Buffalo City Metropolitan Municipality v Asla Construction (Pty) Limited

Buffalo City Metropolitan Municipality v Asla Construction (Pty) Limited

The majority held that the Municipality’s delay in challenging the Reeston contract was unreasonable and unjustified, but that the underlying award of the Reeston contract was clearly unlawful on the common cause facts because it did not comply with section 217 of the Constitution. The Court declined to make the...

Source-derived case information.

Parties
Applicant: BUFFALO CITY METROPOLITAN MUNICIPALITY; Respondent: ASLA CONSTRUCTION (PTY) LIMITED
Jurisdiction
South Africa
Procedural Posture
Constitutional Appeal / Appeal From the Supreme Court of Appeal, on Leave to Appeal
Outcome
Appeal upheld; leave to appeal granted; Reeston contract declared constitutionally invalid; no order as to costs
Legal Topics
Legality Review, Unreasonable Delay, Section 172 of the Constitution, Section 217 Procurement Validity, Self Review by an Organ of State, Settlement Agreement as Court Order
Constitutional Law Administrative Law Public Procurement Legality Review Unreasonable Delay Section 172 of the Constitution Section 217 Procurement Validity Self Review by an Organ of State +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 34 Party arguments 2 Amounts and remedies 11
Sign in to unlock

Parties

BUFFALO CITY METROPOLITAN MUNICIPALITY

Applicant

ASLA CONSTRUCTION (PTY) LIMITED

Respondent

Procedural Posture

Constitutional Appeal / Appeal From the Supreme Court of Appeal, on Leave to Appeal

  1. 1 Whether the Municipality unreasonably delayed in bringing its own review application
  2. 2 Whether the delay should be overlooked in the interests of justice
  3. 3 Whether the Court should declare the Reeston contract invalid notwithstanding delay

Ratio Decidendi

The majority held that the Municipality’s delay in challenging the Reeston contract was unreasonable and unjustified, but that the underlying award of the Reeston contract was clearly unlawful on the common cause facts because it did not comply with section 217 of the Constitution. The Court declined to make the settlement agreement an order of court because it went beyond the dispute and was not shown to be lawful or constitutionally competent. It granted leave to appeal, upheld the appeal, and declared the award constitutionally invalid while preserving accrued rights by not setting the contract aside. The concurring dissent would have refused leave to appeal and declined to pronounce...

Court Disposition

Appeal upheld; leave to appeal granted; Reeston contract declared constitutionally invalid; no order as to costs

Orders

  • Leave to appeal is granted.
  • The appeal is upheld.