Desertmoon Trading 355 CC v Clyde Bergeman Africa (Pty) Ltd and Another (63193/15) [2015] ZAGPPHC 914 (4 September 2015)

Desertmoon Trading 355 CC v Clyde Bergeman Africa (Pty) Ltd and Another (63193/15) [2015] ZAGPPHC 914 (4 September 2015)

The court found that the guarantee in question was a demand guarantee, not subject to the conditional requirements argued by the applicant, because the first respondent terminated the contract under clause 15.2(b), which was not affected by the amendment to clause 4.2. The guarantee's wording made it clear that...

Source-derived case information.

Citation
[2015] ZAGPPHC 914
Parties
Applicant: Desertmoon Trading 355 CC; Respondent: Clyde Bergeman Africa (Pty) Ltd; Respondent: Hollard Insurance Company Limited
Court
North Gauteng High Court, Pretoria
Jurisdiction
South Africa
Case Number
63193/15
Procedural Posture
Urgent Application / Final Interdict Application in Urgent Court
Outcome
Application dismissed with costs, including costs of two counsel where so employed.
Judges
Ranchod
Legal Topics
Performance Guarantee, Demand Guarantee, Fraud Exception, Interdict, Construction Contracts
Commercial and Corporate Civil Procedure Performance Guarantee Demand Guarantee Fraud Exception Interdict Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2
Sign in to unlock

Parties

Desertmoon Trading 355 CC

Applicant

Clyde Bergeman Africa (Pty) Ltd

Respondent

Hollard Insurance Company Limited

Respondent

Procedural Posture

Urgent Application / Final Interdict Application in Urgent Court

  1. 1 Whether the performance guarantee issued by the second respondent is a demand guarantee payable irrespective of contractual disputes between the applicant and first respondent.
  2. 2 Whether the first respondent was entitled to call up the guarantee under the terms of the amended contract.
  3. 3 Whether the call on the guarantee by the first respondent was fraudulent.

Ratio Decidendi

The court found that the guarantee in question was a demand guarantee, not subject to the conditional requirements argued by the applicant, because the first respondent terminated the contract under clause 15.2(b), which was not affected by the amendment to clause 4.2. The guarantee's wording made it clear that payment could not be delayed by disputes between the contractor and subcontractor. The applicant failed to discharge the onus of proving fraud on a balance of probabilities. Therefore, the first respondent was entitled to call up the guarantee, and the application for an interdict was dismissed.

Court Disposition

Application dismissed with costs, including costs of two counsel where so employed.

Orders

  • The application is dismissed with costs, including the costs of two counsel where so employed.