Eskom Holdings SOC Limited v Framatome and Another (5201/23) [2025] ZAWCHC 296 (17 July 2025)

Eskom Holdings SOC Limited v Framatome and Another (5201/23) [2025] ZAWCHC 296 (17 July 2025)

The court found that the adjudicator acted within the wide powers conferred by the NEC3 contract, including issuing instructions to the project manager and deferring quantum determination. The contract's wording and context support a broad interpretation of the adjudicator's powers, and the process followed was...

Source-derived case information.

Citation
[2025] ZAWCHC 296
Parties
Applicant: Eskom Holdings SOC Limited; Respondent: Framatome; Respondent: Peter Ramsden
Court
Western Cape High Court, Cape Town
Jurisdiction
South Africa
Case Number
5201/23
Procedural Posture
Review Application / Final Judgment on Application and Counter Application
Outcome
Application dismissed; counter-application granted. Eskom is ordered to pay the amounts determined and costs.
Judges
R T Williams
Legal Topics
Adjudication Under Construction Contract, Contractual Dispute Resolution Clauses, Enforceability of Adjudicator Awards, Natural Justice in Contractual Tribunals, Functus Officio, Interpretation of Nec3 Contract
Civil Procedure Commercial and Corporate Alternative Dispute Resolution Adjudication Under Construction Contract Contractual Dispute Resolution Clauses Enforceability of Adjudicator Awards Natural Justice in Contractual Tribunals Functus Officio +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Eskom Holdings SOC Limited

Applicant

Framatome

Respondent

Peter Ramsden

Respondent

Procedural Posture

Review Application / Final Judgment on Application and Counter Application

  1. 1 Whether the adjudicator exceeded his jurisdiction in issuing decisions and instructions under the NEC3 contract.
  2. 2 Whether the adjudicator breached the rules of natural justice in the adjudication process.
  3. 3 Whether the adjudicator was functus officio after issuing the merits decision and thus precluded from further instructions or decisions.

Ratio Decidendi

The court found that the adjudicator acted within the wide powers conferred by the NEC3 contract, including issuing instructions to the project manager and deferring quantum determination. The contract's wording and context support a broad interpretation of the adjudicator's powers, and the process followed was consistent with the contract and South African law. The timing of the quantum instructions and further instructions was in accordance with the contract, and both the merits and quantum decisions were issued timeously. The rules of natural justice do not apply unless incorporated into the contract, and Eskom failed to show any breach thereof. The adjudicator provided adequate...

Court Disposition

Application dismissed; counter-application granted. Eskom is ordered to pay the amounts determined and costs.

Orders

  • The applicant's application is dismissed with costs, including costs attendant upon the employment of two counsel, with scale C to apply from 12 April 2024.
  • The applicant is directed to make payment to the first respondent of €35,288,582.00, exclusive of value-added tax and subject to price adjustment for inflation pursuant to secondary option clause X1 of the contract, and pursuant to clauses 51.3 and 51.4 of the contract, interest thereon calculated at the LIBOR rate...