Goldleaf Investments (Pty) Ltd v Orkin (22321/18) [2024] ZAGPJHC 695 (22 July 2024)
- Citation
- [2024] ZAGPJHC 695
- Status
- Judgment
- Jurisdiction
- South Africa
- Court
- South Gauteng High Court, Johannesburg
- Panel
- MIA
- Case number
- 22321/18
More details
- Court
- South Gauteng High Court, Johannesburg
- Panel
- MIA
- Case number
- 22321/18
On this page
Professional case brief
Research organized from the available case record
01
Holding and result
The court found that the respondent's failure to testify did not render her case unproven, as the evidence of Mr Orkin and Mr Parsons constituted the best evidence regarding the relevant facts. The court held that a tacit term existed in the sale agreement requiring the applicant to provide a fully serviced site, including municipal and electrical services, upon completion of construction. The applicant breached this term by failing to ensure the supply of electricity, resulting in the respondent's inability to take occupation and incurring rental losses. The respondent's claim against the contractor did not compromise her claim against the applicant, as the agreements and obligations were distinct. The once-and-for-all rule did not apply because the claims were against different parties for different breaches. The court was not persuaded that another court would reach a different conclusion or that there was any compelling reason for the appeal to be heard. Accordingly, the application for leave to appeal was dismissed with costs.
Court disposition
Application for leave to appeal dismissed with costs.
Orders
- The application for leave to appeal is dismissed with costs.
02
Material facts
Parties
Goldleaf Investments (Pty) Ltd
Applicant Counsel: Adv. N StathernNadine Orkin
Respondent Counsel: Adv. D VettenAmounts and remedies
- Monthly Rental Loss Incurred by Respondent Due to Delay: ZAR 40,000
03
Procedural history
Posture
Leave to Appeal / Application for Leave to Appeal Following Trial Judgment
04
Questions and positions
Legal issues
- 01
Whether the respondent's failure to testify rendered her case unproven.
- 02
Whether a tacit term existed in the sale agreement requiring the applicant to provide a fully serviced site with municipal and electrical services.
- 03
Whether the applicant breached the tacit term and caused the respondent to suffer damages.
- 04
Whether the respondent's claim against the contractor compromised her claim against the applicant.
- 05
Whether the applicant had locus standi in respect of the counterclaim.
- 06
Whether the respondent waived her rights to claim damages by agreeing to a new occupation date.
- 07
Whether the once-and-for-all rule applied to the respondent's claims against different parties.
Party arguments
- Applicant
- The applicant argued that the respondent's case should fail because she did not testify, rendering the evidence hearsay. It was submitted that the evidence of Mr Orkin and Mr Parsons was inadmissible and that the respondent failed to prove her case. The applicant further contended that the agreement presumed bulk electricity was supplied, and that the court erred in finding a tacit term requiring the applicant to provide a fully serviced site. The applicant maintained that bulk electricity was supplied and that any delays were due to Eskom, not the applicant. The applicant also argued that the respondent waived her rights to claim damages by agreeing to a new occupation date and that the respondent's claim against the contractor compromised her claim against the applicant. The applicant challenged the court's finding on locus standi regarding the counterclaim and submitted that costs should be awarded in its favour.
- Respondent
- The respondent argued that the best evidence was provided by Mr Orkin and Mr Parsons, who had direct knowledge of the relevant facts. The respondent maintained that the sale agreement and building contract were interlinked and set a reasonably agreed date for occupation, and that the applicant was aware of the urgency regarding the electrical installation. The respondent asserted that she suffered losses due to the delay in occupation and communicated this to the applicant and contractor. The respondent denied waiving her rights to claim damages and argued that her claim against the contractor did not compromise her claim against the applicant, as the obligations under the respective agreements differed. The respondent contended that the once-and-for-all rule did not apply as the claims were against different parties for different breaches.
05
Court’s reasoning
Legal principles
- 01
Superior Courts Act 10 of 2013, s17(1)(a)(i)
Leave to appeal may only be granted if the appeal has reasonable prospects of success or there is some other compelling reason for it to be heard, such as a question of law or public importance.
- 02
Alfred McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration 1974(3) SA 506 (A) at 531
A tacit term may be determined by the officious bystander test, which considers whether both parties would have agreed to the term had it been suggested at the time of contracting.
