DBH Construction (Edms) Bpk v JF Perreira h/a F P Carpenters (26860/09) [2009] ZAGPPHC 366 (3 December 2009)
The court found that the plaintiff had paid the defendant a total of R168,000 for roofing work at erf 245 Stone Ridge Estate, exceeding the contract price of R160,500. The defendant failed to complete the work and performed it defectively. Expert evidence established the value of completed work at R41,221.29 and remedial costs at R6,549.68. The defendant's explanations regarding payments and the transfer of the R50,000 deposit were rejected as unconvincing and contradicted by documentary and witness evidence. The defendant also failed to deliver proper VAT invoices, which he admitted in testimony. The court found the defendant's conduct in litigation to be dishonest and obstructive,...
- Citation
- [2009] ZAGPPHC 366
- Parties
- Plaintiff: DBH Construction (Edms) Bpk; Defendant: JF Perreira h/a F P Carpenters
- Court
- North Gauteng High Court, Pretoria
- Jurisdiction
- South Africa
- Judgment Date
- 3 December 2009
- Case Number
- 26860/09
- Procedural Posture
- Civil Trial / Final Judgment
- Outcome
- Judgment for the plaintiff with full relief granted.
- Judges
- W J van der Merwe
- Legal Topics
- Breach of Contract, Specific Performance, Damages Assessment, Vat Invoices, Costs Order
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
DBH Construction (Edms) Bpk
Plaintiff
JF Perreira h/a F P Carpenters
Defendant
Procedural Posture
Civil Trial / Final Judgment
Legal Issues
- 1 Whether the defendant breached the contract for roofing works at erf 245 Stone Ridge Estate.
- 2 Whether the plaintiff is entitled to payment of R125,738.39 and interest.
- 3 Whether the defendant must deliver VAT invoices for three properties.
Ratio Decidendi
The court found that the plaintiff had paid the defendant a total of R168,000 for roofing work at erf 245 Stone Ridge Estate, exceeding the contract price of R160,500. The defendant failed to complete the work and performed it defectively. Expert evidence established the value of completed work at R41,221.29 and remedial costs at R6,549.68. The defendant's explanations regarding payments and the transfer of the R50,000 deposit were rejected as unconvincing and contradicted by documentary and witness evidence. The defendant also failed to deliver proper VAT invoices, which he admitted in testimony. The court found the defendant's conduct in litigation to be dishonest and obstructive,...
Court Disposition
Judgment for the plaintiff with full relief granted.
Orders
- The defendant must pay the plaintiff R125,738.39.
- The defendant must pay interest on R125,738.39 at 15.5% per annum from 11 May 2009 until payment.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment