Fisher v Mbombela Local Municipality and Others (15/11/2019) [2019] ZAMPMBHC 13; LEGODI JP (7 February 2020)

Fisher v Mbombela Local Municipality and Others (15/11/2019) [2019] ZAMPMBHC 13; LEGODI JP (7 February 2020)

The court found that the applicant did not unreasonably delay in instituting the review proceedings, as the reasons for the administrative actions were only furnished on 16 May 2016 and proceedings commenced on 1 September 2016. However, the applicant unreasonably delayed in prosecuting the review, with a 14-month...

Source-derived case information.

Citation
[2019] ZAMPMBHC 13
Parties
Applicant: Frank Fisher; Respondent: Mbombela Local Municipality; Respondent: Mataffin Macadamia Devco Proprietary Ltd; Respondent: Mataffin Macadamia Home Owners Association; Respondent: Goodman Mokoena; Respondent: Registrar of Deeds, Mbombela; Respondent: Surveyor General for the Province of Mpumalanga, Mbombela
Court
Mbombela High Court, Mpumalanga
Jurisdiction
South Africa
Case Number
1054/2016
Procedural Posture
Review Application / Final Judgment
Outcome
Application dismissed with costs for the first, second, and fourth respondents; sixth respondent entitled to costs up to the date it was informed the applicant would not pursue a costs order against it.
Judges
Legodi JP
Legal Topics
Unreasonable Delay, Standing, Judicial Review, Prejudice, Non Joinder, Building Regulations
Administrative Law Land and Property Unreasonable Delay Standing Judicial Review Prejudice Non Joinder Building Regulations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2
Sign in to unlock

Parties

Frank Fisher

Applicant

Mbombela Local Municipality

Respondent

Mataffin Macadamia Devco Proprietary Ltd

Respondent

Mataffin Macadamia Home Owners Association

Respondent

Goodman Mokoena

Respondent

Registrar of Deeds, Mbombela

Respondent

Surveyor General for the Province of Mpumalanga, Mbombela

Respondent

Procedural Posture

Review Application / Final Judgment

  1. 1 Whether the applicant unreasonably delayed in instituting and prosecuting the review proceedings.
  2. 2 Whether the applicant has standing to challenge the administrative actions and approvals.
  3. 3 Whether the interests of justice require overlooking the delay.

Ratio Decidendi

The court found that the applicant did not unreasonably delay in instituting the review proceedings, as the reasons for the administrative actions were only furnished on 16 May 2016 and proceedings commenced on 1 September 2016. However, the applicant unreasonably delayed in prosecuting the review, with a 14-month gap after pleadings closed before heads of argument were delivered. This delay caused prejudice to the 48 apartment owners, as the flats were completed, transferred, and occupied during this period. The applicant's standing was minimal, as his interests in space and view were outweighed by those of the apartment owners, and he had already abandoned the relief for demolition. The...

Court Disposition

Application dismissed with costs for the first, second, and fourth respondents; sixth respondent entitled to costs up to the date it was informed the applicant would not pursue a costs order against it.

Orders

  • The application is dismissed with costs for the first, second, and fourth respondents.
  • The sixth respondent is entitled to costs up to the date on which it was informed that the applicant does not pursue a costs order against it.