Bapedi and Associates CC v Tusk Construction Support Services (Pty) Ltd and Another (47218/2020) [2021] ZAGPPHC 630 (27 September 2021)

Bapedi and Associates CC v Tusk Construction Support Services (Pty) Ltd and Another (47218/2020) [2021] ZAGPPHC 630 (27 September 2021)

The court found that the NEC3 standard terms and conditions were expressly incorporated by reference in the tender documents and contract data, and the applicant was made aware of where to obtain the full contract. The applicant acted in accordance with the NEC3 contract during the project, including submitting...

Source-derived case information.

Citation
[2021] ZAGPPHC 630
Parties
Applicant: Bapedi and Associates CC; Respondent: Tusk Construction Support Services (Pty) Ltd; Respondent: Department of Transport and Public Works – Western Cape Provincial Government
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
47218/2020
Procedural Posture
Review Application / First Instance Judgment
Outcome
Application dismissed with costs, including the cost of senior counsel.
Judges
Strydom
Legal Topics
Contractual Incorporation by Reference, Time Barred Claims, Adjudication Vs Arbitration, Repudiation and Termination
Commercial and Corporate Civil Procedure Contractual Incorporation by Reference Time Barred Claims Adjudication Vs Arbitration Repudiation and Termination

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Bapedi and Associates CC

Applicant

Tusk Construction Support Services (Pty) Ltd

Respondent

Department of Transport and Public Works – Western Cape Provincial Government

Respondent

Procedural Posture

Review Application / First Instance Judgment

  1. 1 Whether the applicant was bound by the dispute resolution provisions of the NEC3 contract.
  2. 2 Whether the applicant's claim was time-barred under the NEC3 contract.
  3. 3 Whether the court had jurisdiction to grant the relief sought by the applicant.

Ratio Decidendi

The court found that the NEC3 standard terms and conditions were expressly incorporated by reference in the tender documents and contract data, and the applicant was made aware of where to obtain the full contract. The applicant acted in accordance with the NEC3 contract during the project, including submitting claims and notices under its provisions. The fact that the applicant did not sign the standard terms was immaterial, as the contract documents clearly incorporated them and the applicant demonstrated the necessary intention to be bound. The applicant's referral to adjudication was made outside the time limits stipulated in clause 93.3 of the NEC3 contract, rendering the claim...

Court Disposition

Application dismissed with costs, including the cost of senior counsel.

Orders

  • The application is dismissed with costs, including the cost of senior counsel.