Dunne v Kroch Builders CC (89390/2015) [2017] ZAGPPHC 528 (22 August 2017)
- Citation
- [2017] ZAGPPHC 528
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- North Gauteng High Court, Pretoria
- Panel
- A Millar
- Case number
- 89390/2015
More details
- Court
- North Gauteng High Court, Pretoria
- Panel
- A Millar
- Case number
- 89390/2015
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the alleged contradiction between the contract term ('no less than 7 days') and the letter of demand ('7 days') was not material. The plaintiff was entitled to demand performance within the minimum period stipulated in the contract, and the defendant was not prejudiced or left uncertain as to the case it had to meet. The exception was therefore dismissed. Regarding costs, the court held that the application to strike out precipitated the amendment and that the defendant was substantially successful in this regard, warranting a costs order in its favour for the application to strike out.
Court disposition
Exception dismissed with costs limited to those incurred from 23 November 2016. Costs of the application to strike out awarded to the defendant.
Orders
- The exception is dismissed with costs, such costs however limited to those incurred from 23 November 2016.
- The costs of the application to strike out are to be paid by the plaintiff.
02
Material facts
Parties
EE Dunne
PlaintiffKroch Builders CC
Defendant03
Procedural history
Posture
Exception Application / Ruling on Exception and Costs
04
Questions and positions
Legal issues
- 01
Whether the plaintiff's particulars of claim are vague and embarrassing due to alleged contradictions between the contract terms and the letter of demand.
- 02
Whether the defendant is unable to plead to the particulars of claim as a result of the alleged contradiction.
- 03
Determination of costs relating to the application to strike out certain averments.
Party arguments
- Applicant
- The defendant argued that the particulars of claim were vague and embarrassing because the contract required the plaintiff to demand rectification within 'no less than 7 days', while the letter of demand specified '7 days'. This discrepancy allegedly made it impossible for the defendant to plead to the claim. The defendant also sought costs for the application to strike out certain averments, asserting that the plaintiff's amendment did not resolve the underlying issue.
- Respondent
- The plaintiff contended that the difference between 'no less than 7 days' and '7 days' was immaterial, as the contract allowed for a minimum period and the plaintiff was entitled to choose the minimum. The plaintiff argued that the defendant was fully aware of the case it had to meet and that the particulars were not vague or embarrassing. Regarding costs, the plaintiff tendered wasted costs occasioned by the amendment, but not for the application to strike out.
05
Court’s reasoning
Legal principles
- 01
GENERAL COMMERCIAL AND INDUSTRIAL FINANCE COR, LTD v PRETORIA PORTLAND CEMENT CO., LTD 1944 AD 444 at 454
The test for whether pleadings are vague and embarrassing is whether the opposing party knows the case it is called upon to meet.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the alleged contradiction between the contract term ('no less than 7 days') and the letter of demand ('7 days') was not material. The plaintiff was entitled to demand performance within the minimum period stipulated in the contract, and the defendant was not prejudiced or left uncertain as to the case it had to meet. The exception was therefore dismissed. Regarding costs, the court held that the application to strike out precipitated the amendment and that the defendant was substantially successful in this regard, warranting a costs order in its favour for the application to strike out.
Obiter and limits
- The issue of whether the plaintiff was entitled to plead and rely on the letter of 8 November 2012 is likely to be traversed during the course of the trial.
Court disposition
Exception dismissed with costs limited to those incurred from 23 November 2016. Costs of the application to strike out awarded to the defendant.
- The exception is dismissed with costs, such costs however limited to those incurred from 23 November 2016.
- The costs of the application to strike out are to be paid by the plaintiff.
Source and reliance status
North Gauteng High Court, Pretoria
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
North Gauteng High Court, Pretoria
Judgment
IN
THE HIGH COURT OF SOUTH AFRICA
(GAUTENG DIVISION, PRETORIA DIVISION)
Case No. 89390/2015
Date: 21/8/2017
Reportable: No
Of interest to other judges: No
In the matter between:
EE
DUNNE
PLAINTIFF/RESPONDENT
and
KROCH
BUILDERS CC
DEFENDANT/APPLICANT
JUDGMENT
MILLAR,AJ
1. This is an application for the upholding of an exception taken against the particulars of claim filed by the Plaintiff in an action for damages against the Defendant.
2. There is also an application for an order for costs in respect of an application to strike out certain averments from the particulars of claim. The application to strike out became academic when the Plaintiff amended the particulars to delete the allegation complained
of. All that remains to be determined is the costs.
3. The Defendant delivered on the same day - 25 February 2016, both the application to strike out and a notice in terms of Rule 23 giving notice to remove a cause of complaint.
4. The exception to be delivered was delivered on 18 March 2016. The exception was taken initially on two grounds. It is only the first ground that requires determination, the second having been cured by an amendment effected by the Plaintiff on 22 November 2016.
5. The exception was framed as follows:
"The allegations made by the Plaintiff in paragraph 4.6 and 9 of the particulars of claim are contradictory in that the Plaintiff alleges that it was a term of the contract that the Plaintiff is required to "demand that the Defendant rectify the breach within a period no less than 7 days from date of receipt of such notice", whereas the Plaintiff thereafter alleges that the Plaintiff "demanded that Defendant remedy its above breach within a period of 7 days from date of receipt of the notice" (see Exception paragraph 5 page 67)
6. Essentially the complaint is that the precise wording of the contract - paragraph 11.3.2 of Annexure "A" pleaded at paragraph 4.6 of the particulars of claim does not accord strictly with the precise wording of the letter of demand - Annexure "C" pleaded in paragraph 9.
7. It is the case for the Defendant that the consequence of this is to render the Plaintiffs particulars of claim vague and
embarrassing and that the Defendant is unable to plead thereto.
8. The test to be applied in this regard was stated by Davis AJA in GENERAL COMMERCIAL AND INDUSTRIAL FINANCE COR, LTD v PRETORIA
PORTLAND CEMENT CO., LTD 1944 AD 444 at 454 as follows:
a. "We have to look at the matter from the point of view of the party who is faced with a pleading of this nature. How is he to know what case he is called upon to meet?
9. The two allegations that are claimed to be contradictory are expressed in almost identical terms save that whereas the original
contract and paragraph 4.6 provide for "no less than" 7 days, the letter of demand and paragraph 9 provide for a period "of' 7 days. The former provides for a minimum period with the possibility of a longer period and the latter provides for the minimum period. The Plaintiff chose the minimum period which she was entitled to do in terms of the contract.
10. The Defendant knows the case it is to meet and nothing turns, in my view on the Plaintiff having elected to demand performance within the minimum period contemplated in the contract.
11. In regard to the Application to Strike out, it seems to me that notwithstanding the subsequent amendment the issue raised in that application, that is whether the Plaintiff was entitled to plead and rely on the letter of 8 November 2012 is one that is likely to be traversed during the course of the trial.
12. Having said that, the pleadings were subsequently amended to remove the allegation complained of and the Plaintiff subsequently tendered the wasted costs occasioned by the amendment. Both parties understood that the render was only for the costs of the amendment and not in regard to the application to strike out.
13. The two cannot be separated, the application precipitated the amendment. On this aspect, I find that the defendant was substantially successful and for this reason make the order that I do.
14. In the circumstances, it is ordered:
12.1 The exception is dismissed with costs, such costs however
limited to those incurred from 23 November 2016.
12.2 The costs of the application to strike out are to be paid by the plaintiff.
______
A
MILLAR
ACTING
JUDGE OF THE HIGH COURT
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.