Eskom v Nikelo (CA38/18) [2018] ZAECMHC 48 (21 August 2018)
The court found that Eskom failed to provide a satisfactory and comprehensive explanation for the delay in prosecuting the appeal, particularly for the period between the granting of leave to appeal and the eventual filing of the notice of appeal. The explanation offered was vague, incomplete, and did not cover the entire period of delay. The court held that condonation may be refused in cases of flagrant breaches of the rules, especially where no acceptable explanation is provided, regardless of the prospects of success. On the merits, the court found that Eskom did not have lawful authority to disconnect the respondent's electricity supply without notice, statutory authority, or a court...
- Citation
- [2018] ZAECMHC 48
- Parties
- Appellant: Eskom; Respondent: Vusumzi Nikelo
- Court
- Eastern Cape High Court, Mthatha
- Jurisdiction
- South Africa
- Judgment Date
- 21 August 2018
- Case Number
- CA38/18
- Procedural Posture
- Civil Appeal / Application for Condonation and Appeal
- Outcome
- Application for condonation dismissed with costs. Appeal dismissed with costs.
- Judges
- J D Huisamen, R E Griffiths
- Legal Topics
- Condonation, Mandament Van Spolie, Electricity Supply Termination, Urgent Application, Rule Nisi
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Eskom
Appellant
Vusumzi Nikelo
Respondent
Procedural Posture
Civil Appeal / Application for Condonation and Appeal
Legal Issues
- 1 Whether the appellant provided a satisfactory explanation for the delay in prosecuting the appeal.
- 2 Whether condonation for the late filing of the notice of appeal and failure to apply for a hearing date and file the appeal record should be granted.
- 3 Whether the appellant had lawful authority to disconnect the respondent's electricity supply without notice or court order.
Ratio Decidendi
The court found that Eskom failed to provide a satisfactory and comprehensive explanation for the delay in prosecuting the appeal, particularly for the period between the granting of leave to appeal and the eventual filing of the notice of appeal. The explanation offered was vague, incomplete, and did not cover the entire period of delay. The court held that condonation may be refused in cases of flagrant breaches of the rules, especially where no acceptable explanation is provided, regardless of the prospects of success. On the merits, the court found that Eskom did not have lawful authority to disconnect the respondent's electricity supply without notice, statutory authority, or a court...
Court Disposition
Application for condonation dismissed with costs. Appeal dismissed with costs.
Orders
- The application for condonation is dismissed with costs.
- The appeal is dismissed with costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment