Ekurhuleni West College v Segal and Another (1287/2018) [2020] ZASCA 32 (2 April 2020)

Ekurhuleni West College v Segal and Another (1287/2018) [2020] ZASCA 32 (2 April 2020)

The court held that the adjudicator's determination was an interim measure subject to revision in arbitration, as expressly provided in the building contract and JBCC Adjudication Rules. The College's review application sought to challenge unterminated proceedings, which is only permissible in rare cases of grave...

Source-derived case information.

Citation
[2020] ZASCA 32
Parties
Appellant: Ekurhuleni West College; Respondent: Stanley Harold Segal; Respondent: Trencon Construction (Pty) Ltd
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Case Number
1287/2018
Procedural Posture
Civil Appeal / Appeal From Review Application in High Court
Outcome
Appeal dismissed with costs, including costs of two counsel.
Judges
Ponnan, Van der Merwe, Molemela, Dlodlo, Nicholls
Legal Topics
Building Contracts, Adjudication, Arbitration, Review of Interim Decisions
Commercial and Corporate Civil Procedure Building Contracts Adjudication Arbitration Review of Interim Decisions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 14 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Ekurhuleni West College

Appellant

Stanley Harold Segal

Respondent

Trencon Construction (Pty) Ltd

Respondent

Procedural Posture

Civil Appeal / Appeal From Review Application in High Court

  1. 1 Whether the adjudicator's determination under a building contract is susceptible to judicial review while arbitration proceedings are pending.
  2. 2 Whether the rules of natural justice apply to contractual adjudication proceedings.
  3. 3 Whether the High Court correctly dismissed the review application and granted enforcement of the adjudicator's determination.

Ratio Decidendi

The court held that the adjudicator's determination was an interim measure subject to revision in arbitration, as expressly provided in the building contract and JBCC Adjudication Rules. The College's review application sought to challenge unterminated proceedings, which is only permissible in rare cases of grave injustice. No such circumstances were shown. The adjudicator acted strictly in accordance with the contract, and the College's procedural complaints lacked merit. The College was contractually bound to pay the determined amount and pursue its remedy in arbitration. The review application was an abuse of process and was correctly dismissed by the High Court.

Court Disposition

Appeal dismissed with costs, including costs of two counsel.

Orders

  • The appeal is dismissed with costs, including the costs of two counsel.