November 2023, long before the liquidation application was issued. The respondent

has satisfied me that the grounds which they advance for disputing the applicant’s claim are not unreasonable. It has alleged

facts which, if proved at a trial, would constitute a good defence to the claim made against it. My conclusion that the respondent has succeeded in establishing that its indebtedness to the association is disputed on bona fide and reasonable grounds, renders it unnecessary to decide the question whether the respondent is able to pay its debts.

[22] What remains to consider is the question of liability for costs. The usual order is that the successful party is awarded its costs. I find no reason to deviate from the usual order.

[23] The respondent employed two counsel and during argument it was submitted that the costs of two counsel were reasonably incurred. I agree. The respondent faced an order for its liquidation. Such an order has far-reaching commercial consequences and under the prevailing circumstances the employment of two counsel cannot be said to have been overcautious or luxurious. It was a wise and reasonable precaution on the part of the respondent.[12]

[24] As a result, the following order is made:

[24.1] The liquidation application is dismissed.

[24.2] The applicant is ordered to pay the costs occasioned by the application on scale C, such costs to include those occasioned by the employment of two counsel (where so employed).

J VORSTER, AJ

Acting Judge of the High Court

Date heard: 28 July 2025.

Judgment date: 1 August 2025.

Appearances:

For the applicant:

Counsel: C Shongwe

Instructed by: Mashiane, Moodley & Minama Attorneys (Sandton)

For the respondent:

Counsel: E Mokutu SC

(heads of argument by E Mokutu SC and M Moflogelwa)

Instructed by: Kotzé Low Swanepoel Attorneys (Vryburg)

[1] In the founding affidavit the claim was said to be R790,272.95. In reply, the applicant stated that it had made a mathematical mistake when adding the value of two outstanding invoice together, and reduced its claim to R759,249.76.

[2] 1983 (1) SA 544 (T) at 545 - 546

[3] 1980 (2) SA 776 (NC) at 782.

[4] Court v Standard Bank of SA Ltd; Court v Bester NO and Others [1995] ZASCA 39; 1995 (3) SA 123 (A) at 131B - C.

[5] Director of Hospital Services v Mistry 1979 (1) SA 626 (A) at 653H - 636B; Botha v Smuts 2025 (1) SA 345 (CC) at [58].

[6] 1992 (2) SA 279 (T) at 324F-H.

[7] 1976 (3) SA 772 (W) at 117H – 776A.

[8] (1030/2015) [2016] ZASCA 168 (24 November 2016), para. 1.

[9] [2012] ZAWCHC 43 (15 May 2012) para. 25.

[10] 1998 (2) SA 208 (C) at 219F-220A.

[11] 2001 (3) SA 1117 (C) at para. 15.

[12] Pride Milling Co (Pty) Ltd v Bekker NO and Another 2022 (2) SA 410 (SCA) at 424 [40].

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

De Wet NO v Mandelie (Edms) Bpk 1983 (1) SA 544 (T)

Case cited

Mafeking Creamery Bpk v Mamba Boerdery (Edms) Bpk 1980 (2) SA 776 (NC)

Case cited

Court v Standard Bank of SA Ltd; Court v Bester NO and Others [1995] ZASCA 39; 1995 (3) SA 123 (A)

Case cited

Director of Hospital Services v Mistry 1979 (1) SA 626 (A)

Case cited

Botha v Smuts 2025 (1) SA 345 (CC)

Case cited

Swissborough Diamond Mines (Pty) Ltd and Others v Government of the Republic of South Africa and Others 1992 (2) SA 279 (T)

Case cited

Lipschitz and Schwartz NNO v Markowitz 1976 (3) SA 772 (W)

Case cited

Freshvest Investments (Pty) Ltd v Marabeng (Pty) Ltd (1030/2015) [2016] ZASCA 168 (24 November 2016)

Case cited

ABSA Bank Ltd v Erf 1252 Marine Drive (Pty) Ltd [2012] ZAWCHC 43 (15 May 2012)

Case cited

Hülse-Reutter and Another v HEG Consulting Enterprises (Pty) Ltd (Lane and Fey NNO Intervening) 1998 (2) SA 208 (C)

Case cited

Robsen v Wax Works (Pty) Ltd and Others 2001 (3) SA 1117 (C)

Case cited

Pride Milling Co (Pty) Ltd v Bekker NO and Another 2022 (2) SA 410 (SCA)

Case cited

Close Corporations Act 69 of 1984

Legislation

Legislation referenced in the available case record.

Companies Act 71 of 2008

Legislation

Legislation referenced in the available case record.

Companies Act 61 of 1973

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.