Bila Civil Contractors (Pty) Ltd v Passenger Rail Agency of South Africa (21344/2019) [2023] ZAGPPHC 618 (31 July 2023)
- Citation
- [2023] ZAGPPHC 618
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- North Gauteng High Court, Pretoria
- Panel
- Makhoba
- Case number
- 21344/2019
More details
- Court
- North Gauteng High Court, Pretoria
- Panel
- Makhoba
- Case number
- 21344/2019
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that although the parties reached agreement by tender and acceptance, there were outstanding issues requiring further negotiation, including the failure by the plaintiff to attach a required addendum. The conduct of the parties, including correspondence and minutes from meetings, indicated a lack of animus contrahendi and consensus. As such, no binding contract was concluded between the plaintiff and defendant. The plaintiff’s claim was dismissed. The defendant was awarded costs, including costs for the hearing on 1 November 2022, as the matter was not properly placed before the court due to the plaintiff’s non-compliance.
Court disposition
Plaintiff’s claim dismissed with costs, including costs for 1 November 2022.
Orders
- The plaintiff’s claim is dismissed with costs, including costs of 1 November 2022.
02
Material facts
Parties
Bila Civil Contractors (Pty) Ltd
Plaintiff Counsel: Ms J HarwoodPassenger Rail Agency of South Africa
Defendant Counsel: Adv C Erasmus SC03
Procedural history
Posture
Civil Trial / Special Case Stated Under Rule 33
04
Questions and positions
Legal issues
- 01
Whether an agreement was concluded between the plaintiff and defendant as pleaded by the plaintiff.
- 02
If an agreement was concluded, whether the plaintiff’s claim against the defendant has become prescribed.
- 03
If the above are in favour of the plaintiff, whether performance under the agreement became impossible and the contract therefore null and void.
- 04
Costs.
Party arguments
- Applicant
- The plaintiff contended that a binding agreement was concluded with the defendant for the upgrade of the Mamelodi Garden Station, that the defendant repudiated the agreement, and that the defendant is liable for breach of contract. The plaintiff maintained that all necessary steps for contract formation were completed and that the defendant’s conduct amounted to acceptance and consensus.
- Respondent
- The defendant argued that no consensus was reached and thus no binding agreement was concluded. Alternatively, the defendant raised the defence of prescription, and further contended that even if consensus was present, performance was impossible as the defendant could not obtain ownership of certain properties required for execution. The defendant also argued that the plaintiff suffered no damages.
05
Court’s reasoning
Legal principles
- 01
Command Protection Services (Gauteng) (Pty) Ltd t/a Maxi Security v South Africa Post Office Ltd [2013] 1 All SA 266 (SCA)
Where parties reach agreement by offer and acceptance but there are outstanding material matters requiring further negotiation, the agreement may lack contractual force unless consensus is reached on those matters.
- 02
CGEE Alsthom Equipment et Enterprises Electriques, South African Division v GKN Sankey (Pty) Ltd 1987 (1) SA 81 (A)
The intention of the parties to be contractually bound is determined from their conduct and the facts of the particular case.
- 03
Sivubo Trading and Projects CC v Development Bank of Southern Africa 233/2018 [2019] ZASCA 28 (28 March 2019)
If consensus is absent due to failure to agree on material terms or attach required addenda, no contract comes into existence.
06
Ratio, limits and disposition
Ratio decidendi
The court found that although the parties reached agreement by tender and acceptance, there were outstanding issues requiring further negotiation, including the failure by the plaintiff to attach a required addendum. The conduct of the parties, including correspondence and minutes from meetings, indicated a lack of animus contrahendi and consensus. As such, no binding contract was concluded between the plaintiff and defendant. The plaintiff’s claim was dismissed. The defendant was awarded costs, including costs for the hearing on 1 November 2022, as the matter was not properly placed before the court due to the plaintiff’s non-compliance.
Obiter and limits
- The court noted that the question of damages was not determined and would be addressed separately depending on the outcome of the stated case.
- The defendant was entitled to costs for 1 November 2022 as it was not responsible for the matter not proceeding on that day.
Court disposition
Plaintiff’s claim dismissed with costs, including costs for 1 November 2022.
- The plaintiff’s claim is dismissed with costs, including costs of 1 November 2022.
Source and reliance status
North Gauteng High Court, Pretoria
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
North Gauteng High Court, Pretoria
Judgment
THE
REPBLIC OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG HIGH COURT DIVISION, PRETORIA
Case no: 21344/2019
1) REPORTABLE: NO
(2) OF INTEREST TO OTHER JUDGES: NO
(3) REVISED.
31 JULY 2023
DATE
SIGNATURE
In the matter between:
BILA CIVIL CONTRACTORS (PTY) LTD
PLAINTIFF
And
PASSENGER
RAIL AGENCY OF SOUTH AFRICA
DEFENDANT
JUDGMENT
MAKHOBA, J
[1] The plaintiff is Bila Civil Contractors (PTY LTD, a company incorporated and registered in accordance with the company laws of South Africa.
[2] The Defendant is the Passenger Rail Agency of South Africa is a juristic entity established in terms of the Legal Succession of the South African Transport Services Act 9 of 1989, it is an organ of State.
[3] In 2011 the defendant invited tenders under Tender No. HO/INF/304/03/2011 for the upgrade of the Mamelodi Garden Station above platform level (“the tender”), to which the plaintiff submitted a proposal.
[4] Part of the tender documents forming part of the tender was the contract data for the Principal Building Contracts Committee (the JBCC”) Contract, Series 2000, Edition 5.0 (“the contract data”).
[5] On 9 September 2011 the Supply Chain Management of the defendant approved the appointment of the plaintiff and the contract was signed by the plaintiff on 23 September 2011.
