Bombardier Africa Alliance Consortium v Passenger Rail Agency of South Africa (65099/2017) [2018] ZAGPPHC 413 (18 May 2018)

Bombardier Africa Alliance Consortium v Passenger Rail Agency of South Africa (65099/2017) [2018] ZAGPPHC 413 (18 May 2018)

The court held that the contract expressly provides that the DAB decision is binding and must be promptly given effect to unless and until it is revised by amicable settlement or arbitrable award. The respondent's notice of dissatisfaction and referral to arbitration do not suspend its obligation to comply with the...

Source-derived case information.

Citation
[2018] ZAGPPHC 413
Parties
Applicant: Bombardier Africa Alliance Consortium; Respondent: Passenger Rail Agency of South Africa
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
65099/2017
Procedural Posture
Urgent Application / Application for Enforcement of Dispute Adjudication Board Decision
Outcome
Application granted; respondent ordered to comply with DAB decision and pay the awarded amount plus escalation, VAT, and interest.
Judges
Nochumsohn
Legal Topics
Contractual Dispute Resolution, Dispute Adjudication Board, Enforcement of Adjudicator Award, Arbitration Clause Interpretation
Commercial and Corporate Civil Procedure Contractual Dispute Resolution Dispute Adjudication Board Enforcement of Adjudicator Award Arbitration Clause Interpretation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 3 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Bombardier Africa Alliance Consortium

Applicant

Passenger Rail Agency of South Africa

Respondent

Procedural Posture

Urgent Application / Application for Enforcement of Dispute Adjudication Board Decision

  1. 1 Whether the respondent is contractually obligated to comply with the Dispute Adjudication Board decision pending arbitration.
  2. 2 Whether the respondent's notice of dissatisfaction and referral to arbitration suspends the obligation to pay under the DAB decision.
  3. 3 Whether the court has jurisdiction to enforce the DAB decision despite the pending arbitration.

Ratio Decidendi

The court held that the contract expressly provides that the DAB decision is binding and must be promptly given effect to unless and until it is revised by amicable settlement or arbitrable award. The respondent's notice of dissatisfaction and referral to arbitration do not suspend its obligation to comply with the DAB decision. Clause 20.7 only applies where no notice of dissatisfaction is given, which is not the case here. The court found that the respondent's late attempt to introduce an oral agreement regarding milestone payments was unsupported and irregular. The applicant is entitled to escalation and VAT as provided for in the contract. The court has jurisdiction to enforce the DAB...

Court Disposition

Application granted; respondent ordered to comply with DAB decision and pay the awarded amount plus escalation, VAT, and interest.

Orders

  • The respondent is ordered to give effect to the decision of the Dispute Adjudication Board handed down on 20 April 2016.
  • The respondent is ordered to pay to the applicant the amount of R173 238 944.80.