Buffalo City Metropolitan Municipality v Asla Construction (Pty) Ltd (5668/2015, 5246/2015) [2016] ZAECGHC 55; [2016] 4 All SA 60 (ECG) (29 July 2016)

Buffalo City Metropolitan Municipality v Asla Construction (Pty) Ltd (5668/2015, 5246/2015) [2016] ZAECGHC 55; [2016] 4 All SA 60 (ECG) (29 July 2016)

The court found that the award of the Reeston contract to the respondent was invalid as it was not preceded by a competitive tender process, in contravention of section 217 of the Constitution and procurement legislation. The turnkey contract did not legitimately encompass the Reeston contract, and the argument that...

Source-derived case information.

Citation
[2016] ZAECGHC 55
Parties
Applicant: Buffalo City Metropolitan Municipality; Respondent: Asla Construction (Pty) Ltd
Court
Eastern Cape High Court, Grahamstown
Jurisdiction
South Africa
Case Number
5668/2015, 5246/2015
Procedural Posture
Review Application / Judgment After Hearing of Consolidated Review and Provisional Sentence Actions
Outcome
The award of the Reeston contract is declared invalid and set aside. The payment certificates issued under the contract are void ab initio. The respondent's action for provisional sentence is dismissed with costs. Each party to bear its own costs in the review application.
Judges
E Revelas
Legal Topics
Public Procurement, Section 217 Constitution, Promotion of Administrative Justice Act, Delay in Review, Unjust Enrichment, Setting Aside Administrative Action
Administrative Law Civil Procedure Land and Property Public Procurement Section 217 Constitution Promotion of Administrative Justice Act Delay in Review Unjust Enrichment +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 8 Party arguments 2 Amounts and remedies 9
Sign in to unlock

Parties

Buffalo City Metropolitan Municipality

Applicant

Asla Construction (Pty) Ltd

Respondent

Procedural Posture

Review Application / Judgment After Hearing of Consolidated Review and Provisional Sentence Actions

  1. 1 Whether the award of the Reeston contract to the respondent was lawful and valid under section 217 of the Constitution and procurement legislation.
  2. 2 Whether the applicant's review application was brought within the time limits prescribed by section 7(1) of PAJA, or whether condonation should be granted.
  3. 3 Whether the payment certificates issued under the impugned contract are enforceable.

Ratio Decidendi

The court found that the award of the Reeston contract to the respondent was invalid as it was not preceded by a competitive tender process, in contravention of section 217 of the Constitution and procurement legislation. The turnkey contract did not legitimately encompass the Reeston contract, and the argument that the Reeston contract was a valid extension was unsustainable. The applicant was granted condonation for the delay in bringing the review application, as the breach of constitutional procurement requirements was serious and public interest demanded that unlawful contracts not be enforced. Consequently, the payment certificates issued under the invalid contract were declared...

Court Disposition

The award of the Reeston contract is declared invalid and set aside. The payment certificates issued under the contract are void ab initio. The respondent's action for provisional sentence is dismissed with costs. Each party to bear its own costs in the review application.

Orders

  • The award by the applicant of contract BCC/DES/PIU/HOUS/1122/2010 for internal engineering services for Reeston Phase 3 B is declared invalid and set aside.
  • The payment certificates issued by Messrs Royal Haskoning in terms of the aforesaid contract are declared void ab initio.