Colvic Marketing & Engineering (Pty) Ltd v Minister of Public Works and Infrastructure and Others (21819/2020) [2022] ZAGPPHC 375 (9 June 2022)

Colvic Marketing & Engineering (Pty) Ltd v Minister of Public Works and Infrastructure and Others (21819/2020) [2022] ZAGPPHC 375 (9 June 2022)

The court found that the applicant launched the review application outside the 180-day period prescribed by PAJA, and the delay was per se unreasonable. The applicant failed to provide a full and reasonable explanation for the delay, both in launching the review and in filing the replying affidavit, which was...

Source-derived case information.

Citation
[2022] ZAGPPHC 375
Parties
Applicant: Colvic Marketing & Engineering (Pty) Ltd; Respondent: Minister of Public Works and Infrastructure; Respondent: BSE Distributors Western Cape CC; Respondent: ECM Technologies (Pty) Ltd; Respondent: Blue Apple Trading CC; Respondent: Matakanye Construction CC; Respondent: BSE Distributions CC
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
21819/2020
Procedural Posture
Review Application / Judgment on Condonation and Review
Outcome
Application for condonation dismissed; costs awarded against applicant.
Judges
AC Basson
Legal Topics
Promotion of Administrative Justice Act, Public Procurement, Condonation for Late Filing, Judicial Review, Tender Award, Delay Rule
Administrative Law Civil Procedure Promotion of Administrative Justice Act Public Procurement Condonation for Late Filing Judicial Review Tender Award Delay Rule

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 7 Party arguments 2
Sign in to unlock

Parties

Colvic Marketing & Engineering (Pty) Ltd

Applicant

Minister of Public Works and Infrastructure

Respondent

BSE Distributors Western Cape CC

Respondent

ECM Technologies (Pty) Ltd

Respondent

Blue Apple Trading CC

Respondent

Matakanye Construction CC

Respondent

BSE Distributions CC

Respondent

Procedural Posture

Review Application / Judgment on Condonation and Review

  1. 1 Whether the applicant's delay in launching the review application should be condoned under section 9 of PAJA.
  2. 2 Whether the Department's award of the tender to BSE was lawful and rational.
  3. 3 Whether the applicant's bid was unlawfully rejected based on the certification of artisan qualifications.

Ratio Decidendi

The court found that the applicant launched the review application outside the 180-day period prescribed by PAJA, and the delay was per se unreasonable. The applicant failed to provide a full and reasonable explanation for the delay, both in launching the review and in filing the replying affidavit, which was substantially late. The prejudice to the Department, BSE, and affected communities was significant, given that most of the contract period had elapsed and 14 bridges had already been manufactured. The interests of justice did not warrant condonation of the delay. The administrative action, even if unlawful, was rendered unassailable due to the delay and the advanced stage of contract...

Court Disposition

Application for condonation dismissed; costs awarded against applicant.

Orders

  • The application for condonation for the late filing of the review application is dismissed.
  • The applicant is ordered to pay the costs of the first and sixth respondents, including the costs of two counsel where so employed.