Chapman Fund Manager (Pty) Ltd v Minister of Public Works and Another (25558/2021) [2024] ZAGPPHC 273 (26 March 2024)

Chapman Fund Manager (Pty) Ltd v Minister of Public Works and Another (25558/2021) [2024] ZAGPPHC 273 (26 March 2024)

The court found that the extension of the contract was lawfully effected in accordance with the terms of the original agreement, which expressly provided for such an extension at the discretion of the first defendant and subject to mutual agreement. The evidence established that the extension was properly...

Source-derived case information.

Citation
[2024] ZAGPPHC 273
Parties
Plaintiff: Chapman Fund Manager (Pty) Ltd; Defendant: Minister of Public Works; Defendant: Director-General of Public Works
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
25558/2021
Procedural Posture
Civil Trial / Separation of Issues Under Rule 33(4); Judgment on Legality of Contract Extension
Outcome
The separated issue of illegality is decided in favour of the plaintiff; the contract extension is declared lawful.
Judges
C J van der Westhuizen
Legal Topics
Public Procurement, Contract Extension, Section 217 Constitution, Tender Award, Onus of Proof, Practice Note 8 Pfma
Commercial and Corporate Civil Procedure Constitutional Law Public Procurement Contract Extension Section 217 Constitution Tender Award Onus of Proof +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2
Sign in to unlock

Parties

Chapman Fund Manager (Pty) Ltd

Plaintiff

Minister of Public Works

Defendant

Director-General of Public Works

Defendant

Procedural Posture

Civil Trial / Separation of Issues Under Rule 33(4); Judgment on Legality of Contract Extension

  1. 1 Whether the extension of the contract between the parties was lawful and complied with section 217 of the Constitution.
  2. 2 Whether the extension required a new public tender process under procurement law.
  3. 3 Whether the defendants discharged the onus of proving illegality of the contract extension.

Ratio Decidendi

The court found that the extension of the contract was lawfully effected in accordance with the terms of the original agreement, which expressly provided for such an extension at the discretion of the first defendant and subject to mutual agreement. The evidence established that the extension was properly considered, approved by the Bid Committee, and accepted in writing by both parties. The defendants failed to present credible evidence of any breach of section 217(1) of the Constitution or any irregularity in the extension process. The court accepted the plaintiff's reliance on the 3P Consulting precedent, holding that no new procurement process was required for an extension on the same...

Court Disposition

The separated issue of illegality is decided in favour of the plaintiff; the contract extension is declared lawful.

Orders

  • It is declared that, on or about 11 April 2008, the parties lawfully, by agreement, extended the contract, following on the lawful award of Public Tender number P[...] to the plaintiff, on the same terms and conditions for an additional period of 10 years calculated from 20 May 2010 to 20 May 2020.
  • The defendants are ordered to pay the costs of the trial from Wednesday 6 March 2024 to Thursday 14 May 2024, including the costs consequent upon the employment of two counsel.