Buffalo City Metropolitan Municipality v Nurcha Development Finance (Pty) Ltd and Others (378/2017) [2018] ZASCA 122; 2019 (3) SA 379 (SCA) (21 September 2018)

Buffalo City Metropolitan Municipality v Nurcha Development Finance (Pty) Ltd and Others (378/2017) [2018] ZASCA 122; 2019 (3) SA 379 (SCA) (21 September 2018)

The Supreme Court of Appeal found that the conduct of Buffalo City Metropolitan Municipality in accepting and acting upon the irrevocable payment instruction, entering into the construction contract with New Boss after acknowledging the instruction, and making payments in accordance with it, constituted unequivocal...

Source-derived case information.

Citation
[2018] ZASCA 122
Parties
Appellant: Buffalo City Metropolitan Municipality; Respondent: Nurcha Development Finance (Pty) Ltd; Respondent: Tusk Construction Support Services (Pty) Ltd; Respondent: New Boss Construction CC
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Case Number
378/2017
Procedural Posture
Civil Appeal / Appeal From Eastern Cape Division of the High Court, East London Circuit
Outcome
Appeal dismissed with costs.
Judges
Lewis, Seriti, Makgoka, Mokgohloa, Nicholls
Legal Topics
Tacit Contract, Municipal Finance Management Act, Breach of Contract, Damages, Authority of Municipal Officials
Commercial and Corporate Civil Procedure Tacit Contract Municipal Finance Management Act Breach of Contract Damages Authority of Municipal Officials

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Buffalo City Metropolitan Municipality

Appellant

Nurcha Development Finance (Pty) Ltd

Respondent

Tusk Construction Support Services (Pty) Ltd

Respondent

New Boss Construction CC

Respondent

Procedural Posture

Civil Appeal / Appeal From Eastern Cape Division of the High Court, East London Circuit

  1. 1 Whether a tacit contract existed between Nurcha and Buffalo City Metropolitan Municipality regarding payment instructions.
  2. 2 Whether the conduct of the City amounted to unequivocal acceptance of the payment instruction.
  3. 3 Whether the City was liable for damages for breach of contract.

Ratio Decidendi

The Supreme Court of Appeal found that the conduct of Buffalo City Metropolitan Municipality in accepting and acting upon the irrevocable payment instruction, entering into the construction contract with New Boss after acknowledging the instruction, and making payments in accordance with it, constituted unequivocal conduct manifesting an intention to be bound by a tacit contract with Nurcha. The City's subsequent deviation from the payment instruction was acknowledged as a breach. The evidence, including the City's performance and lack of rebuttal to Nurcha's claims, established on a balance of probabilities that a tacit contract existed, obliging the City to pay progress payments into...

Court Disposition

Appeal dismissed with costs.

Orders

  • The appeal is dismissed with costs.