[6] This is a matter in terms of Rule 33(1), (2) (3) and (5) of the uniform Rules of Court, namely a special case premised upon a written statement of fact, to be decided by this court. Parties agree that the following are the questions of law and issues in dispute.
6.1 Whether an agreement was concluded between the Plaintiff and the Defendant as pleaded by the plaintiff;
6.2 If indeed an agreement was concluded whether the Plaintiff’s claim against the Defendant has become prescribed;
6.3 If the answer to the aforementioned questions are in favour of the plaintiff, whether performance in term of the agreement by the Defendant became impossible and the contract therefore null and void;
6.4 The parties have agreed that the question of damages not be determined as part of this stated case but will be determined separately dependant on the outcome of this stated case.
6.5 Costs.
[7] The plaintiff contends that there is an agreement between it and the defendant, the defendant repudiated the upgrade agreement. The defendant denies this.
[8] The defendant raise the defence of prescription and that there was no consensus between the parties and thus, no agreement.
[9] The defendant contends further that insofar as it is found that consensus was present, that it was impossible for it to perform as in order to perform it was required to obtain ownership of certain properties and was unable to do do and the plaintiff has suffered no damages.
[10] The matter was initially set down for the 1st of November 2022, but due to non-compliance on the part Plaintiff the matter did not appear on the trial roll of the day. The parties however utilized the opportunity to prepare the agreed statement of facts, for special adjudication by this court.
Whether an agreement was concluded between the parties as pleaded by plaintiff.
[11] In Command Protection Services (Gauteng) (Pty) Ltd t/a Maxi Security v South Africa Post Office Ltd[1] the facts of this case are slightly similar to the facts of this matter before me.
[12] In that matter, the appellant was advised that it had been awarded the tender. Shortly thereafter the respondent was provided with a draft contract however the contract was not finalized.
[13] In paragraph 12 the court said the following: “[12] The dispute thus arising is not novel. It frequently happens, particularly in complicated transactions, that the parties reach
agreement by tender (or offer) and acceptance while there are clearly some outstanding issues that require further negotiation and agreement. Our case law recognises that in these situations there are two possibilities. The first is that the agreement reached by the acceptance of the offer lacked animus contrahendi because it was conditional upon consensus being reached, after further negotiation, on the outstanding issues. In that event, the law will recognise no contractual relationship, the offer and acceptance notwithstanding, unless and until the outstanding issues have been settled by agreement. The second possibility is that the parties intended that the acceptance of the offer would give rise to a binding contract and that the outstanding issues would merely be left for later negotiation. If in this event the parties should fail to reach agreement on the outstanding issues, the original contract would prevail (see eg CGEE Alsthom Equipments et Enterprises Electriques, South African Division v GKN Sankey (Pty) Ltd 1987 (1) SA 81 (A) at 92A-E; Namibian Minerals Corporation Ltd v Benguela Concessions Ltd [1996] ZASCA 140; 1997 (2) SA 548 (A) at 567a-c [also reported at [1996] ZASCA 140; [1997] 1 All SA 191 (A) – Ed]).”
This decision is quoted with approval in Sivubo Trading and Projects CC v Development Bank of Southern Africa[2]
[14] In CGEE Alsthom Equipment et Enterprises Electriques, South Africa Division v GKH Sankey (Pty) Ltd[3] at paragraph A the court said “…..where in the course of negotiating a contract the parties reach an agreement by offer and acceptance, the fact that there are still a number of outstanding matter material to the contract upon which the parties have not yet agreed may well prevent the agreement from having contractual force.”
[15] It depends on the facts of a particular case whether the initial agreement acquires contractual force or not. The intention of the parties is to be determined from their conduct.[4]
[16] In my view the failure by the plaintiff to attach the addendum which was required resulted in a failure to reach consensus by the parties.
[17] Furthermore, In Prasa Steering Committee meeting NO 16, The following was said: “ *Finalization of the Bila Contract is critical.
*Construction work on the non-station structure can commence as soon as
PRASA conclude their agreement with Bila Civil Contractors”.[5]
In my view this is indicative of the fact that the parties lacked animus contrahendi.
[18] In addition the letter dated 26 July 2017[6] from the plaintiff reads as follows: “Can we now sign the contract of which the tender document is in your possession”
[19] It is clear from the conduct of the parties that they did reach an agreement by tender however, there are clearly some outstanding issues that require further negotiations and agreement.
[20] In my view there is no contract between the plaintiff and defendant until the outstanding issues have been settled by
agreement.
[21] In regard to the costs for 1 November 2022, counsel for the defendant did come to court however the matter was not properly placed before court, and it ended up in the chambers of the Deputy Judge President.
[22] In my view the defendant is entitled to the cost for 1 November 2022 since it is not the defendant’s fault that the matter could not proceed on said day.
[23] I make the following order;
25.1 The plaintiff’s claim is dismissed with cost including cost of 1 November 2022.
______
MAKHOBA
J
JUDGE
OF THE HIGH COURT
GAUTENG DIVISION, PRETORIA
HEARD AND RESERVED JUDGMENT: 6 JUNE 2023
JUDGMENT HANDED DOWN ON: 31 JULY 2023
Appearances:
For the Plaintiff: Ms J Harwood (instructed by) Hewlett Bunn Incorporated
For the Respondent: Adv C Erasmus SC (instructed by) Ngeno & Mteto Incorporated.
[1] [2013] 1 All SA 266 (SCA).
[2] 233/2018 [2019] ZASCA 28 ( 28 March 2019) para 13.
[3] 1987 (1) SA 81 (A).
[4]
CGEE Alsthom Equipment papa 92E.
[5] CaseLines 074-6 to o74-7 para 27.
[6] CaseLines 0020 – 32.
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.