Download PDF

South Africa Judgment

Limpopo High Court, Polokwane

Botshabelo Consulting Engineers (Pty) Ltd v Greater Giyani Municipality (5346/2020) [2023] ZALMPPHC 61 (4 August 2023)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the plaintiff had established its entitlement to provisional sentence on both claims. The tenth interim payment certificate was properly issued and communicated to the defendant, who failed to raise any substantiated defence regarding its authenticity or liquidity. The defendant's claim of ignorance and allegations of fraud were unsupported by evidence. As for the retention monies, the contract did not require a close-out report as a precondition for payment; the completion certificate sufficed. The defendant's objections were found to be baseless and did not raise triable issues. Consequently, the plaintiff's claims were upheld and provisional sentence granted for both amounts, with interest and costs.

Court disposition

Provisional sentence granted in favour of the plaintiff for both claims with interest and costs.

Orders

  • Provisional sentence is granted against the defendant in the amount of R3,547,011.24.
  • Interest on R3,547,011.24 shall run at the prescribed rate from 7 May 2019 a tempore mora until date of payment.
  • Provisional sentence is granted against the defendant in the amount of R2,954,133.17.
  • Interest on R2,954,133.17 shall run a tempore mora from 14 April 2019 until date of payment.
  • The defendant is ordered to pay the costs of these proceedings on a party and party scale.

02

Material facts

Parties

Botshabelo Consulting Engineers (Pty) Ltd

Plaintiff Counsel: Adv CM Rip

Greater Giyani Municipality

Defendant

Amounts and remedies

  • Interim Payment Certificate Amount: ZAR 3,547,011.24
  • Retention Monies: ZAR 2,954,133.17

03

Procedural history

  1. Posture

    Civil Procedure / Provisional Sentence Application

04

Questions and positions

Legal issues

Party arguments

Applicant
The plaintiff contends that it is entitled to payment of R3,547,011.24 based on interim payment certificate number 10 and R2,954,133.17 as retention monies following completion of the contract. The plaintiff asserts that all contractual requirements have been met, including the issuance of a completion certificate, and that the defendant's refusal to pay is without valid basis. The plaintiff maintains that the payment certificates are liquid documents and that no clause in the contract requires a close-out report before release of retention funds.
Respondent
The defendant challenges the tenth payment certificate, alleging lack of knowledge of its existence and suggesting possible fraudulent conduct in its issuance. Regarding the retention monies, the defendant argues that payment is conditional upon the plaintiff providing a close-out report, which it claims has not been furnished. The defendant does not dispute the existence of the contract or the completion of the project but raises these procedural objections as its defence.

05

Court’s reasoning

  1. 01

    Rule 8 of the Uniform Rules of Court

    Provisional sentence is a summary remedy available to a plaintiff who holds a liquid document proving a liquid claim against a defendant who lacks a valid defence.

  2. 02

    Joob Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture 2009(5) SA 1 (SCA); Radcon (Pty) Ltd v Florida Twin Estates (Pty) Ltd 1973 (4) SA 181 (D); Dawnays Ltd v F G Minter Ltd & Another (1971) 2 ALL ER 1389

    A payment certificate is treated as a liquid document akin to an acknowledgement of debt and is virtually regarded as cash, requiring honour by the debtor.

  3. 03

    Twee Jonge Gezellen (Pty) Ltd v Land and Agricultural Development Bank of South Africa 2011(3) SA 1 (CC)

    Provisional sentence may be defeated by proof that there is an even balance in the main case with a reasonable prospect of success for the defendant at trial.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the plaintiff had established its entitlement to provisional sentence on both claims. The tenth interim payment certificate was properly issued and communicated to the defendant, who failed to raise any substantiated defence regarding its authenticity or liquidity. The defendant's claim of ignorance and allegations of fraud were unsupported by evidence. As for the retention monies, the contract did not require a close-out report as a precondition for payment; the completion certificate sufficed. The defendant's objections were found to be baseless and did not raise triable issues. Consequently, the plaintiff's claims were upheld and provisional sentence granted for both amounts, with interest and costs.

Obiter and limits

  • A payment certificate certified by the contractor in terms of the contract is almost equivalent to cash and needs no further belaboring.
  • The defendant's attempt to introduce a requirement for a close-out report, absent from the contract, is a non-starter and cannot constitute a valid defence.

Court disposition

Provisional sentence granted in favour of the plaintiff for both claims with interest and costs.