- 03
Caratco (Pty) Ltd v Independent Advisory (Pty) Ltd (Case no 982/18) [2020] ZASCA 17 (25 March 2020)
The best evidence rule requires that the most direct and relevant evidence be presented, and parties are not required to testify if other witnesses have superior knowledge of the facts.
06
Ratio, limits and disposition
Ratio decidendi
The court found that the respondent's failure to testify did not render her case unproven, as the evidence of Mr Orkin and Mr Parsons constituted the best evidence regarding the relevant facts. The court held that a tacit term existed in the sale agreement requiring the applicant to provide a fully serviced site, including municipal and electrical services, upon completion of construction. The applicant breached this term by failing to ensure the supply of electricity, resulting in the respondent's inability to take occupation and incurring rental losses. The respondent's claim against the contractor did not compromise her claim against the applicant, as the agreements and obligations were distinct. The once-and-for-all rule did not apply because the claims were against different parties for different breaches. The court was not persuaded that another court would reach a different conclusion or that there was any compelling reason for the appeal to be heard. Accordingly, the application for leave to appeal was dismissed with costs.
Obiter and limits
- The parties need not be married in community of property to share home expenses; evidence of joint financial arrangements is sufficient.
- The settlement agreement between the respondent and the contractor did not affect the respondent's claim against the developer, as their obligations were different.
- The respondent's communication regarding losses and delay was clear and sufficient to establish breach and damages; there was no need to place the applicant in mora.
Court disposition
Application for leave to appeal dismissed with costs.
- The application for leave to appeal is dismissed with costs.
Source and reliance status
South Gauteng High Court, Johannesburg
This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.
Judgment reading view
Judgment text
The complete available source text.
South Gauteng High Court, Johannesburg
Judgment
REPUBLIC
OF SOUTH AFRICA
IN
THE HIGH COURT OF SOUTH AFRICA
GAUTENG DIVISION, JOHANNESBURG
Case Number: 22321/18
1.REPORTABLE: NO
2. OF INTEREST TO OTHER JUDGES: NO
3.REVISED: NO
In the matter between:
GOLDLEAF INVESTMENTS (PTY) LTD
APPLICANT
v.
NADINE
ORKIN
RESPONDENT
In re:
And
GOLDLEAF INVESTMENTS (PTY) LTD
DEFENDANT
JUDGMENT
MIA, J:
[1] The applicant, the defendant in the trial, appeals the whole of the judgment handed down on 21 April 2023. The issue for determination in the trial was whether or not it was a tacit term of the sale agreement that the applicant would have had to "supply all of the necessary infrastructure so as to provide a fully serviced site both in respect of municipal and electrical services
alternatively that the defendant would ensure that all of the necessary infrastructure was in place so as to provide a fully serviced site both in respect of municipal and electrical services"[1]. If there was such a tacit term, the court was enjoined to determine whether the applicant had breached such a term and caused the respondent to suffer damages. The applicant lodged a counterclaim, and the court was required to determine whether the respondent was liable for the costs of the applicant's counterclaim. The appeal was opposed.
[2] The applicant raised numerous grounds in the application for leave to appeal, which spanned twenty-nine pages and several grounds. To succeed in this application for leave to appeal, in terms of s17(1)(a)(i)[2] of the Superior Courts Act 10 of 2013, the applicant must satisfy the court that the appeal will have reasonable prospects of success or that there is some other compelling reason why the appeal should be heard. The enquiry does not end there. “If the court is unpersuaded of the prospects of success, it must still inquire whether there is a compelling reason to entertain the appeal. This includes an essential question of law or a discreet issue of public importance that will affect future disputes. The merits remain important and are often decisive.[3]
[3] I deal with the salient points raised in the appeal.
[4] It is appropriate to commence with the argument on behalf of the applicant that the respondent's case should fail as she did not testify. Counsel argued that the respondent had not met her case as the evidence tendered amounted to hearsay in that she did not testify in her matter. It was submitted that Mr Orkin’s and Mr Parson's evidence constituted hearsay and should not be accepted. Regarding the law of evidence, the evidence of Mr Orkin and Mr Parsons constituted the best evidence. This is so because Mr Orkin
and Mr Parsons had the best knowledge about the aspects they testified about. Mr Orkin was best qualified to testify where he assisted his wife each step of the way, completing the agreement and was best placed to testify about the agreement, the process and the payments he made. Mr Orkin was the best witness to explain why they required a lift to be installed as it met his requirement due to frailty.
