Amakhala Emoyeni Re Project 1 (RF) (Pty) Ltd v Nordex Energy South African (RF) (Pty) Ltd and Others (20035/2024) [2025] ZAWCHC 164 (8 April 2025)

Amakhala Emoyeni Re Project 1 (RF) (Pty) Ltd v Nordex Energy South African (RF) (Pty) Ltd and Others (20035/2024) [2025] ZAWCHC 164 (8 April 2025)

The court found that the applicant was not entitled to the amended declaratory relief sought, as the purported agreement to refer all disputes to arbitration constituted a variation of the EPC Contract, which required written and signed agreement by both parties under clause 37.11. No such signed variation existed....

Source-derived case information.

Citation
[2025] ZAWCHC 164
Parties
Applicant: Amakhala Emoyeni RE Project 1 (RF) (Pty) Ltd; Respondent: Nordex Energy South African (RF) (Pty) Ltd; Respondent: Engineering Council of South Africa; Respondent: Refilwe Buthelezi N.O
Court
Western Cape High Court, Cape Town
Jurisdiction
South Africa
Case Number
20035/2024
Procedural Posture
Civil Application / Judgment After Opposed Application for Declaratory Relief and Amendment
Outcome
Application for amended declaratory relief refused; main application dismissed; leave to amend granted; costs apportioned as per order.
Judges
L G Nuku
Legal Topics
Arbitration Agreement, Contract Variation, Declaratory Relief, Costs Order, Fast Track Dispute Resolution
Commercial and Corporate Civil Procedure Arbitration Agreement Contract Variation Declaratory Relief Costs Order Fast Track Dispute Resolution

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Amakhala Emoyeni RE Project 1 (RF) (Pty) Ltd

Applicant

Nordex Energy South African (RF) (Pty) Ltd

Respondent

Engineering Council of South Africa

Respondent

Refilwe Buthelezi N.O

Respondent

Procedural Posture

Civil Application / Judgment After Opposed Application for Declaratory Relief and Amendment

  1. 1 Whether the applicant is entitled to request ECSA to nominate an alternative independent expert under the EPC Contract.
  2. 2 Whether the applicant is entitled to declaratory relief amending the dispute resolution regime prescribed by the EPC Contract.
  3. 3 Whether the applicant's non-compliance with Rule 28(1) should be condoned and leave to amend granted.

Ratio Decidendi

The court found that the applicant was not entitled to the amended declaratory relief sought, as the purported agreement to refer all disputes to arbitration constituted a variation of the EPC Contract, which required written and signed agreement by both parties under clause 37.11. No such signed variation existed. Furthermore, there was disagreement between the parties regarding the existence of the alleged agreement, and the court cannot create or enforce a contract for the parties. The applicant's non-compliance with Rule 28(1) was condoned by agreement, and leave to amend was granted. The first respondent's tender to accept the jurisdiction of the arbitrator if the applicant refers...

Court Disposition

Application for amended declaratory relief refused; main application dismissed; leave to amend granted; costs apportioned as per order.

Orders

  • The applicant’s non-compliance with Rule 28(1) is condoned and leave to amend its notice of motion is granted.
  • The applicant’s main relief (as amended) and alternative relief are refused, and the main application is dismissed.