Competition Commission v B And E International (Pty) Ltd (019091) [2014] ZACT 17 (24 July 2014)
The Tribunal found that B & E International (Pty) Ltd admitted to engaging in collusive tendering by providing a cover price to Grinaker-LTA in respect of the Braamhoek Quarry Dam tender, thereby contravening section 4(1)(b)(iii) of the Competition Act. The respondent cooperated fully with the Commission, ceased the prohibited conduct, and undertook to implement a compliance programme. The Tribunal was satisfied that the consent agreement, including the administrative penalty of R8,158,447 (representing 2% of annual turnover), was appropriate and in accordance with the Act. The Tribunal confirmed the consent agreement as an order, thereby concluding all proceedings between the parties in...
- Citation
- [2014] ZACT 17
- Parties
- Applicant: Competition Commission; Respondent: B & E International (Pty) Ltd
- Court
- Competition Tribunal
- Jurisdiction
- South Africa
- Judgment Date
- 24 July 2014
- Case Number
- 019091
- Procedural Posture
- Consent Order Application / Order Confirming Consent Agreement
- Outcome
- Consent agreement confirmed as an order of the Tribunal. Administrative penalty imposed.
- Judges
- N Manoim, T Madima, A Roskam
- Legal Topics
- Collusive Tendering, Price Fixing, Market Allocation, Administrative Penalty, Consent Agreement
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Competition Commission
Applicant
B & E International (Pty) Ltd
Respondent
Procedural Posture
Consent Order Application / Order Confirming Consent Agreement
Legal Issues
- 1 Whether B & E International (Pty) Ltd contravened section 4(1)(b)(iii) of the Competition Act by engaging in collusive tendering.
- 2 Whether the consent agreement between the Competition Commission and B & E International (Pty) Ltd should be confirmed as an order of the Tribunal.
- 3 Whether the administrative penalty imposed is appropriate and in accordance with the Act.
Ratio Decidendi
The Tribunal found that B & E International (Pty) Ltd admitted to engaging in collusive tendering by providing a cover price to Grinaker-LTA in respect of the Braamhoek Quarry Dam tender, thereby contravening section 4(1)(b)(iii) of the Competition Act. The respondent cooperated fully with the Commission, ceased the prohibited conduct, and undertook to implement a compliance programme. The Tribunal was satisfied that the consent agreement, including the administrative penalty of R8,158,447 (representing 2% of annual turnover), was appropriate and in accordance with the Act. The Tribunal confirmed the consent agreement as an order, thereby concluding all proceedings between the parties in...
Court Disposition
Consent agreement confirmed as an order of the Tribunal. Administrative penalty imposed.
Orders
- The consent agreement between the Competition Commission and B & E International (Pty) Ltd is confirmed as an order of the Tribunal.
- B & E International (Pty) Ltd shall pay an administrative penalty of R8,158,447 to the Competition Commission within 30 days of confirmation of the order.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment