Asla Construction (Pty) Limited v Buffalo City Metropolitan Municipality and Another (894/2016) [2017] ZASCA 23; [2017] 2 All SA 677 (SCA); 2017 (6) SA 360 (SCA) (24 March 2017)

Asla Construction (Pty) Limited v Buffalo City Metropolitan Municipality and Another (894/2016) [2017] ZASCA 23; [2017] 2 All SA 677 (SCA); 2017 (6) SA 360 (SCA) (24 March 2017)

The Supreme Court of Appeal held that the respondent failed to bring its review application within the 180-day period prescribed by section 7 of PAJA and did not provide a full and reasonable explanation for the entire duration of the delay. The respondent's contention that the time period only commenced upon actual...

Source-derived case information.

Citation
[2017] ZASCA 23
Parties
Appellant: Asla Construction (Pty) Limited; Respondent: Buffalo City Metropolitan Municipality; Amicus Curiae: The South African Civics Organisation
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Case Number
894/2016
Procedural Posture
Civil Appeal / Appeal From Eastern Cape Division of the High Court, Grahamstown
Outcome
Appeal upheld; order of the court a quo set aside and replaced.
Judges
Ponnan, Cachalia, Swain, Dambuza, Gorven
Legal Topics
Promotion of Administrative Justice Act, Unreasonable Delay, Condonation, Public Procurement, Section 217 Constitution, Prejudice and Finality
Administrative Law Civil Procedure Promotion of Administrative Justice Act Unreasonable Delay Condonation Public Procurement Section 217 Constitution Prejudice and Finality

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 13 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Asla Construction (Pty) Limited

Appellant

Buffalo City Metropolitan Municipality

Respondent

The South African Civics Organisation

Amicus Curiae

Procedural Posture

Civil Appeal / Appeal From Eastern Cape Division of the High Court, Grahamstown

  1. 1 Whether the respondent's application to review and set aside the Reeston contract was brought within the statutory period prescribed by section 7 of PAJA.
  2. 2 Whether the respondent furnished a full and reasonable explanation for the delay in bringing the review application.
  3. 3 Whether the interests of justice justified an extension of the 180-day period under section 9 of PAJA.

Ratio Decidendi

The Supreme Court of Appeal held that the respondent failed to bring its review application within the 180-day period prescribed by section 7 of PAJA and did not provide a full and reasonable explanation for the entire duration of the delay. The respondent's contention that the time period only commenced upon actual knowledge of irregularities was rejected, as the reasons for the administrative action were always within its knowledge. The respondent did not make a substantive application for extension under section 9 of PAJA, and the court a quo erred by deciding the merits of the review before considering condonation. The prejudice to the appellant and the community was substantial, as...

Court Disposition

Appeal upheld; order of the court a quo set aside and replaced.

Orders

  • The appeal succeeds with costs, including costs of two counsel.
  • In case number 5246/2015: The defendant is ordered to pay the plaintiff's costs, including costs of two counsel where employed.