Download PDF

South Africa Judgment

South Gauteng High Court, Johannesburg

Cape Town 4 Properties (Pty) Ltd v Guardrisk Insurance Company Limited (2020/4130) [2021] ZAGPJHC 159 (26 May 2021)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court held that the respondent was liable to pay mora interest to the applicant for the period from the expiry of the seven-day demand period until payment was made. The respondent's reliance on public policy and the pendency of interdict proceedings did not absolve it from liability, as payment under a performance guarantee is intended to be made on demand, and the respondent's actions in paying before the finalisation of the interdict proceedings undermined its own defence. The court found that the non-payment by the respondent was the legal cause of the applicant's damages, entitling the applicant to mora interest at the prescribed rate. The respondent's arguments regarding constructive contempt and causation were rejected, and the applicant was awarded the relief claimed, including costs.

Court disposition

Application granted in favour of the applicant.

Orders

  • The respondent shall pay the amount of R1,920,849.61 to the applicant.
  • The respondent shall pay interest on the aforesaid amount calculated at 9.75% a tempore morae.
  • The respondent shall pay the costs of this application.

02

Material facts

Parties

Cape Town 4 Properties (Pty) Ltd

Applicant Counsel: Mr T N Hamman

Guardrisk Insurance Company Limited

Respondent Counsel: Adv. A. Lamplough

Amounts and remedies

  • Mora Interest Claimed: ZAR 1,920,849.61
  • Guaranteed Sum: ZAR 13,041,482.67
  • Interest Rate Awarded: ZAR 9.75

03

Procedural history

  1. Posture

    Civil Application / Opposed Application for Payment of Mora Interest Following Performance Guarantee Call

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant contends that it entered into a building agreement with TGP, which provided a performance guarantee issued by the respondent. Upon lawful demand, the respondent failed to pay the guaranteed sum within seven days, only paying months later. The applicant claims mora interest at the prescribed rate from the expiry of the seven-day period until payment, arguing that the respondent's delay entitles it to compensation for loss suffered due to late payment.
Respondent
The respondent argues that it was prevented from paying the guaranteed sum before 15 January 2019 due to legal proceedings brought by TGP, and that payment before the conclusion of those proceedings would have been contemptuous and against public policy. It further contends that its maximum liability is limited by the guarantee and that the damages suffered by the applicant were caused by TGP's actions, not its own delay. The respondent tenders payment of mora interest only for the period after the interdict proceedings concluded.

05

Court’s reasoning

  1. 01

    Guardrisk Insurance Co Ltd & Others v Kentz 2013 SCA 182 @ para 29

    Performance guarantees are commercial instruments intended to allow beneficiaries to call up payment without waiting for the final determination of accessory obligations. Accessory obligations are irrelevant to the obligation to pay under the guarantee.

  2. 02

    Land Agricultural Development Bank of South Africa v Reyton Estates (Pty) Ltd & Others 2013 (6) SA 319 (SCA)

    Mora interest is compensation for loss or damage resulting from a breach of contract, specifically mora debitoris, and is not payable in terms of an agreement but arises from late payment.

  3. 03

    Dormell Properties 282 CC v Renasa Insurance Co Ltd & Ano 2011 (1) SA 70 (SCA)

    Payment under a guarantee may be refused only where fraud is perpetrated to the knowledge of the finance institution.

  4. 04

    Gauteng Gambling Board & Another v MEC for Economic Development, Gauteng Provincial Government 2013 (5) SA 24 (SCA); City of Tshwane Metropolitan Municipality v Afriforum 2016 (6) SA 279 (CC)

    Public policy does not absolve a guarantor from liability for mora interest where payment is delayed due to pending interdict proceedings unless the guarantor reasonably believes an interim order will be granted.

06

Ratio, limits and disposition

Ratio decidendi

The court held that the respondent was liable to pay mora interest to the applicant for the period from the expiry of the seven-day demand period until payment was made. The respondent's reliance on public policy and the pendency of interdict proceedings did not absolve it from liability, as payment under a performance guarantee is intended to be made on demand, and the respondent's actions in paying before the finalisation of the interdict proceedings undermined its own defence. The court found that the non-payment by the respondent was the legal cause of the applicant's damages, entitling the applicant to mora interest at the prescribed rate. The respondent's arguments regarding constructive contempt and causation were rejected, and the applicant was awarded the relief claimed, including costs.

