Download PDF

South Africa Judgment

North Gauteng High Court, Pretoria

Avgold Limited and Another v Minister of Water and Sanitation and Others (039650 /2023) [2023] ZAGPPHC 1892 (27 October 2023)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the Directive issued by the Department of Water and Sanitation was procedurally unfair, as the applicants were not informed of the true reasons for its issuance and were not afforded a reasonable opportunity to make representations. The urgency of the matter was established when the respondents refused to extend the compliance period, and the applicants demonstrated that immediate compliance would result in severe and disproportionate harm, including flooding of the mine, health and safety risks, cessation of mining operations, and mass retrenchments. The court held that the requirements for an urgent interim interdict were met and that the suspension of the Directive was justified to prevent irreparable harm and allow the applicants to cure the unlawful conduct pending the outcome of their appeal.

Court disposition

Interim interdict granted; operation of the Directive suspended pending appeal or until 30 June 2023, whichever occurs first.

Orders

  • The operation of the Directive issued by the second respondent to the first applicant dated 30 March 2023 is suspended until and including 30 June 2023, alternatively until the appeal lodged by the applicants to the Water Tribunal under section 148(1)(a) and (j) of the National Water Act, 36 of 1998 has been finally determined, whichever occurs first.
  • The respondents who opposed this application shall pay the costs of this application jointly and severally, the one paying the other/s to be absolved, including the cost of two counsel.

02

Material facts

Parties

Avgold Limited

Applicant Counsel: Adv. M Mantrobus SC

Harmony Gold Mining Company Limited

Applicant Counsel: Adv. I Nongogo

Minister of Water and Sanitation

Respondent Counsel: Adv. Ramatsekisa

Director-General Department of Water and Sanitation

Respondent

Provincial Head, Free State Department of Water and Sanitation

Respondent

Director: Compliance and Enforcement for the Free State

Respondent

Amounts and remedies

  • Number of Employees at Risk of Retrenchment: 2,225
  • Maximum Authorised Water Discharge Per Month (historical Exemption): MI 140
  • Average Monthly Discharge During Rainy Season (nov 2021 May 2022): MI 80
  • Average Monthly Discharge (nov 2022 Mar 2023): MI 46.5
  • Annual Rainfall in Region (recent Period): mm 923
  • Regional Average Rainfall (historical): mm 587

03

Procedural history

  1. Posture

    Urgent Application / Interim Interdict Application

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicants argued that the Directive was issued without procedural fairness, as they were not informed of the true reasons for its issuance and were not given a reasonable opportunity to make representations. They contended that immediate compliance would result in catastrophic consequences, including flooding of the mine, health and safety risks, cessation of mining activities, and mass retrenchments. They submitted that the urgency arose when their request for an extension was refused and that the requirements for an interim interdict were met.
Respondent
The respondents opposed the application, arguing that the matter was not urgent and that any urgency was self-created by the applicants. They maintained that the applicants had failed to meet the requirements for an interim interdict and that the discharge of water into Voelpan was unlawful and continued to cause harm to surrounding communities and infrastructure.

05

Court’s reasoning

  1. 01

    Minister of Public Works v Kyalami Ridge Environmental Association 2001 7 BCLR 652 (CC) para 101

    Procedural fairness requires that an administrative functionary must have an open mind and a complete picture of the facts and circumstances before taking administrative action.

  2. 02

    National Water Act, 36 of 1998

    An appeal in terms of section 148(2) of the National Water Act does not suspend the operation of a Directive.

  3. 03

    Mogalakwena Local Municipality v Provincial executive council Limpopo & others case no: 35248/14

    Courts may suspend the operation of an order requiring cessation of unlawful conduct to prevent serious adverse consequences and allow the conduct to be cured.

