Banda and Another v Xenforce Proprietary Limited (008220/2022) [2023] ZAGPJHC 1195 (23 October 2023)
- Citation
- [2023] ZAGPJHC 1195
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- South Gauteng High Court, Johannesburg
- Panel
- Twala M L
- Case number
- 008220/2022
More details
- Court
- South Gauteng High Court, Johannesburg
- Panel
- Twala M L
- Case number
- 008220/2022
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the plaintiffs' particulars of claim are neither vague nor embarrassing and sufficiently disclose a cause of action. The oral agreements relied upon by the plaintiffs are independent contracts concluded after the breach of the initial written agreement and do not purport to amend the original contract, thus the non-variation clause does not apply. The amounts claimed arise from these oral agreements and are not damages. The doctrine of privity of contract does not preclude the plaintiffs' claims, as they are directed against the defendant, not its contractors. The exception raised by the defendant lacks merit and is dismissed.
Court disposition
Exception dismissed with costs.
Orders
- The exception is dismissed with costs.
02
Material facts
Parties
Siphamandla Bongani Banda
Plaintiff Counsel: Adv. PhaladiNoxolo Linda Banda
Plaintiff Counsel: Adv. PhaladiXenforce Proprietary Limited
Defendant Counsel: Mr J MeyerAmounts and remedies
- Daily Penalty for Contractor Non Attendance: ZAR 2,500
- Payment for Electrical Faults, Building Levies, Furniture Removal, and Rental: ZAR 19,824
03
Procedural history
Posture
Civil Procedure / Exception to Amended Particulars of Claim
04
Questions and positions
Legal issues
- 01
Whether the plaintiffs' amended particulars of claim disclose a cause of action.
- 02
Whether the particulars of claim are vague, embarrassing, or bad in law.
- 03
Whether the oral agreements are enforceable despite the non-variation clause in the written agreement.
- 04
Whether the amounts claimed are damages or arise from independent oral agreements.
Party arguments
- Applicant
- The plaintiffs argue that the defendant breached the written agreement by failing to deliver a dwelling constructed in a proper and workmanlike manner in compliance with the Housing Consumers Protection Measures Act. After the breach, two oral agreements were concluded: one imposing a daily penalty of R2,500.00 for contractor non-attendance, and another for payment of R19,824.00 for specific expenses. The plaintiffs maintain these oral agreements are independent of the initial written contract and do not amend it. They assert that the particulars of claim are clear, not vague or embarrassing, and that the amounts claimed are based on the oral agreements, not damages.
- Respondent
- The defendant contends that the particulars of claim are vague and embarrassing, lacking necessary averments to sustain a cause of action. It argues that the plaintiffs plead mutually exclusive positions regarding maintenance works and fail to provide a breakdown of the amounts claimed. The defendant further asserts that the claims are based on a written agreement containing a non-variation clause, rendering subsequent oral agreements unenforceable. It also raises the doctrine of privity of contract regarding the penalty for contractor non-attendance.
05
Court’s reasoning
Legal principles
- 01
Telematrix (Pty) Ltd v Advertising Standards Authority SA [2005] ZASCA 73; [2006] 1 ALL SA 6 (SCA); 2006 1 SA 461 (SCA)
An exception that a pleading does not disclose a cause of action must demonstrate that the pleading as a whole lacks necessary averments to sustain a cause of action. Exceptions should be dealt with sensibly and not in an overly technical manner.
- 02
Luke M Tembani and Others v President of the Republic of South Africa and Another [2022] ZASCA 70; 2023 (1) SA 432 (SCA) (20 May 2022)
Exceptions are competent where pleadings are so vague that it is impossible to determine the nature of the claim or where pleadings are bad in law and do not support a legally recognised cause of action. The burden rests on the excipient to establish that on every reasonable interpretation, the pleading is excipiable.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the plaintiffs' particulars of claim are neither vague nor embarrassing and sufficiently disclose a cause of action. The oral agreements relied upon by the plaintiffs are independent contracts concluded after the breach of the initial written agreement and do not purport to amend the original contract, thus the non-variation clause does not apply. The amounts claimed arise from these oral agreements and are not damages. The doctrine of privity of contract does not preclude the plaintiffs' claims, as they are directed against the defendant, not its contractors. The exception raised by the defendant lacks merit and is dismissed.
