Broadband Infraco SOC Limited v Eskom Holdings SOC Limited (2023/062380) [2023] ZAGPJHC 880 (7 August 2023)

Broadband Infraco SOC Limited v Eskom Holdings SOC Limited (2023/062380) [2023] ZAGPJHC 880 (7 August 2023)

The court found that Broadband Infraco and Eskom, as organs of state, are subject to constitutional and statutory obligations to avoid litigation and exhaust dispute resolution mechanisms under the Intergovernmental Relations Framework Act (IRFA) before instituting legal proceedings. Eskom's actions in terminating...

Source-derived case information.

Citation
[2023] ZAGPJHC 880
Parties
Applicant: Broadband Infraco SOC Limited; Respondent: Eskom Holdings SOC Limited
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Judgment Date
7 August 2023
Case Number
2023/062380
Procedural Posture
Urgent Application / Interim Interdict (part A) Pending Review (part B)
Outcome
Interim interdict granted in favour of Broadband Infraco; Eskom's legal action stayed; services to be restored pending dispute resolution.
Judges
WJ Du Plessis
Legal Topics
Intergovernmental Relations Framework Act, Urgent Interdict, Judicial Review, Statutory Servitude, Spoliation, Promotion of Administrative Justice Act
Administrative Law Telecoms and Media Civil Procedure Intergovernmental Relations Framework Act Urgent Interdict Judicial Review Statutory Servitude Spoliation +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 6 Party arguments 2
Sign in to unlock

Parties

Broadband Infraco SOC Limited

Applicant

Eskom Holdings SOC Limited

Respondent

Procedural Posture

Urgent Application / Interim Interdict (part A) Pending Review (part B)

  1. 1 Whether Eskom was required to exhaust the dispute resolution process under the Intergovernmental Relations Framework Act before instituting legal proceedings against Broadband Infraco.
  2. 2 Whether Broadband Infraco is entitled to urgent interim interdictory relief restoring lease and maintenance services pending the outcome of the dispute resolution process.
  3. 3 Whether Eskom's termination of agreements and disconnection of optic fibres constituted unlawful administrative action and actionable spoliation.

Ratio Decidendi

The court found that Broadband Infraco and Eskom, as organs of state, are subject to constitutional and statutory obligations to avoid litigation and exhaust dispute resolution mechanisms under the Intergovernmental Relations Framework Act (IRFA) before instituting legal proceedings. Eskom's actions in terminating agreements, disconnecting optic fibres, and instituting legal action without first declaring a formal intergovernmental dispute and following the prescribed process under IRFA were unlawful. The court held that BBI established a prima facie right to have the disputed decisions reviewed and set aside, demonstrated irreparable harm to its statutory mandate and business, and...

Court Disposition

Interim interdict granted in favour of Broadband Infraco; Eskom's legal action stayed; services to be restored pending dispute resolution.

Orders

  • The ordinary forms and service provided for in the Uniform Rules of Court are dispensed with, and this application is heard and determined on an urgent basis in terms of Rule 6(12)(a).
  • Pending the conclusion of the dispute resolution process contemplated in Part B, the action instituted by Eskom against Broadband Infraco under case number 12662/23 is stayed.