  4. 04

    Luna Meubel Vervaardigers v Makin 1977 (4) SA 135 (W)

    Requirements for an interim interdict include urgency, a prima facie right, irreparable harm, and the balance of convenience.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the Directive issued by the Department of Water and Sanitation was procedurally unfair, as the applicants were not informed of the true reasons for its issuance and were not afforded a reasonable opportunity to make representations. The urgency of the matter was established when the respondents refused to extend the compliance period, and the applicants demonstrated that immediate compliance would result in severe and disproportionate harm, including flooding of the mine, health and safety risks, cessation of mining operations, and mass retrenchments. The court held that the requirements for an urgent interim interdict were met and that the suspension of the Directive was justified to prevent irreparable harm and allow the applicants to cure the unlawful conduct pending the outcome of their appeal.

Obiter and limits

  • The affected households have already been relocated or will soon be relocated, mitigating the impact of rising water levels in Voelpan.
  • Measures undertaken by the applicants will ensure that no further discharge occurs after 30 June 2023, preventing further harm.
  • The principle of procedural fairness is inherent in the Bill of Rights and must be observed in all administrative actions.
  • The court previously granted a similar order in June 2023, confirming the appropriateness of suspending the Directive.

Court disposition

Interim interdict granted; operation of the Directive suspended pending appeal or until 30 June 2023, whichever occurs first.

  • The operation of the Directive issued by the second respondent to the first applicant dated 30 March 2023 is suspended until and including 30 June 2023, alternatively until the appeal lodged by the applicants to the Water Tribunal under section 148(1)(a) and (j) of the National Water Act, 36 of 1998 has been finally determined, whichever occurs first.
  • The respondents who opposed this application shall pay the costs of this application jointly and severally, the one paying the other/s to be absolved, including the cost of two counsel.

Source and reliance status

North Gauteng High Court, Pretoria

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North Gauteng High Court, Pretoria

Judgment

[2023] ZAGPPHC 1892

HIGH

COURT OF SOUTH AFRICA

(GAUTENG DIVISION, PRETORIA)

CASE NO:039650 /2023

(1) REPORTABLE: YES/NO

(2)

OF INTEREST TO OTHERS JUDGES: YES/NO

(3)

REVISED

DATE: 8/11/2023

SIGNATURE

In the matter between:

AVGOLD

LIMITED

First Applicant

HARMONY

GOLD MINING COMPANY LIMITED

Second Applicant

and

MINISTER

OF WATER AND SANITATION

First Respondent

DIRECTOR-GENERAL

DEPARTMENT

OF

WATER AND SANITATION

Second Respondent

PROVINCIAL HEAD, FREE STATE

Third Respondent

DEPARTMENT

OF WATER AND SANITATION

DIRECTOR: COMPLIANCE AND ENFORCEMENT Fourth Respondent

FOR

THE FREE STATE

JUDGEMENT

RAULINGA, J

This matter has been heard in open court and is otherwise disposed of in terms of the Directives of the Judge President of this Division. The judgment is accordingly published and distributed electronically.

Introduction

[1] This is an application brought by the applicants on an urgent basis for an interim interdict.

Background

[2] The applicants submit that the application is urgent since it meets the requirements set out in Rule 6(5)(b) as further communicated in the leading case of Luna Meubel Vervaardigers v Makin 1977 (4) SA 135 (W), and other relevant cases.

[3] The respondents oppose the application and contend that the matter is not urgent, and the urgency is self-created.

[4] The respondents contended further that the applicants failed to meet the requirements necessary for granting of the interim interdict.

[5] In September 2022, the Department of Water and Sanitation (DWS), Free State Provincial Office received a complaint that the applicants (Harmony); Target Operations situated near the town of Allanridge was discharging water into the Voelpan Dam. Following receipt of the complaints, an officer of DWS, contacted Harmony to enquire if they are aware of the discharge. Harmony acknowledged the discharge into the Voelpan and presented a mitigation plan to DWS including measures to be implemented to stop the discharge.

