City of Tshwane Metropolitan Municipality v Moipone Group of Companies (Pty) Ltd and Another (27752/2017) [2024] ZAGPPHC 456 (21 May 2024)

City of Tshwane Metropolitan Municipality v Moipone Group of Companies (Pty) Ltd and Another (27752/2017) [2024] ZAGPPHC 456 (21 May 2024)

The court found that the plaintiff, City of Tshwane, delayed unreasonably in instituting review proceedings to set aside its own procurement decision and the PPP Agreements with the first defendant. The delay spanned several years, during which the plaintiff was aware of the relevant facts and alleged irregularities...

Source-derived case information.

Citation
[2024] ZAGPPHC 456
Parties
Plaintiff: City of Tshwane Metropolitan Municipality; Defendant: Moipone Group of Companies (Pty) Ltd; Defendant: Absa Vehicle Management Solutions (Pty) Ltd
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
27752/2017
Procedural Posture
Review Application / Trial Judgment Following Referral From Motion Proceedings
Outcome
Plaintiff's action dismissed with costs, including costs of the review application and costs of three counsel for the first defendant and two counsel for the second defendant.
Judges
Collis
Legal Topics
Municipal Procurement, Public Private Partnerships, Unreasonable Delay, Legality Review, Condonation, Fraudulent Misrepresentation
Administrative Law Commercial and Corporate Civil Procedure Municipal Procurement Public Private Partnerships Unreasonable Delay Legality Review Condonation +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

City of Tshwane Metropolitan Municipality

Plaintiff

Moipone Group of Companies (Pty) Ltd

Defendant

Absa Vehicle Management Solutions (Pty) Ltd

Defendant

Procedural Posture

Review Application / Trial Judgment Following Referral From Motion Proceedings

  1. 1 Whether the plaintiff's delay in instituting review proceedings to set aside its own procurement decision was unreasonable and fatal to its claim.
  2. 2 Whether the PPP Agreements concluded between the plaintiff and first defendant were unlawful due to non-compliance with statutory procurement requirements and fraud.
  3. 3 Whether the rights of the second defendant, as an innocent third party financier, should be preserved despite the alleged invalidity of the PPP Agreements.

Ratio Decidendi

The court found that the plaintiff, City of Tshwane, delayed unreasonably in instituting review proceedings to set aside its own procurement decision and the PPP Agreements with the first defendant. The delay spanned several years, during which the plaintiff was aware of the relevant facts and alleged irregularities but failed to act. The explanation for the delay was inadequate, and the plaintiff did not seek condonation. The court held that such excessive and unexplained delay is fatal to legality reviews, particularly where third parties, such as the second defendant (Absa Vehicle Management Solutions), have acted in reliance on the impugned contracts and would suffer prejudice if the...

Court Disposition

Plaintiff's action dismissed with costs, including costs of the review application and costs of three counsel for the first defendant and two counsel for the second defendant.

Orders

  • The plaintiff's action is dismissed with costs, including the costs of the review application and costs of three counsel for the first defendant and two counsel for the second defendant.
  • The rights acquired by the second defendant in terms of the PPP Agreements and related finance agreements are preserved and are not set aside.