Compagnie Interafricaine de Travaux v South African Transport Services and Others (680/89) [1991] ZASCA 16; 1991 (4) SA 217 (AD); [1991] 2 All SA 155 (A) (21 March 1991)

Compagnie Interafricaine de Travaux v South African Transport Services and Others (680/89) [1991] ZASCA 16; 1991 (4) SA 217 (AD); [1991] 2 All SA 155 (A) (21 March 1991)

Clause 2(b) of the general conditions of contract entitles the contractor to claim reasonable remuneration for additional work or expense caused by adverse subsurface conditions which, in the opinion of the Engineer, could not reasonably have been foreseen. The quantification of such a claim is not governed by the...

Source-derived case information.

Citation
[1991] ZASCA 16
Parties
Appellant: Compagnie Interafricaine de Travaux; Respondent: South African Transport Services; Respondent: President of the South African Institution of Civil Engineers; Respondent: Resident Engineer of the South African Transport Services (Construction) Belville; Respondent: Chief Civil Engineer South African Transport Services
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Case Number
680/89
Procedural Posture
Civil Appeal / Appeal From Dismissal of Application for Declaratory Relief in the Witwatersrand Local Division
Outcome
Appeal allowed. Declaratory relief granted in favour of the appellant. Costs awarded to the appellant, including costs of three counsel.
Judges
Corbett, Hefer, Vivier, Milne, Eksteen
Legal Topics
Construction Contracts, Implied Terms, Quantification of Claims, Arbitration Clauses, Declaratory Relief
Commercial and Corporate Civil Procedure Construction Contracts Implied Terms Quantification of Claims Arbitration Clauses Declaratory Relief

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Compagnie Interafricaine de Travaux

Appellant

South African Transport Services

Respondent

President of the South African Institution of Civil Engineers

Respondent

Resident Engineer of the South African Transport Services (Construction) Belville

Respondent

Chief Civil Engineer South African Transport Services

Respondent

Procedural Posture

Civil Appeal / Appeal From Dismissal of Application for Declaratory Relief in the Witwatersrand Local Division

  1. 1 Does clause 2(b) of the general conditions of contract entitle the contractor to reasonable remuneration when adverse subsurface conditions not reasonably foreseeable are encountered?
  2. 2 Is the quantification of such a claim governed by the variation order and rate adjustment procedures in clauses 35 and 50, or does the law imply a right to reasonable remuneration?
  3. 3 Was the Engineer entitled to refuse to make a ruling on the contractor's claims for reasonable remuneration under clause 2(b)?

Ratio Decidendi

Clause 2(b) of the general conditions of contract entitles the contractor to claim reasonable remuneration for additional work or expense caused by adverse subsurface conditions which, in the opinion of the Engineer, could not reasonably have been foreseen. The quantification of such a claim is not governed by the variation order and rate adjustment procedures in clauses 35 and 50, as those clauses apply only to ordered alterations, extras, additions, or omissions. Instead, the law implies a right to reasonable remuneration in the absence of a contractual mechanism for quantification. The Engineer and Chief Civil Engineer are obliged to decide the contractor's claims on the information...

Court Disposition

Appeal allowed. Declaratory relief granted in favour of the appellant. Costs awarded to the appellant, including costs of three counsel.

Orders

  • It is declared that, on the assumption that materials, methods of construction and/or site conditions were different from those assumed by the applicant in tendering for the contract, and that this was due to adverse sub-surface conditions which, in the opinion of the Engineer, Chief Civil Engineer, or any...
  • The Engineer was not entitled to refuse to make a ruling on the applicant's main tunnel and eastern cut claims; he must either admit or reject them.