Clifford Harris (South West) (Pty) Ltd. v Government of the Republic of South Africa (81/83) [1986] ZASCA 22 (24 March 1986)

Clifford Harris (South West) (Pty) Ltd. v Government of the Republic of South Africa (81/83) [1986] ZASCA 22 (24 March 1986)

The court held that the appellant was not entitled to the claimed 'extra-over' payment because it failed to comply with the contract's requirements for classification and measurement of class A material prior to excavation. The contract implicitly required the upper horizon of class A material to be established...

Source-derived case information.

Citation
[1986] ZASCA 22
Parties
Appellant: Clifford Harris (South West) (Proprietary) Ltd.; Respondent: Government of the Republic of South Africa
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Case Number
81/83
Procedural Posture
Civil Appeal / Appeal From the Transvaal Provincial Division
Outcome
Appeal dismissed with costs, including costs of two counsel.
Judges
Trengove, Van Heerden, Boshoff, Jacobs, Smalberger
Legal Topics
Construction Contracts, Interpretation of Contracts, Extra Over Payments, Estoppel, Measurement of Quantities
Commercial and Corporate Civil Procedure Construction Contracts Interpretation of Contracts Extra Over Payments Estoppel Measurement of Quantities

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Clifford Harris (South West) (Proprietary) Ltd.

Appellant

Government of the Republic of South Africa

Respondent

Procedural Posture

Civil Appeal / Appeal From the Transvaal Provincial Division

  1. 1 Whether the appellant was entitled to an 'extra-over' payment of R3,00 per cubic metre for class A material excavated from borrow pits and used in fills under the contract.
  2. 2 Whether the classification and measurement of class A material should have occurred prior to excavation as required by the contract.
  3. 3 Whether the appellant's failure to notify the Resident Engineer and establish the upper horizon of class A material precluded its claim for payment.

Ratio Decidendi

The court held that the appellant was not entitled to the claimed 'extra-over' payment because it failed to comply with the contract's requirements for classification and measurement of class A material prior to excavation. The contract implicitly required the upper horizon of class A material to be established before excavation, which the appellant did not do. Had the appellant notified the Resident Engineer upon encountering class A material, the Engineer would have directed the use of class B material from other borrow pits, avoiding the need for 'extra-over' payment. The subsequent site instructions and tests did not constitute an agreement to accept the appellant's claim under the...

Court Disposition

Appeal dismissed with costs, including costs of two counsel.

Orders

  • The appeal is dismissed with costs, including the costs incurred by the employment of two counsel.