  • Provisional sentence is granted against the defendant in the amount of R3,547,011.24.
  • Interest on R3,547,011.24 shall run at the prescribed rate from 7 May 2019 a tempore mora until date of payment.
  • Provisional sentence is granted against the defendant in the amount of R2,954,133.17.
  • Interest on R2,954,133.17 shall run a tempore mora from 14 April 2019 until date of payment.
  • The defendant is ordered to pay the costs of these proceedings on a party and party scale.

Source and reliance status

Limpopo High Court, Polokwane

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Limpopo High Court, Polokwane

Judgment

[2023] ZALMPPHC 61

REPUBLIC

OF SOUTH AFRICA

IN

THE HIGH COURT OF SOUTH AFRICA

(LIMPOPO DIVISION, POLOKWANE)

CASE NO: 5346/2020

REPORTABLE: YES/NO

OF INTEREST TO OTHER JUDGES: YES/NO

REVISED

Date: 2023/08/04

In the matter between:

BOTSHABELO CONSULTING ENGINEERS (PTY) LTD

PLAINTIFF And

GREATER

GIYANI MUNICIPALITY

DEFENDANT

JUDGMENT

This Judgement was handed down electronically by circulation to the parties' legal representatives via their e-mail addresses and

released to SAFLII . The date and time for hand down are deemed to be 04 AUGUST 2023 at 10:00

MONENE AJ

[1] On 24 August 2020 the plaintiff issued provisional sentence summons against the defendant raising therein two claims to wit:

1.1 A sum of R3 547 011.24 arising from an interim payment certificate pursuant to a tender contract between the parties.

1.2 A sum of R2 954 133.17 comprising retention monies payable upon completion of the same contract as in the first claim.

[2] Post being served with the provisional sentence summons on 28 August 2020, the defendant filed an opposing affidavit on 20 November 2020.

[3] The matter served before this court on 4 May 2023 for determination of whether the two claims in terms of provisional sentence summons should be granted or not.

BACKGROUND

INFORMATION

[4] Upon or about March 2015 the plaintiff and the defendant entered a written contract in terms of which the plaintiff was to construct and/or develop the Giyani Section E Sports Centre for an initial contract value of R25 273 456.15.

[5] The defendant was, pursuant to the contract, obligated to pay the plaintiff monies upon the plaintiff issuing payment certificates as and when monies became due to the plaintiff during the lifespan of the contract.

[6] A portion of the monies due to the plaintiff was retained by the defendant to be payable upon the production of a certificate of completion in respect of the Sport Centre construction project.

[7] As the contract between the parties evolved, no less than nine payment certificates were issued by the plaintiff demanding payment and all nine were honoured by the defendant.

[8] On 9 April 2019 the plaintiff issued interim payment certificate number 10 indicating an amount of R3 547 011.24 as due and payable.

[9] The defendant refused to honour this last payment demand.

[10] On 14 April 2018 the plaintiff issued a certificate of completion of the project and with it an invoice demanding an amount of R2 954 133.17 as contractually agreed to retention funds.

[11] As it did with payment certificate number 10, the defendant refused to satisfy the plaintiffs invoice regarding the retention funds.

[12] Consequently in the wake of the defendant's failure to pay the two amounts demanded, the plaintiff issued provisional sentence summons claiming the amounts with interest.

THE

ISSUE

[13] There being on the papers no dispute about the existence of the contract between the parties nor on the fact that the original contract price was subsequently varied, the key issues raised by the defendant in its opposing papers are the following:

13.1 Whether the defendant knows about or is aware of the tenth interim payment certificate.

13.2 Whether the monies claimed in the tenth payment certificate are contractually due to the plaintiff or whether the plaintiff had by the ninth certificate been paid in full or not.

13.2 Whether, in terms of the contract between the parties, the retention amount is only payable upon the plaintiff furnishing a close-out report as pleaded by the defendant or upon the mere provision of a certificate of completion as per the plaintiff's case.

THE

APPLICABLE LAW

[14] The incidence of provisional sentence is provided for in rule 8 of the Uniform rules of court which rule does not need belaboring upon.

[15] Suffice to state that provisional sentence is a summary remedy available to a plaintiff who has a liquid claim against a defendant whom he believes has no valid defence to the claim. The jurisdictional factors attendant to provisional sentence are thus the following:

15.1 A liquid document in the plaintiff's possession proving a liquid claim against the defendant.

15.2 Absence of a valid defence, as viewed by the plaintiff, on the part of the defendant.

[16] The provisional nature of the provisional sentence lies in the fact that even if it is granted the defendant can subsequent thereto upon provision of security still enter the principal case and proceed to trial. It is aimed primarily at stopping a defendant who does not have a claim from kicking the can along the street and unnecessarily and needlessly prolonging proceedings.

