Buffalo City Metropolitan Municipality v THM Engineers EL CC and Others (CA344/2018) [2019] ZAECGHC 91 (20 September 2019)

Buffalo City Metropolitan Municipality v THM Engineers EL CC and Others (CA344/2018) [2019] ZAECGHC 91 (20 September 2019)

The court held that the respondents did not comply with the mandatory claims procedure set out in Clause 48 of the General Conditions of Contract for Construction Works (2004). The procedure requires a written claim, proper record of facts, and a ruling by the engineer, none of which occurred. The unique position of...

Source-derived case information.

Citation
[2019] ZAECGHC 91
Parties
Appellant: Buffalo City Metropolitan Municipality; Respondent: THM Engineers EL CC; Respondent: EL Gregory CC; Respondent: Bright Ideas CC
Court
Eastern Cape High Court, Grahamstown
Jurisdiction
South Africa
Case Number
CA344/2018
Procedural Posture
Civil Appeal / Appeal From Trial Court Judgment
Outcome
Appeal upheld. The respondents are not entitled to extension of time claims or additional legal costs. Only mediation costs are awarded.
Judges
E Revelas, MJ Lowe, NP Jaji
Legal Topics
Construction Contracts, Variation Orders, Extension of Time, Fiduciary Duties, Mediation Costs
Commercial and Corporate Civil Procedure Construction Contracts Variation Orders Extension of Time Fiduciary Duties Mediation Costs

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Buffalo City Metropolitan Municipality

Appellant

THM Engineers EL CC

Respondent

EL Gregory CC

Respondent

Bright Ideas CC

Respondent

Procedural Posture

Civil Appeal / Appeal From Trial Court Judgment

  1. 1 Whether the respondents complied with the mandatory claims procedure under Clause 48 of the General Conditions of Contract for extension of time and additional payment claims.
  2. 2 Whether the joint venture was entitled to payment for extension of time claims and additional legal costs.
  3. 3 Whether mediation costs were properly awarded to the respondents.

Ratio Decidendi

The court held that the respondents did not comply with the mandatory claims procedure set out in Clause 48 of the General Conditions of Contract for Construction Works (2004). The procedure requires a written claim, proper record of facts, and a ruling by the engineer, none of which occurred. The unique position of the first respondent as both engineer and contractor did not excuse non-compliance, and the court found that the contestation process is essential to protect the employer's interests. Mere notification or submission of a variation order was insufficient. Waiver or estoppel was not pleaded, and the court found no basis for their application. Accordingly, the joint venture was...

Court Disposition

Appeal upheld. The respondents are not entitled to extension of time claims or additional legal costs. Only mediation costs are awarded.

Orders

  • The appeal is upheld with costs on appeal, except for costs incurred for perusal of specified volumes.
  • The order of the court a quo is substituted: The defendant is to pay the plaintiffs, in their capacity as the joint venture, the amount of R8,500.00 in respect of mediation costs.