Obiter and limits

  • The court noted that nothing prevents a guarantor from withholding payment pending legal proceedings, but such a course of action carries the consequence of liability for mora interest.
  • The respondent's conduct in paying before the finalisation of the interdict proceedings contradicted its own argument regarding contempt and public policy.
  • The court reaffirmed the commercial purpose of performance guarantees, which is to provide prompt payment to beneficiaries without awaiting the resolution of underlying disputes.

Court disposition

Application granted in favour of the applicant.

  • The respondent shall pay the amount of R1,920,849.61 to the applicant.
  • The respondent shall pay interest on the aforesaid amount calculated at 9.75% a tempore morae.
  • The respondent shall pay the costs of this application.

Source and reliance status

South Gauteng High Court, Johannesburg

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

South Gauteng High Court, Johannesburg

Judgment

[2021] ZAGPJHC 159

IN

THE HIGH COURT OF SOUTH AFRICA

GAUTENG DIVISION, JOHANNESBURG

CASE NO: 2020/4130

NOT

REPORTABLE

NOT

OF INTEREST TO OTHER JUDGES

REVISED

DATE: 26 May 2021

In the matter between:

CAPE TOWN 4 PROPERTIES (PTY) LTD

Applicant

And

GUARDRISK

INSURANCE COMPANY LIMITED

Respondent

JUDGMENT

ALLY

AJ

INTRODUCTION

[1] This is an opposed application for the payment of the amount of R 1 920 849.61, being mora interest of 10.5% in terms of the Prescribed Rate of Interest Act, 1975, calculated on the amount of R 13 041 482.67 (hereinafter referred to as the “the Guaranteed Sum”) from 23 August 2018 to 17 January 2020.

[2] Applicant alleges that on 13 September 2016, it entered into a Principal Building Agreement with TGP Building (Pty) Ltd (hereinafter referred to as “TGP”) being a construction contractor, in terms of whereof the Applicant engaged TGP to construct a residential development of 310 flats in Observatory, Cape Town.

[3] Applicant alleges that on 8 February 2018, pursuant to the building agreement between the Applicant and TGP, TGP provided a performance guarantee[1] that had been issued by the Respondent under policy no. CG16/02680-02 in favour of the Applicant.

[4] According to Applicant, on 16 August 2018, it notified the Respondent that it was calling up the Guarantee in terms of clause 5.0 and 5.1 thereof.

[5] Applicant alleges that despite lawful demand, the Respondent failed and/or refused to pay the Guaranteed Sum within 7 (seven) days and only paid the amount of R 13 041 482.67 to the Applicant on 17 January 2019.

[6] Applicant submits that the amount of R 1 920 849.61 being claimed by the Applicant constitutes mora interest that is due and payable to the Applicant (calculated from 23 August 2018 to 17 January 2020 on at 10.5% on R 13 041 482.67), resultant from the Respondent’s failure and/or refusal to pay the Guaranteed Sum to the Applicant within 7 (seven) days of lawful demand.

[7] The Respondent contends that it was prevented from paying the Guaranteed Sum before 15 January 2019, due to the legal proceedings brought by TGP prior to the seven days mentioned above expiring. (Payment was made on 17 January 2019; the Respondent has tendered payment for the mora interest from 15 January 2019 to 17 January 2019).

[8] The Respondent contends further that it is not liable to pay mora interest due to the maximum liability clause contained in the Guarantee.

EVALUATION

AND ANALYSIS

[9] This application brings to the fore the issue of performance guarantees. However, this application raises the issue of whether on demand, an insurance company can refuse to pay only for the reason that an application interdicting them from paying has been launched. Basically this is the crux of this case.

[10] The Courts have expressed themselves on ‘performance guarantees’ and their nature and effect. I align myself with the sentiments expressed in those cases.[2] In my view the Applicant complied with the terms of the performance guarantee and in the circumstances expected to be paid following the expiry of the 7 (seven) days.

[11] Our Courts have, however, mentioned that payment may be refused where there is a fraud perpetrated to the knowledge of the ‘finance institution’.