[6] On 20th October 2022, a site inspection was conducted with Harmony officials, and it was observed that there was an overflow from Harmony into the Voelpan. This resulted in DWS issuing a Notice of Intention to issue a Directive (pre-directive) dated 14 November 2022 to Harmony for the unauthorised discharge into Voelpan and its possible pollution to the dam. Consequently, Harmony submitted a

representation. According to the representation submitted in response to the Notice issued to Harmony in November 2022, they acknowledged

water having been discharged into the Voelpan from 2019 without informing DWS or without authorisation which is a contravention of the National Water Act, 36 of 1998 (NWA)

[7] This resulted in the issuance of the Directive dated 30 March 2023. Following receipt of the Directive, Harmony submitted a request to DWS for extension of the deadline to comply with the Directive. DWS rejected the request citing the unlawful discharge into Voelpan and flooding in which the rising water levels has caused and continues to

cause the Allanridge /Nyakallong communities and the R30 road.

[8] Avgold owns and operates the Target Operations (“Target Mine”) a technologically advanced deep-level mine in the Free State, approximately 270m Sout-West of Johannesburg.

[9] Mining operations use both mechanised and conventional stopping techniques. The gold mineralisation currently exploited is contained in a succession of Elsburg and Dreyerskuil quartz conglomerate reefs. Theses reefs are mined to depth of approximately 2,300 meters below surface. Ore mined is milled and processed at the Target plant, with gold recovered on site by means of gold cyanide leaching. The target mine is situated adjacent to the Allan Ridge town and a water resource known as “Voelpan”, nearby Nyakallong in the Free State Province.

[10] Following the closure of the Lorraine mine in August 1998, the Lorraine 1 and 2 shafts were transferred to the Target Mine as target 1 and 2 shafts. As a result, although the Target Mines are only 21

years old, the infrastructure and operations have been in existence much longer.

[11] When the Lorraine shafts were transferred to Target Mine, Avgold was granted an exemption in terms of section 21(a) and (b) of the Water Act, 1956 to dispose of the purified or treated water, including

water recovered from any effluent into Voelpan.

[12] Water use by Target Mine

Under the exemption Avgold was authorised to discharge a maximum of 140MI/month of excess mine water into Voelpan for evaporation. Based on an average 30-day month, this amounted to an average discharge of 4.6MI/day. The motivation for granting the exemption indicated that investigations revealed that “the water discharged into Voelpan will not negatively affect any groundwater users, nor would an expected rising of the water level affect the area surrounding the pan.”

[13] The groundwater discharged is not a dirty by-product of mining processing but is groundwater that is pumped out of the mine shafts to prevent flooding.

[14] This exemption was recognised as an existing lawful water use when the National Water Act (the NWA) came into effect and was registered with the DWS. Avgold was permitted to continue with the existing lawful water use in accordance with the terms and conditions of the exemptions until October 2004.

[15] At the time that the exemption expired, Avgold elected not to apply for a water use license under NWA as it was no longer discharging water into Voelpan as the Target Mine, at that time, was experiencing a negative water balance.

[16] The negative water balance continued until approximately 2016 when the water balance at the Target Mine began to be water positive. At this time, the Target Mine was able to store excess water at the Million Gallon Dam, with occasional, low (8MI/month) discharge into the Voelpan.

[17] However, since September 2021, the volume of water depositing into the Target Mine increased significantly due to Avgold’s mining activities intercepting underground water and a significant increase in rainfall, approximately 923mm, in the region compared against the regional average of 587mm for the period November to March each year which percolated into Target Mines underground mining operations.

[18] As a result, the water discharged into Voelpan doubled during the rainy season to over 80MI per month from November 2021 to May 2022. For the period November 2022- March 2023 the average water discharged to the Voelpan was 46.5MI per month. This despite the higher rainfall during that period.

[19] During September 2022, the DWS indicated that it received a compliant regarding discharge of water into Voelpan.

Was the issuing of the Directive by the DWS an unreasonable administrative action.

[20] On or about 17 November 2022, Avgold received from the Provincial Head, a Notice of Intention to issue a Directive in terms of sections 19(3) and 53(1) of the NWA (the Notice).