[17] If the provisional sentence granted is left unchallenged it ceases being provisional and automatically becomes a final judgement.

[18] To obviate the granting of a provisional sentence a defendant must prove some valid defence which at least persuades the court that there can be a triable issue. He can for example challenge the supposed liquidity of the liquid document relied upon or the authenticity of his or his agent's signature on the liquid document relied upon by the plaintiff. In Twee Jonge Gezellen (Pty) Ltd v Land and Agricultural Development Bank of South Africa 2011(3) SA 1(CC) the apex court in our land held that a provisional sentence may be defeated by proof that there is an even balance in the main case which has a reasonable prospect of being tipped in the defendant's favour when oral evidence is lead at trial.

[19] The Supreme Court of Appeal in Joob Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture 2009(5) SA 1 (SCA) at paragraph 27 stated that a payment certificate is treated as a liquid document akin to an acknowledgement of debt. Indeed as determined by Radcon (Pty) Ltd v Florida Twin Estates (Pty) Ltd 1973 (4) SA 181 (D) at 184 D-H when approvingly quoting Lord Denning in Dawnays Ltd v F G Minter Ltd & Another (1971) 2 ALL ER 1389, an interim payment certificate of the kind at issue in the first claim in casu "is to be regarded virtually as cash, like a bill of exchange" which has to be honoured.

APPLYING

THE ABOVE LEGAL INSTRUMENTS TO THE FACTS

[20] As I understand the defendant's case from the answering affidavit, the first claim is challenged in the first instance on the basis that payment certificate number 10 never came to the knowledge of the defendant and not on a view that the certificate is not a liquid document. But this defence flies in the face of the evidence before this court in the form of a letter dated 9 April 2016 which was sent to the defendant by project manager Msibi advising the defendant about the last payment certificate. At any rate, owing to these proceedings the defendant now definitely knows about the said interim payment certificate.

[21] In the second instance the tenth payment certificate is challenged on unsubstantiated allegations that there is some fraudulent unlawful conduct in its make up. With the allegation flying solo in the realm of unsubstantiated untruths, this does not raise any triable issue which begins to suggest a viable defence should the matter go on trial.

[22] As already alluded to supra that a payment certificate, duly certified by the plaintiff who is so empowered in terms of the contract certify work done, after having done it itself, is a liquid document almost equivalent to cash needs no belaboring.

[22] As regards the second claim, the defendant does acknowledge that the plaintiff is entitled to retention funds upon completion. The defendant is also not making an argument suggesting that the plaintiff has not completed work on the project. All that the defendant feebly attempts to say is that before it releases the retention funds to the plaintiff, the plaintiff must have produced a close out report. But there is no clause anywhere in the contract calling for such a report as a requirement before retention funds are released upon completion, making this attempted defence a non-starter.

[23] In all the above premises it cannot be gainsaid that the plaintiff has made out a proper case for provisional sentence in circumstances where the defendant has fallen woefully short of raising any reasonably conceivable defence.

[24] Resultantly the following order is made:

21.1 Provisional sentence is granted against the defendant in the amount of R3 547 011.24.

24.2 Interest on the above amount shall run at the prescribed rate from 7 May 2019 a tempore mora until date of payment.

24.3 Provisional sentence is granted against the defendant in the amount of R2 954 133.17 with interest on this amount running a tempore mora from 14 April 2019 until date of payment.

24.4 The defendant is ordered to pay the costs of this proceedings on a party and party scale.

M

S MONENE

ACTING JUDGE OF THE HIGH COURT,

LIMPOPO DIVISION, POLOKWANE

APPEARANCES

Heard on

:04 May 2023

Judgment delivered on :04 August 2023

For the Plaintiff :Adv CM Rip Instructed by :Thomas and Swanepoel Attorneys :Tel: 015 307 1027 :Email: maryka@tslegal.co.za :colinrip@clubadvocates.co.za For the Respondents :No appearance

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Joob Joob Investments (Pty) Ltd v Stocks Mavundla Zek Joint Venture 2009(5) SA 1 (SCA)

Case cited

Radcon (Pty) Ltd v Florida Twin Estates (Pty) Ltd 1973 (4) SA 181 (D)

Case cited

Dawnays Ltd v F G Minter Ltd & Another (1971) 2 ALL ER 1389

Case cited

Twee Jonge Gezellen (Pty) Ltd v Land and Agricultural Development Bank of South Africa 2011(3) SA 1 (CC)

Case cited

Uniform Rules of Court, Rule 8

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.