Constantine Panayotides v Mayor of the Steve Tshwete Local Municipality N.O and Others (68028/2012) [2015] ZAGPPHC 429 (1 July 2015)

Constantine Panayotides v Mayor of the Steve Tshwete Local Municipality N.O and Others (68028/2012) [2015] ZAGPPHC 429 (1 July 2015)

The court held that the second respondent is obliged to comply with the Magistrate's Court order dated 1 August 2008, which requires the demolition of the building at 13A Laver Street, Middelburg. In the event of non-compliance within one month, the Sheriff is authorised to execute the demolition. The conduct of the...

Source-derived case information.

Citation
[2015] ZAGPPHC 429
Parties
Applicant: Constantine Panayotides; Respondent: Mayor of the Steve Tshwete Local Municipality N.O; Respondent: Steve Tshwete Local Municipality; Respondent: MEC for the Provincial Government of Mpumalanga; Respondent: William Jacobus Harrington; Respondent: Nexbed CC
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
68028/2012
Procedural Posture
Civil Application / Post Judgment Order
Outcome
Application granted; demolition order enforced; costs awarded on attorney and client scale including costs of two counsel.
Judges
C Pretorius
Legal Topics
Demolition Order, Enforcement of Magistrates Court Order, Costs Award
Land and Property Civil Procedure Demolition Order Enforcement of Magistrates Court Order Costs Award

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Party arguments 2
Sign in to unlock

Parties

Constantine Panayotides

Applicant

Mayor of the Steve Tshwete Local Municipality N.O

Respondent

Steve Tshwete Local Municipality

Respondent

MEC for the Provincial Government of Mpumalanga

Respondent

William Jacobus Harrington

Respondent

Nexbed CC

Respondent

Procedural Posture

Civil Application / Post Judgment Order

  1. 1 Whether the second respondent is obliged to comply with the Magistrate's Court order to demolish the building at 13A Laver Street, Middelburg.
  2. 2 Whether the Sheriff should be authorised to enforce the demolition if the second respondent fails to comply.
  3. 3 Whether costs should be awarded on an attorney and client scale, including costs of two counsel.

Ratio Decidendi

The court held that the second respondent is obliged to comply with the Magistrate's Court order dated 1 August 2008, which requires the demolition of the building at 13A Laver Street, Middelburg. In the event of non-compliance within one month, the Sheriff is authorised to execute the demolition. The conduct of the second and fourth respondents justified an award of costs on an attorney and client scale, including the costs of two counsel, to be paid jointly and severally.

Court Disposition

Application granted; demolition order enforced; costs awarded on attorney and client scale including costs of two counsel.

Orders

  • The second respondent is ordered to give effect to the Magistrate's Court order dated 1 August 2008 by demolishing the building on the property situated at 13A Laver Street, Middelburg, Mpumalanga.
  • If the second respondent fails to comply within one month, the Sheriff is authorised to take any steps necessary to give effect to this order.