Obiter and limits
- Exceptions should not be approached in an overly technical manner, as this undermines their usefulness in weeding out cases without legal merit.
- The oral agreements in question are separate and independent from the initial written contract and do not constitute amendments to it.
Court disposition
Exception dismissed with costs.
- The exception is dismissed with costs.
Source and reliance status
South Gauteng High Court, Johannesburg
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
South Gauteng High Court, Johannesburg
Judgment
SAFLII Note: Certain personal/private details of parties or witnesses have been redacted from this document in compliance with the law and SAFLII Policy
IN THE HIGH COURT OF
SOUTH AFRICA
GAUTENG LOCAL DIVISION, JOHANNESBURG
CASE NO: 008220/2022
NOT REPORTABLE
NOT OF INTEREST TO
OTHER JUDGES
REVISED
23/10/23
In the matter between:
SIPHAMANDLA
BONGANI BANDA
FIRST
PLAINTIFF
NOXOLO
LINDA BANDA
SECOND
PLAINTIFF And
XENFORCE
PROPRIETARY LIMITED
DEFENDANT
JUDGMENT
TWALA, J
[1] The defendant has taken an exception against the plaintiffs’ amended particulars of claim to the summons dated the 26th of October 2022 in that they lack the averments necessary to sustain the cause of action and/or are vague and embarrassing and/or are bad in law.
[2] The genesis of this case arose when on the 23rd of March 2020 the plaintiffs and the defendant concluded a written agreement whereby the plaintiffs employed the defendant to erect a dwelling on the property known and described as Erf […] Midstream Estate, Extension 68, Ekurhuleni Metropolitan Municipality, Gauteng, Midstream Ridge (“the property”).
[3] The plaintiffs allege that they (the plaintiffs) performed in terms of agreement, but the defendant breached the terms of the agreement in that it failed to deliver a dwelling on the property that is constructed in a proper and workmanlike manner that complies with the Housing Consumers Protection Measures Act.[1] It is alleged further that the defendant has failed to rectify the faults and defects after having been served with a 30 days notice to do so.
[4] It is further alleged that as a result of the defendant’s failure to remedy the breach, the plaintiffs and the defendant concluded an oral agreement in February 2021, whereby it was agreed that the defendant would send its contractors to the property of the plaintiffs to remedy the faults and defects. It was a term of the agreement that for each day the defendant’s contractors failed to arrive at the plaintiffs’ property, it will be levied a penalty in the sum of R 2 500.00. On the 17th of May 2021, the defendant further concluded another oral agreement whereby it was agreed that it will pay the plaintiffs a sum of R 19 824.00 being for electrical faults, building levies, furniture removal and for two weeks rental.
[5] It is trite that an exception that a pleading does not disclose a cause of action strikes at the formulation of the cause of action and its legal validity. The complaint is not directed at a particular paragraph in the pleading but at the pleading as a whole, which must be demonstrated to be lacking the necessary averments to sustain a cause of action. Furthermore, it is trite that exceptions should be dealt with sensibly since they provide a useful mechanism to weed out cases without legal merit. However, an overly technical approach should be avoided because it destroys the usefulness of the exception procedure.[2]
[6] Recently, the Supreme Court of Appeal in Luke M Tembani and Others v President of the Republic of South Africa and Another[3] referring to the authority quoted above stated the following:
“[14] Whilst exceptions provide a useful mechanism ‘to weed out cases without legal merit’, it is nonetheless necessary that they be dealt with sensibly. It is where pleadings are so vague that it is impossible to determine the nature of the claim or where pleadings are bad in law in that their contents do not support a discernible and legally recognised cause of action, that exception is competent. The burden rests on an excipient, who must establish that on every interpretation that can reasonably be attached to it, the pleading is excipiable. The test is whether on all possible readings of the facts no cause of action may be made out; it being for the excipient to satisfy the court that the conclusion of law for which the plaintiff contends cannot be supported on every interpretation that can be put upon the facts.”
[7] As regards the first ground of the defendant’s complaint, there is no merit in the argument that the plaintiffs pleaded two mutually exclusive positions by alleging that the defendant failed to undertake maintenance works and then immediately acknowledge that there is no dispute that it undertook the necessary maintenance work. The plaintiffs pleaded that, although the defendant performed the works, it has failed to deliver a dwelling that meets the requirements of the Housing Consumers Protection Measures Act and, a dwelling that is constructed in a proper and workmanlike manner. Therefore, there is no ambiguity in this pleading or vagueness which makes it impossible for the defendant to plead.
[8] It is a misconstruction of the plaintiffs’ particulars of claim, as amended, to say that the plaintiffs are claiming specific performance and/or damages without giving a breakdown as to how the amount claimed is computed. Furthermore, there is no merit in the contention that the plaintiffs’ claim is based on a written agreement which has been annexed to the particulars of claim which has a clause that any changes or alterations to the agreement shall be of no force or effect unless reduced to writing, (the non-variation clause). The plaintiffs do not rely on the initial agreement between the parties for the claims, but on the subsequent oral agreements concluded by the parties after the defendant had breached the written agreement and failed to remedy the breach.
[9] The two oral agreements are completely independent of the initial written agreement and do not purport to be amending the terms thereof. It was agreed between the parties that, should the contractors of the defendant fail to attend to the property of the plaintiffs on any day, the defendant shall be liable to a levy of R 2 500.00. This is a separate contract entered into after the defendant breached the initial written contract and therefore does not purport to amend that contract. It is my respectful view therefore that the amounts on claims B and C of the particulars of claim are not damages but are based on the oral agreements.
[10] The oral agreement concluded in February 2021 is between the plaintiffs and the defendant. The doctrine of privity of contract, as contended by the defendant, does not arise in as far as the contractors of the defendant are concerned. The plaintiffs are not claiming anything against the contractors for they do not have any agreement with them but are claiming against the defendant as it undertook, in the oral agreement, that it will pay R 2 500.00 as a penalty for each day that its contractors do not avail themselves at the property of the plaintiffs. Furthermore, the plaintiffs allege that they have performed in terms of the agreement by paying the construction price – thus there is no merit in the defendant’s argument that the plaintiffs say they have performed but established no facts that necessitates that conclusion.
[11 I am of the considered view therefore that there is no merit in the complaint raised by the defendant and the exception falls to be dismissed.
[12] In the circumstances, I make the following order:
1. The exception is dismissed with costs.
TWALA M L
JUDGE OF THE HIGH
COURT OF SOUTH AFRICA
GAUTENG LOCAL DIVISION
Delivered: This judgment and order were prepared and authored by the Judge whose name is reflected and is handed down electronically by circulation to Parties / their legal representatives by email and by uploading it to the electronic file of this matter on Case Lines. The date of the order is deemed to be the 23rd of October 2023.
APPEARANCES:
For the Plaintiff:
Adv. Phaladi
Instructed by:
Fluxmans Incorporated
Tel: 011 328 1814
bduma@fluxmans.com
For the Defendant:
Mr J Meyer
Meyer and Partners Attorneys Inc
Tel: 012 653 8445
junior@meyerattorneys.co.za
Date of Hearing: 9th of October 2023
Date of Judgment: 23rd of October 2023
[1] 95 of 1998.
[2] See in this regard Telematrix (Pty) Ltd v Advertising Standards Authority SA [2005] ZASCA 73; [2006] 1 ALL SA 6 (SCA); 2006 1 SA 461 (SCA).
[3] [2022] ZASCA 70; 2023 (1) SA 432 (SCA) (20 May 2022).
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.