The Tribunal found that the delay in lodging the appeal was excessive, but the appellant provided a strong and adequate explanation for the delay, including multiple extensions granted by the respondent's office. Although the respondent lacked authority to grant such extensions, both parties operated under a genuine...

Source-derived case information.

Citation
[2010] ZAWT 5
Parties
Appellant: Hendrik Sand van Heerden (Pty) Ltd; Respondent: Minister of Water & Environmental Affairs
Court
Water Tribunal
Jurisdiction
South Africa
Case Number
WT26/11/2010
Procedural Posture
Condonation Application / Preliminary Ruling on Condonation for Late Appeal
Outcome
Condonation for late lodging of the appeal is granted.
Judges
L.J Lekale, W Singo, A.S Makhanya, H Thompson
Legal Topics
National Water Act, Condonation, Appeal Lateness, Estoppel, Jurisdiction of Tribunal
Administrative Law Environmental Law National Water Act Condonation Appeal Lateness Estoppel Jurisdiction of Tribunal

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 9 Party arguments 2
Sign in to unlock

Parties

Hendrik Sand van Heerden (Pty) Ltd

Appellant

Minister of Water & Environmental Affairs

Respondent

Procedural Posture

Condonation Application / Preliminary Ruling on Condonation for Late Appeal

  1. 1 Whether good reason exists for condonation of the late lodging of the appeal under item 5(2) of Schedule 6 to the National Water Act and Rule 4(4) of the Water Tribunal Rules.
  2. 2 Whether the respondent is estopped from opposing condonation due to its conduct in granting extensions.
  3. 3 Whether the Water Tribunal has jurisdiction over issues relating to the Promotion of Administrative Justice Act.

Ratio Decidendi

The Tribunal found that the delay in lodging the appeal was excessive, but the appellant provided a strong and adequate explanation for the delay, including multiple extensions granted by the respondent's office. Although the respondent lacked authority to grant such extensions, both parties operated under a genuine common mistake of law. The Tribunal held that the appellant discharged the burden of proving good reason for condonation, with no evidence of prejudice to the respondent, who had effectively consented to the extensions. The prospects of success in the appeal were considered sufficient for condonation, and the respondent was estopped from relying on strict legal timelines due...

Court Disposition

Condonation for late lodging of the appeal is granted.

Orders

  • Condonation is granted for the late lodging of the appeal.
  • The appeal shall be rescheduled for a hearing in due course.