Fynbosland 435 CC v Torro ya Africa (Pty) Ltd and Others (1861/2011) [2011] ZANWHC 68 (15 December 2011)

Fynbosland 435 CC v Torro ya Africa (Pty) Ltd and Others (1861/2011) [2011] ZANWHC 68 (15 December 2011)

The court found that the applicant was in peaceful and undisturbed possession of the completed and partially completed housing units and associated infrastructure at Naledi Extension 25, and held a valid builder's lien over these structures and installations due to unpaid contract amounts. The first respondent,...

Source-derived case information.

Citation
[2011] ZANWHC 68
Parties
Applicant: Fynbosland 435 CC; Respondent: Torro ya Africa (Pty) Ltd; Respondent: MEC for Human Settlement, Public Safety and Liaison, North West; Respondent: Naledi Local Municipality
Court
North West High Court, Mafikeng
Jurisdiction
South Africa
Case Number
1861/2011
Procedural Posture
Urgent Application / First Instance Judgment
Outcome
Application granted in part; urgent relief restoring possession of completed units and infrastructure to applicant; application against second respondent dismissed; each party to pay its own costs.
Judges
M M Leeuw
Legal Topics
Mandament Van Spolie, Builder Lien, Urgent Interdict, Right of Retention, Possession, Municipal Contract Dispute
Civil Procedure Land and Property Mandament Van Spolie Builder Lien Urgent Interdict Right of Retention Possession Municipal Contract Dispute

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Fynbosland 435 CC

Applicant

Torro ya Africa (Pty) Ltd

Respondent

MEC for Human Settlement, Public Safety and Liaison, North West

Respondent

Naledi Local Municipality

Respondent

Procedural Posture

Urgent Application / First Instance Judgment

  1. 1 Whether the applicant's builder's lien extends to the completed and partially built structures together with the entire premises in Extension 25.
  2. 2 Whether the respondents have interfered or disturbed the applicant's right to the builder's lien.

Ratio Decidendi

The court found that the applicant was in peaceful and undisturbed possession of the completed and partially completed housing units and associated infrastructure at Naledi Extension 25, and held a valid builder's lien over these structures and installations due to unpaid contract amounts. The first respondent, through its employees and subcontractors, unlawfully disturbed the applicant's possession by occupying completed units, removing notice boards, and interfering with stored materials and infrastructure. However, the applicant failed to prove that its builder's lien extended to the entire premises of Naledi Extension 25; the lien was limited to the specific units and infrastructure...

Court Disposition

Application granted in part; urgent relief restoring possession of completed units and infrastructure to applicant; application against second respondent dismissed; each party to pay its own costs.

Orders

  • The applicant was entitled to approach the Court on an urgent basis.
  • The first respondent and its workmen, subcontractors and other persons interfering with the applicant's right to a builder's lien are directed to restore the applicant's undisturbed possession of the 365 low cost units constructed by the applicant in Naledi Extension 25, the secured area where the applicant's...