[21] The Notice afford Avgold an opportunity to respond to and to provide reasons why a Directive should not be issued requiring Avgold to cease all water uses within 14 days of the issue of the Directive.

The details of the complaint were not specified in the Notice.

[22] The only substantive conclusion of the site inspection was that there

is no authorisation for the discharge taking place.

[23] On the 7th December 2022, Avgold responded to the Notice. The response acknowledged that there were certain water uses which were being conducted without a water use licence, being the discharge of groundwater into Voelpan. The response included details of measures taken to date to reduce the groundwater discharge and measures that were to be implemented in the immediate future to bring about the cession of ground water discharge into the Voelpan.

[24] On 5 April 2023 Avgold received the Directive dated 30 March 2023 issued by the Director General, Department of Water and Sanitation (“DWS”), advising that Avgold’s response to the Notice was “deemed unsatisfactory”. This Directive requires Avgold to:

[24.1] Stop the abovementioned water use within fourteen (14) working days from the date of the receipt of the Directive.

[24.2] Appoint a suitably qualified environmental consultant to compile a rehabilitation plan for the affected areas within thirty (30) working days upon receipt of the Directive. The rehabilitation plan must entail amongst others; the nature and extent of the impact of the water use activity had or may have on the water resources and measures that will be implemented to remediate or mitigate the impacts with clear timeframes and descriptions of how and when each remedial/ mitigation action will be implemented.

[24.3] The rehabilitation plan must further indicate the cost estimate of the entire rehabilitation process, and

[24.4] Implement all the recommendations contained in the rehabilitation plan and rehabilitate the areas affected by the water use activities within thirty (30) working days of the Departmental Recommendation of the Rehabilitation Plan.

[25] On the 19 April 2023, the first applicant addressed a letter to the DWS. The letter requested that the Department consider amending paragraph 1 of section II of the Directive to take effect from 1 July 2023. This was to afford Avgold sufficient opportunity to complete the communicated measures contained in the response to the pre-Directive and in the letter of 19 April 2023, which measures were necessary to achieve zero discharge.

[26] The letter to DWS and its attendant request were based on the understanding that if Avgold were to stop discharging ground water, there would be catastrophic consequences, including the flooding and potential permanent closure of the mine.

[27] On 24 April 2023, the third respondent directed a letter to the first

applicant refusing to extend the Directive until 30 June 2023.

[28] As a consequence of the DWS refusing to countenance the applicant’s

proposal for an extension, an appeal has been launched against the decision to issue the Directive in the form that it was.

[29] I agree with the applicant’s submissions that, the procedure followed by both the second and third respondents in issuing the Directive was procedurally unfair as it failed to indicate the underlying reason for which it sought to issue the Directive, namely the increasing water level in the Voelpan and the impact on houses adjacent to Voelpan. As a result, the first applicant was not afforded a reasonable opportunity to make representations to the second respondent which would and should have influenced the third respondent’s decision to issue the Directive.

[30] First applicant only became aware that the “real” reason for the issuing of the Directive was that the rising water levels of the Voelpan were impacting on some houses along the pan that had been flooded. This information was only made available to the applicant after it sought in a letter addressed to the DWS on the 19 April 2023 for an extension of the timelines provided in the Directive.

[31] Importantly, it must be noted that measures were already undertaken to move the affected households to alternative accommodation while the process for permanent relocation had already been substantially

advanced. As such Avgold was not afforded a fair and proper opportunity to address the DWS as the decision maker on the true facts surrounding this issue and concern.

[32] In effect, the affected houses either have already been relocated or will soon be relocated from the one area likely to be impacted by any rising water levels of the Voelpan. Furthermore, the measures

undertaken by the first applicant which will be completed by 30 June 2023, will ensure that no further discharge will occur and therefore there will be no rising in water levels of the Voelpan.

