Eskom Holdings Soc Limited v Khum MK Investments & Bie Joint Venture (Pty) Ltd and Others (18627/2014) [2015] ZAGPJHC 98; [2015] 3 All SA 439 (GJ) (4 June 2015)

Eskom Holdings Soc Limited v Khum MK Investments & Bie Joint Venture (Pty) Ltd and Others (18627/2014) [2015] ZAGPJHC 98; [2015] 3 All SA 439 (GJ) (4 June 2015)

The court found that Eskom failed to prove misconduct, gross irregularity, or bias on the part of the arbitrator. The arbitrator acted fairly, applied the correct legal principles, and made findings supported by the evidence. Eskom, through its conduct and representations, accepted the company as the contracting...

Source-derived case information.

Citation
[2015] ZAGPJHC 98
Parties
Applicant: Eskom Holdings SOC Limited; Respondent: Khum MK Investments & BIE Joint Venture (Pty) Ltd; Respondent: Khum MK Investments CC and BIE International Engineers (Pty) Ltd Joint Venture; Respondent: Judge L I Goldblatt
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
18627/2014
Procedural Posture
Review Application / Judgment on Application to Set Aside Arbitration Award and for Remittal to New Tribunal
Outcome
Application dismissed with costs, including costs on attorney and client scale and costs of two counsel.
Judges
D S S Moshidi
Legal Topics
Arbitration Review, Estoppel, Procurement Policy, Contractual Illegality, Gross Irregularity, Remittal of Dispute
Civil Procedure Commercial and Corporate Arbitration Review Estoppel Procurement Policy Contractual Illegality Gross Irregularity Remittal of Dispute

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 24 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Eskom Holdings SOC Limited

Applicant

Khum MK Investments & BIE Joint Venture (Pty) Ltd

Respondent

Khum MK Investments CC and BIE International Engineers (Pty) Ltd Joint Venture

Respondent

Judge L I Goldblatt

Respondent

Procedural Posture

Review Application / Judgment on Application to Set Aside Arbitration Award and for Remittal to New Tribunal

  1. 1 Whether the arbitrator committed misconduct or gross irregularity in the conduct of the arbitration proceedings.
  2. 2 Whether Eskom is estopped from denying the existence of a contract with the company as opposed to the joint venture.
  3. 3 Whether the substitution of the joint venture by the company rendered the contract illegal and unenforceable under procurement law.

Ratio Decidendi

The court found that Eskom failed to prove misconduct, gross irregularity, or bias on the part of the arbitrator. The arbitrator acted fairly, applied the correct legal principles, and made findings supported by the evidence. Eskom, through its conduct and representations, accepted the company as the contracting party and is estopped from denying this. The incorporation of the joint venture into a company did not materially alter the contract or violate procurement law, as there was no evidence of illegality or breach of statutory provisions. The application to set aside the award and for remittal to a new tribunal was dismissed, as Eskom did not establish good cause for remittal and the...

Court Disposition

Application dismissed with costs, including costs on attorney and client scale and costs of two counsel.

Orders

  • The application is dismissed with costs, including all costs previously reserved, if any.
  • Costs are awarded on the scale as between attorney and client, including the costs consequent upon the employment of two counsel.