DFS Flemingo SA Pty (Ltd) v Airport Company SA (Pty) Ltd and Others (59131/09) [2009] ZAGPPHC 348 (11 December 2009)
The court found that the applicant was entitled to fair and just administrative procedure in the tender process. The refusal to provide requested information and the lack of disclosure of criteria weightings placed the applicant at a disadvantage compared to the incumbent, undermining the fairness and transparency...
Source-derived case information.
- Citation
- [2009] ZAGPPHC 348
- Parties
- Applicant: DFS Flemingo SA Pty (Ltd); Respondent: Airport Company SA (Pty) Ltd; Respondent: Big Five Duty Free (Pty) Ltd; Respondent: The Tender Board of ACSA
- Court
- North Gauteng High Court, Pretoria
- Jurisdiction
- South Africa
- Case Number
- 59131/09
- Procedural Posture
- Urgent Application / Interim Interdict Pending Review
- Outcome
- Interim interdict granted pending the finalisation of the review application.
- Judges
- Tolmay
- Legal Topics
- Public Procurement, Interim Interdict, Fair Administrative Action, Tender Review
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
DFS Flemingo SA Pty (Ltd)
Applicant
Airport Company SA (Pty) Ltd
Respondent
Big Five Duty Free (Pty) Ltd
Respondent
The Tender Board of ACSA
Respondent
Procedural Posture
Urgent Application / Interim Interdict Pending Review
Legal Issues
- 1 Whether the tender process conducted by the first respondent was fair, equitable, and transparent as required by law.
- 2 Whether the applicant is entitled to interim relief pending the review of the tender award.
- 3 Whether the balance of convenience and irreparable harm favour the granting of an interim interdict.
Ratio Decidendi
The court found that the applicant was entitled to fair and just administrative procedure in the tender process. The refusal to provide requested information and the lack of disclosure of criteria weightings placed the applicant at a disadvantage compared to the incumbent, undermining the fairness and transparency required by law. The applicant established a prima facie right to relief. The balance of convenience did not favour the respondents, as performing under a contract potentially subject to review would not serve any party's interests. The applicant demonstrated the risk of irreparable harm if interim relief was not granted, and no other satisfactory remedy was available....
Court Disposition
Interim interdict granted pending the finalisation of the review application.
Orders
- Pending the finalisation of the review and setting aside of the tender and/or the decision to award the tender, the first and second respondents are interdicted from implementing and performing in terms of any contract concluded between them pursuant to the award of the tender.
- Costs of this application are to be costs in the review application.
Full Case Text
Judgment text and source record
55 paragraphs
IN THE HIGH COURT OF SOUTH AFRICA
(NORTH GAUTENG HIGH COURT, PRETORIA)
CASE NO: 59131/09
DATE: 11 DECEMBER 2009
DFS FLEMINGO SA PTY (LTD) APPLICANT
And
AIRPORT COMPANY SA (PTY) LTD FIRST
RESPONDENT
BIG FIVE DUTY FREE (PTY) LTD SECOND
RESPONDENT
THE TENDER BOARD OF ACSA THIRD
RESPONDENT
JUDGMENT
TOLMAY AJ
Applicant applied for urgent interim relief pending the review and setting aside of a tender award and a contract based on such a tender. A review application was instituted during November 2009.
Urgency
The Applicant alleges that the matter is urgent in that it no interim relief is grained the effluxion of time may result in the applicant, even if successful, not being granted effective relief.
The Respondents on the other hand contend that the matter is not urgent.
In the light of the fact that the implementation date of the tender is 1 March 2010. I regard it in the interest of justice to adjudicate on this matter on an urgent based.
Background
The first Respondent issued invitations to bid for the operation of the Core Duty and VAT free stores in the International Departures and Arrival Airside Terminals at O R Tambo International Airport. Cape Town International Airport and the new International Airport at La Mercy (North of Durban).
The Applicant submitted a tender but the tender was awarded to second Respondent. Second Respondent is the present incumbent of the duty free stores. The first and second Respondent entered into a written agreement on 25 September 2009. The effective date of the agreement is 1 March 2010.
The Applicant alleges that the content of the tender was formulated in a manner which benefited the present incumbent and prejudiced other bidders. The Applicant requested information in respect of inter alia turnover figures and information regarding the top 10 selling items under each category with their respective selling prices. Applicant was refused the information. Applicant alleges that it needed the information in order to develop a more comprehensive and meaningful proposal. The first Respondent refused to divulge duty free turnover details of the shops because it was confidential information pertaining to the second Respondent’s business. Obviously as a result of the second Respondents present position the information was available to second Respondent. Applicant also complained that the respective weightings allocated to criteria and sub-criteria needed to be disclosed to all renderers.
The Applicant alleges that due to the aforesaid second Respondent was in a better position to formulate a winning bid The lack of transparency placed the second Respondent in a better position than other bidders, according to Applicant.
The further allegation is that in the light of the fact that the respective weightings allocated to criteria and sub-criteria were not disclosed the procedure followed was not fair and equitable.
Applicable legal principles
1. The first Respondent is a public entity in terms of the Public Finance Management Act (PFMA) and is enjoined in terms of sec 217 of the Constitution and sec 51(a) (iii) of the PFMA to procure goods and services by means of a system which is fair, equitable, transparent and cost effective.
2. As a result of the aforesaid Applicant is entitled to procedure that complies with the aforesaid legislation.
3. In order to succeed with an interim interdict the Applicant must prove
(i) A prima facic right;
(ii) A well grounded apprehension of harm:
(iii) That the balance of the convenience favours it
(iv) That no other satisfactory remedy is available.
See: L F Boshoff Investments (PTY) Ltd v Cape Town Municipality; Cape Town Municipality v L F Boshoff Investment (PTY) Ltd 1969 (2) SA 256(C) on 267 B - E
Prima facre right
In order to establish whether a prima facie right exists. I need to consider the facts set out by the Applicant, together with any facts set out by the Respondent which the Applicant cannot dispute, and to decide whether with regard to the inherent probabilities and the ultimate onus, the Applicant should obtain final relief at the trial. The facts set up in contradiction by the Respondent should then be considered and if they throw serious doubt on the Applicant's case the Applicant cannot succeed.
On an evaluation of the facts in this case the Applicant is entitled to fair and just administrative procedure. Due to the fact that Applicant did not get the information it requested it could be argued that it was not treated fairly and on equal footing with the Second Respondent. It could also be argued that the weightings allocated to the different criteria should have been revealed to the bidders. Consequently the Applicant did prove a prima facie right.
Balance of convenience
The Applicant alleges that since Second Respondent is the present incumbent there is no short term issue of handover from one successful bidder lo another. It is argued that the granting of interim relief will not prejudice the First and Second Respondents in that the operation of facilities will continue uninterrupted until the review application has been finalised.
The Respondents contend that the balance of convenience favours them in that they should proceed with the concluded agreement pending the finalisation of the review application Due to the long term of the contract. 10 years, the Applicant will have more than enough time to challenge the existing contract in due course. The Respondents will be greatly inconvenienced if the contract is not proceeded with.
In my view it is not in the interest of any of the parties to perform in terms of a contract that could be set. aside by the Court hearing the review application.
Irreparable harm
Applicant alleges that if First and Second Respondents arc permitted to proceed with the implementation of the tender the outcome of the review application will be academic and potentially nugatory. The Respondents dispute this and argues that there will be no irreparable harm.
It is however conceivable that if an interdict is not granted the Applicant could suffer irreparable harm.
No other satisfactory remedy
The Respondents argued that the review application is a sufficient alternative remedy and that therefore 1 should not grant an interim
interdict. This argument however looses sight of the fact that if the terms of the contract arc complied with during the time pending the determining of the review application any relief granted may become academic.
Consequently the Applicant did prove the requirements for an interim interdict.
I make the following order:
1. Pending the finalisation of the review and setting aside of the tender and/or setting aside of the decision of the First Respondent
and/or Third Respondent to award a tender for the operation of the Core Duty and VAT free stores in the international departures and arrival airside terminals at OR Tambo International Airport. Cape Town International Airport and the new International Airport at La Mercy (North of Durban KZN) in terms of bid reference number CDF08 05/2009 (“the tender").
1.2 The First and Second Respondents are interdicted from implementing and performing in terms of any contract concluded between the First and Second Respondents, pursuant to the award of the aforesaid tender.
2. Costs of this application is to be costs in the review application.
R TOLMAY
ACTING JUDGE OF THE HIGH COURT