[12] The Respondent in this matter has not raised the ‘fraud exception’ but raised in argument, the public policy defence in terms of which if Respondent had paid before the interdict proceedings were finalised, it would be contemptuous and against public policy.

[13] In my view, nothing stops a person in the shoes of the Respondent from taking a course as was taken by them in this matter, namely, by not paying the amount claimed on demand. However, the Respondent must then face the consequences of that course of action.

[14] I also align myself with the sentiments of Theron JA, as she then was:[3]

“In my view this principle is based on sound reason. It underscores the commercial nature of performance guarantees. In determining whether payment should be made on such a guarantee, accessory obligations are of no consequence. The very purpose of the guarantee is so that the beneficiary can call up the guarantee without having to wait for the final determination of its rights in terms of accessory obligations. To find otherwise, would involve an unjustified paradigm shift and defeat the commercial purpose of performance guarantees.”

[15] Whilst our Courts are jealous of the jurisdiction to adjudicate matters unless good grounds exist for an ouster, it is my view that the intervening issue of an interdict application, does not avail the Respondent in this case, in the sense that, it must face the consequences as stated above and that consequence is that they must pay mora interest to the Applicant for the reason that they did not pay within the timeframe demanded.

[16] Respondent’s Counsel enjoined the Court to consider the issue of the competence of the Court to adjudicate applications and actions lodged with it. In this regard, so the argument went, it would be contemptuous of a litigant to decide on its own before allowing the Court to make a decision.

[17] Furthermore, the Respondent contended that non-payment was not the legal cause of the damages suffered by the Applicant but that it was the actions of TGP by instituting interdict proceedings that caused such damages.

[18] The third contention on behalf of the Respondent was the public policy issue which has been dealt with above.

[19] With regard to the argument by the Respondent relating to its possible constructive contemptuous conduct in paying prior to adjudication by the Court, I am of the view that there is no substance in the argument. I am in agreement with Counsel for the Applicant that, firstly, Respondent’s conduct paying the amount in January 2020 before Part B of the interdict proceedings having been pronounced upon, belies their defence. In other words, are they not in contempt of court, on their argument, by paying the amount, demanded, in January 2020, before a Court pronounced itself? This clear contradiction works against the Respondent.

[20] In my view, the paying of the amount demanded, would not amount to an intention to defeat the course of justice by taking away the Court’s competence of the Court as expressed in Gauteng Gambling Board & Another v MEC for Economic Development, Gauteng Provincial Government.[4]

[21] I further agree with the submission by Applicant’s Counsel that the Respondent did not make out a case on the papers that they knew or reasonably believed that the interim order would be granted by the Court which is one of the requirements set out in the Gauteng Gambling Board case and City of Tshwane Metropolitan Municipality v Afriforum[5].

[22] I turn now to the causation argument raised by the Respondent. As I understand this submission, it states that the non-payment by the Respondent of the amount demanded in terms of the ‘performance guarantee’ was not the cause of any damages suffered by the Applicant but that the application proceedings launched by the TGP resulted in Respondent not paying within the timeframe mentioned in the demand letter. I am satisfied that the non-payment of the amount as demanded is the causa causans of the Applicant not being placed in a position it would have been had the amount been paid on time and therefore entitles it to mora interest as described in Land Agricultural Development Bank of South Africa v Reyton Estates (Pty) Ltd & Others[6] where it was stated:

“Mora interest, on the other hand, is something fundamentally different. It is not payable in terms of an agreement, but constitutes compensation for loss or damage resulting from a breach of contract, specifically mora debitoris.”

[23] The Respondent as part of their submission argued that if they were liable for mora interest such mora interest must be calculated from 15 January 2020 – 17 January 2020.

[24] In my view the liability for mora interest arises from the date of expiry of the 7 (seven) days given to the Respondent to pay and in the amount as claimed by the Applicant in accordance and alignment with the view expressed above regarding placing the Applicant in the same position it would have been had the amount been paid on time.

COSTS

[25] There is no need to deviate from the norm that costs should follow the result and none was argued. Therefore, in my view, the Respondent is liable for the costs of the Applicant.

[26] Accordingly the Applicant is entitled to the relief claimed in the Notice of Motion with costs.

In the result the following Order shall issue:

1) The Respondent shall pay the amount of R1, 920, 849, 61 to the Applicant;

2) The Respondent shall pay interest on the aforesaid amount calculated at 9.75% a tempore morae;

3) Respondent to pay the costs of this application

ACTING

JUDGE OF THE HIGH COURT

GAUTENG DIVISION OF THE HIGH COURT, JOHANNESBURG

Electronically submitted therefore unsigned

Delivered: This judgement was prepared and authored by the Judge whose name is reflected and is handed down electronically by circulation to the Parties/their legal representatives by email and by uploading it to the electronic file of this matter on CaseLines. The date for hand-down is deemed to be 27 May 2021.

Date of hearing: 10 September 2020

Date of judgment: 26 May 2021

Appearances:

Applicant :

Mr T N Hamman

Du Toit Sanchez Moodley Inc

Stonemill Office Park, Ground Floor

Kiepersol House No 2

300 Acacia Road

Randburg

jaco@hahnlaw.co.za

merilynn@hahnlaw.co.za

Respondent : Adv. A. Lamplough

ENSAFRICA

The MARC, Tower 1

129 Rivonia Road

Sandton

rscott@ENSafrica.com

zsher@ENSafrica.com

[1] Caselines: 001 - 053

[2] Dormell Properties 282 CC v Renasa Insurance Co Ltd & Ano 2011 (1) SA 70 (SCA) @ para 61 et seq Lombard Ins Co Ltd v Landmark Holdings (Pty) Ltd 2010 (2) SA 86 (SCA) @ para 20 Edward Owen v Barclays Bank International 1978 (1) All ER 976 (CA) @ 983 b-d First Rand Bank v Brera 2013 SCA 25 @ para 2 State Bank of India v Denel SOC Ltd 2014 SA 212 (SCA) @ para 8-9

[2] Dormell Properties 282 CC v Renasa Insurance Co Ltd & Ano 2011 (1) SA 70 (SCA) @ para 61 et seq

Lombard Ins Co Ltd v Landmark Holdings (Pty) Ltd 2010 (2) SA 86 (SCA) @ para 20

Edward Owen v Barclays Bank International 1978 (1) All ER 976 (CA) @ 983 b-d

First Rand Bank v Brera 2013 SCA 25 @ para 2

State Bank of India v Denel SOC Ltd 2014 SA 212 (SCA) @ para 8-9

[3] Guardrisk Insurance Co Ltd & Others v Kentz 2013 SCA 182 @ para 29

[4] 2013 (5) SA 24 (SCA)

[5] 2016 (6) SA 279 (CC)

[6] 2013 (6) SA 319 (SCA) Bellairs v Hodnett 1978 (1) SA 1109 (A) @1145 D-G and 1146H – 1147A

[6] 2013 (6) SA 319 (SCA)

Bellairs v Hodnett 1978 (1) SA 1109 (A) @1145 D-G and 1146H – 1147A

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Dormell Properties 282 CC v Renasa Insurance Co Ltd & Ano 2011 (1) SA 70 (SCA)

Case cited

Lombard Ins Co Ltd v Landmark Holdings (Pty) Ltd 2010 (2) SA 86 (SCA)

Case cited

Edward Owen v Barclays Bank International 1978 (1) All ER 976 (CA)

Case cited

First Rand Bank v Brera 2013 SCA 25

Case cited

State Bank of India v Denel SOC Ltd 2014 SA 212 (SCA)

Case cited

Guardrisk Insurance Co Ltd & Others v Kentz 2013 SCA 182

Case cited

Gauteng Gambling Board & Another v MEC for Economic Development, Gauteng Provincial Government 2013 (5) SA 24 (SCA)

Case cited

City of Tshwane Metropolitan Municipality v Afriforum 2016 (6) SA 279 (CC)

Case cited

Land Agricultural Development Bank of South Africa v Reyton Estates (Pty) Ltd & Others 2013 (6) SA 319 (SCA)

Case cited

Bellairs v Hodnett 1978 (1) SA 1109 (A)

Case cited

Prescribed Rate of Interest Act, 1975

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.