Bodies Under Construction CC and Others v Permasolve Investments (Pty) Ltd (19457/2023) [2023] ZAWCHC 326 (20 December 2023)

Bodies Under Construction CC and Others v Permasolve Investments (Pty) Ltd (19457/2023) [2023] ZAWCHC 326 (20 December 2023)

The court found that the applicants had a historic and substantial connection to the alternative power supply, which was critical to their use of the leased premises as a gym. The right to use the generator was not merely personal but was closely connected to their possession of the premises, given its necessity for business continuity during load shedding. The respondent's unilateral disconnection, despite ongoing arbitration discussions, amounted to unlawful deprivation of quasi-possession and constituted spoliation. The applicants satisfied both requirements for the remedy: peaceful possession and unlawful deprivation. The court ordered immediate reconnection to restore the status quo...

Citation
[2023] ZAWCHC 326
Parties
Applicant: Bodies Under Construction CC; Applicant: Specialised Weight Endurance and Aerobic Training CC; Applicant: Fluidity Wellness CC; Respondent: Permasolve Investments (Pty) Ltd
Court
Western Cape High Court, Cape Town
Jurisdiction
South Africa
Judgment Date
20 December 2023
Case Number
19457/2023
Procedural Posture
Urgent Application / Interim Relief and Reasons for Order
Outcome
Interim relief granted; respondent ordered to immediately reconnect applicants to the alternative power supply pending arbitration. Costs awarded against respondent.
Judges
Wille
Legal Topics
Spoliation, Quasi Possession, Lease Dispute, Alternative Power Supply, Urgent Interdict

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Bodies Under Construction CC

Applicant

Specialised Weight Endurance and Aerobic Training CC

Applicant

Fluidity Wellness CC

Applicant

Permasolve Investments (Pty) Ltd

Respondent

Procedural Posture

Urgent Application / Interim Relief and Reasons for Order

  1. 1 Whether the applicants were unlawfully deprived of their quasi-possession of the alternative power supply at the leased premises.
  2. 2 Whether the applicants are entitled to a spoliation remedy and reconnection to the alternative power supply.
  3. 3 Whether the right to use the alternative power supply is sufficiently connected to possession of the premises to warrant protection under spoliation.

Ratio Decidendi

The court found that the applicants had a historic and substantial connection to the alternative power supply, which was critical to their use of the leased premises as a gym. The right to use the generator was not merely personal but was closely connected to their possession of the premises, given its necessity for business continuity during load shedding. The respondent's unilateral disconnection, despite ongoing arbitration discussions, amounted to unlawful deprivation of quasi-possession and constituted spoliation. The applicants satisfied both requirements for the remedy: peaceful possession and unlawful deprivation. The court ordered immediate reconnection to restore the status quo...

Court Disposition

Interim relief granted; respondent ordered to immediately reconnect applicants to the alternative power supply pending arbitration. Costs awarded against respondent.

Orders

  • The respondent is directed to immediately reconnect the premises occupied by the applicants to the alternative power supply so that the applicants may continue occupation thereof.