De Mona Eindomme CC v Department of Water Affairs (WT 24/11/2010) [2011] ZAWT 3 (19 May 2011)
The Water Tribunal found that the Applicant lodged the appeal approximately one year late and failed to provide any reasonable or substantive explanation for the delay. The Tribunal was not convinced by the Applicant's argument that the change in ownership during the verification process justified condonation. The Tribunal held that the verification process under section 35 of the National Water Act is directed at the person claiming entitlement to water use, not necessarily the owner, and there is no legal obligation to restart the process upon a change in ownership. The Tribunal was not satisfied that the Applicant demonstrated prospects of success or that the delay was excusable. No...
- Citation
- [2011] ZAWT 3
- Parties
- Applicant: De Mona Eindomme CC; Respondent: Department of Water Affairs
- Court
- Water Tribunal
- Jurisdiction
- South Africa
- Judgment Date
- 19 May 2011
- Case Number
- WT 24/11/2010
- Procedural Posture
- Condonation Application / Ruling on Condonation
- Outcome
- Condonation for the late lodging of the appeal is refused. The file before the Water Tribunal is to be closed.
- Judges
- W Singo, H Thompson, A S Makhanya
- Legal Topics
- National Water Act, Condonation, Late Appeal, Verification of Water Use
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
De Mona Eindomme CC
Applicant
Department of Water Affairs
Respondent
Procedural Posture
Condonation Application / Ruling on Condonation
Legal Issues
- 1 Whether there is a good reason to condone the late lodging of an appeal by the Applicant against the Respondent's decision dated 23 September 2008.
- 2 Whether the Applicant provided a reasonable explanation for the delay in lodging the appeal.
- 3 Whether the Applicant has prospects of success in the appeal if condonation is granted.
Ratio Decidendi
The Water Tribunal found that the Applicant lodged the appeal approximately one year late and failed to provide any reasonable or substantive explanation for the delay. The Tribunal was not convinced by the Applicant's argument that the change in ownership during the verification process justified condonation. The Tribunal held that the verification process under section 35 of the National Water Act is directed at the person claiming entitlement to water use, not necessarily the owner, and there is no legal obligation to restart the process upon a change in ownership. The Tribunal was not satisfied that the Applicant demonstrated prospects of success or that the delay was excusable. No...
Court Disposition
Condonation for the late lodging of the appeal is refused. The file before the Water Tribunal is to be closed.
Orders
- Condonation for the late lodging of the appeal by the Applicant is refused.
- The file before the Water Tribunal is closed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment