First Rand Bank Ltd v Brera Investments CC (385/2012) [2013] ZASCA 25; 2013 (5) SA 556 (SCA) (25 March 2013)
The Supreme Court of Appeal held that the payment guarantee issued by First Rand Bank was an independent obligation, not accessory to the underlying contract between the respondent and the contractor. Liability under the guarantee arose upon the respondent's compliance with the demand procedure set out in clause 3, specifically the failure of the contractor to issue a payment certificate within seven days of demand. The subsequent issuance of a payment certificate for a lesser amount did not affect the appellant's liability, as the trigger event for payment had already occurred. The court rejected the appellant's interpretation that liability depended on the continued failure to issue a...
- Citation
- [2013] ZASCA 25
- Parties
- Appellant: First Rand Bank Limited; Respondent: Brera Investments CC
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 25 March 2013
- Case Number
- 385/2012
- Procedural Posture
- Civil Appeal / Appeal From the South Gauteng High Court, Johannesburg
- Outcome
- Appeal dismissed with costs.
- Judges
- Lewis, Ponnan, Malan, Theron, Plasket
- Legal Topics
- Construction Guarantee, Performance Bond, Interpretation of Contract, Payment Certificate, Independent Guarantee
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
First Rand Bank Limited
Appellant
Brera Investments CC
Respondent
Procedural Posture
Civil Appeal / Appeal From the South Gauteng High Court, Johannesburg
Legal Issues
- 1 Whether the appellant is liable to pay the respondent under a payment guarantee when the payment certificate was not issued within the stipulated period.
- 2 Whether events occurring after the due date for issuing the payment certificate affect the appellant's liability under the guarantee.
- 3 Whether the guarantee constitutes a suretyship or an independent obligation.
Ratio Decidendi
The Supreme Court of Appeal held that the payment guarantee issued by First Rand Bank was an independent obligation, not accessory to the underlying contract between the respondent and the contractor. Liability under the guarantee arose upon the respondent's compliance with the demand procedure set out in clause 3, specifically the failure of the contractor to issue a payment certificate within seven days of demand. The subsequent issuance of a payment certificate for a lesser amount did not affect the appellant's liability, as the trigger event for payment had already occurred. The court rejected the appellant's interpretation that liability depended on the continued failure to issue a...
Court Disposition
Appeal dismissed with costs.
Orders
- The appeal is dismissed with costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment