Drake Flemmer and Orsmond Inc and Another v Gajjar NO (21/2017) [2017] ZASCA 169; [2018] 1 All SA 344 (SCA); 2018 (3) SA 353 (SCA) (1 December 2017)

Drake Flemmer and Orsmond Inc and Another v Gajjar NO (21/2017) [2017] ZASCA 169; [2018] 1 All SA 344 (SCA); 2018 (3) SA 353 (SCA) (1 December 2017)

The Supreme Court of Appeal held that in claims for professional negligence against attorneys arising from under-settlement of a Road Accident Fund claim, damages must be assessed at the date of the notional trial against the original debtor (RAF), not at the date of breach or at the date of trial against the...

Source-derived case information.

Citation
[2017] ZASCA 169
Parties
Appellant: Drake Flemmer & Orsmond Inc; Appellant: Le Roux Inc; Respondent: G Gajjar NO
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Case Number
21/2017
Procedural Posture
Civil Appeal / Appeal From Eastern Cape Local Division of the High Court, Port Elizabeth
Outcome
Appeal dismissed with costs; cross-appeal upheld with costs. The damages awarded to the plaintiff are reinstated to R9 211 953, with interest to run from the date of prescription.
Judges
Cachalia, Tshiqi, Makgoka, Ploos van Amstel, Rogers
Legal Topics
Professional Negligence, Breach of Mandate, Prescription, Damages Assessment, Interest on Unliquidated Debt
Commercial and Corporate Civil Procedure Professional Negligence Breach of Mandate Prescription Damages Assessment Interest on Unliquidated Debt

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 21 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Drake Flemmer & Orsmond Inc

Appellant

Le Roux Inc

Appellant

G Gajjar NO

Respondent

Procedural Posture

Civil Appeal / Appeal From Eastern Cape Local Division of the High Court, Port Elizabeth

  1. 1 What is the correct date for assessing damages in a professional negligence claim against attorneys for under-settling a Road Accident Fund claim.
  2. 2 Whether the court a quo erred in reducing damages for delay in bringing the claim to trial.
  3. 3 Whether interest under s 2A(5) of the Prescribed Rate of Interest Act 55 of 1975 is applicable to the damages awarded.

Ratio Decidendi

The Supreme Court of Appeal held that in claims for professional negligence against attorneys arising from under-settlement of a Road Accident Fund claim, damages must be assessed at the date of the notional trial against the original debtor (RAF), not at the date of breach or at the date of trial against the attorney. The evidence and law applicable at the notional trial date determine the recoverable amount. The court found that the reduction of damages for delay in bringing the claim to trial was unjustified, as the delay was attributable to the negligent attorneys and not the plaintiff. The time-value of money should be addressed by awarding interest under s 2A(5) of the Prescribed...

Court Disposition

Appeal dismissed with costs; cross-appeal upheld with costs. The damages awarded to the plaintiff are reinstated to R9 211 953, with interest to run from the date of prescription.

Orders

  • The appeal is dismissed with costs, including those attendant on the employment of two counsel, such costs to be paid by the second appellant.
  • The cross-appeal is upheld with costs, including those attendant on the employment of two counsel, such costs to be paid by the second appellant.