[33] The principle of procedural fairness as inherent in the Bill of Rights was discussed by Chaskalson P, in KYALAMI Ridge – see in this regard Minister of Public Works v Kyalami Ridge Environmental Association 2001 7 BCLR 652 CCC par 101.

‘Observants of the rules of procedural fairness that an administrative functionary has an open mind and a complete picture of the facts and circumstances within which the administrative action is taken. In that way the functionary is likely to apply his or her mind to the matter in fair and regular manner- LAWSA Procedural Fairness para 16.’

[34] There is no reason to discuss the Applicant’s appeal in terms of section 148 of the NWA in this judgement, since this has no bearing on the suspension of the decision made. Without dwelling into any minute details, I ‘am also of the view that the decision to issue the directive is not reasonable in that the impact of complying

with the Directive are not proportional to the impact caused by the discharging water into the Voelpan as, among others;

[34.1] Complying with the Directive will result in;

(a) the Target Mine floods,

(b) risks to the health and safety of the employees at the mine,

(c) the sterilisation of minerals which are an important component of the South African economy,

(d) the ultimate cessation of mining activities of the Target Mine due to flooding and

(e) the retrenchment of 2225 employees most of whom reside in the surrounding communities thus significantly affecting the socio-economic survival of the community.

Conclusion

[35] In my view, this matter can be decided only on the reasons discussed above in this judgement.

[36] As the applicants correctly submit, the court may enquire whether by granting the interdict, it is not condoning and perpetuating unlawful conduct on the part of the first applicant. One important such consideration is that such an appeal by the applicants, in terms of section 148(2) of NWA indicates that such an appeal does not suspend the operation of the Directive. A further consideration is that there is precedent for the court to suspend the operation of an order requiring the cessation of unlawful conduct. This is in order to permit the conduct to be cured and prevent serious adverse consequences of the immediate cession of the unlawful conduct. This approach was followed in Mogalakwena Local Municipality v Provincial executive council Limpopo & others case no: 35248/14. See also Gijima & and Passenger Rail Agency of South Africa v Siyangena Technologies (pty) ltd others (487/2021) [2022] ZASCA 149 [2023] 1 All SA 74 (SCA); 2023 (2) SA 51 (SCA) (1 November 2022).

[37] This is the type of order that this court granted in June 2023.

[38] In my view urgency arose on 24 April 2023 when the third respondent refused to extend the Directive until 30 June 2023. The result of my order is that all requirements of urgency and interdict have been met by the applicants.

Order

[39] Consequently the order that I made on the 26th of June 2023 stands.

[39.1] The operation of the Directive issued by the second respondent to the first applicant dated 30 March 2023 is suspended until and including 30 June 2023 alternatively until the appeal lodged by the applicants to Water Tribunal under section 148(1)(a) and (j) of the National Water Act, 36 of 1998 has been finally determined, whichever occurs first.

[39.2] The respondents who opposed this application shall pay the costs of this application jointly and severally, the one paying the other/s to be absolved, including the cost of two counsel.

J

RAULINGA

Judge of the High Court

Gauteng Division, Pretoria

Date of Hearing: 10/05/2023

Judgment delivered

27/10/2023

APPEARANCES:

For the Applicant: Adv. M Mantrobus SC Adv. I Nongogo Attorney for the Applicant: White & Case SA c/o Martin Attorneys For the Respondent: Adv. Ramatsekisa Attorney for the Respondent: The State Attorney Pretoria

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Luna Meubel Vervaardigers v Makin 1977 (4) SA 135 (W)

Case cited

Minister of Public Works v Kyalami Ridge Environmental Association 2001 7 BCLR 652 (CC)

Case cited

Mogalakwena Local Municipality v Provincial executive council Limpopo & others case no: 35248/14

Case cited

Gijima & Passenger Rail Agency of South Africa v Siyangena Technologies (Pty) Ltd and others (487/2021) [2022] ZASCA 149; [2023] 1 All SA 74 (SCA); 2023 (2) SA 51 (SCA)

Case cited

National Water Act, 36 of 1998

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.