[5] Mr Parsons, who engaged with Mr Robinson directly, was also the best witness to testify regarding his communication with the contractor. Counsel’s submission that the plaintiff was required to testify ignores that the best evidence is necessary. Mr Orkin’s evidence about payments made was thus relevant to prove the amount relating to the loss and damages. It was also Mr Orkin's evidence that he and Mrs Orkin would later reconcile the amounts paid from his account. Thus, he was best placed to testify regarding how the parties determined the money would be paid into his account or how they, as partners, contributed to their joint living arrangement. Mr Orkin's evidence indicated as much. The parties need not be married in community of property to share their home expenses. On this ground, I do not see that another court will come to a different conclusion relating to the best evidence rule.
[6] A further ground related to the tacit term, based on paragraph 8 of the judgment which reads:
“and the surrounding circumstances as well as the evidence all point to the developer being responsible for having a fully serviced site in place once the construction was completed to enable the plaintiff to take occupation of the home.”
Counsel submitted that the agreement presumes that bulk electricity is supplied to the site. This was erroneous, counsel continued, as Mr Orkin indicated that no electricity supplied to the site at the time the agreement was entered into. The submission is misguided as a proper reading of the paragraph indicates that the site was to be fully serviced upon completion of the construction. As indicated in the evidence, this was necessary to test the supply of electricity and issue the certificates before handing over the occupation
certificate.
[7] Counsel argued furthermore that the court found that there was a tacit term that required the applicant to provide “a fully serviced site both in respect of municipal and electrical services alternatively that the defendant would ensure that all of the necessary infrastructure was in place to provide a fully serviced site both in respect of municipal and electrical services”. Counsel submitted that the court erred in this regard at the outset, as this was an agreement between the applicant and the respondent. As the respondent did not testify in the trial, the respondent did not prove her case. The court referred to the decision of Alfred McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration[4]In the judgment handed down, an unexpressed term or tacit term can be determined no better than by the officious bystander test. The test on this aspect has not changed, and counsel has not persuaded me that another will find necessary for the respondent to lead evidence in person on this aspect or that the test has changed.
[8] Counsel further submitted that the court erred in finding that the applicant failed to ensure that bulk electricity was supplied to the site. It was submitted as the court ignored that bulk electricity was supplied to the site and the applicant had obtained a regulation 38 certificate in terms of the Town Planning and Township Ordinance which required internal reticulation. This required cabling to be laid to particular units. The last phase was to be completed during construction. The evidence of the applicant and the contractor was that the applicant was responsible for the supply of electricity. This was supported by the applicant’s evidence that he sent various communications to Eskom, approximately fifty-eight.
[9] Counsel for the applicant referred to these fifty-eight communications of the applicant which occurred between March 2017 and March 2018 to ensure the bulk supply to the site. It is noteworthy that counsel argued that Ms Forstman was not an expert and her view is not decisive. That is so as the applicant's evidence was clear that he engaged with Ms Forstman in respect of many projects, and upon his enquiry about Bellisimo, she indicated a requote was required as the project was “old”. It follows that the fifty-eight calls made to Eskom did not relate to the Bellisimo development alone. The applicant was compelled to act on the final stage of the installation on his own evidence when Mr Robinson approached him and indicated that the respondent would be requiring occupation of their unit shortly. The applicant’s response was that he was waiting for Eskom. The applicant’s
plea that there was no obligation to supply electricity, that the plaintiff frustrated the supply or to blame Eskom are all defences
that fail.
[10] It was Mr Robinsons initiative, after Mr Parson’s enquiry about electricity and the respondent's correspondence demanding information and indicating the loss suffered that caused the applicant sign off and move on the electrical supply. The applicant approved the quotation from Consolidated Power Engineering (CPE) to assist in facilitating the process. The applicant of necessity and on Mr Robinson’s advice after Mr Robinson obtained a quotation from CPE appointed the engineering company to address the delay after a substantial delay had already occurred.
[11] Counsel for the respondent argued in the present matter there had been an agreed date for delivery per the sale agreement and building contract which were linked, thus the argument made on behalf of the applicant that the applicant was not placed in mora was not applicable. It is evident that Mr Parsons enquired in February 2017 alerting the applicant that their programme may not meet the agreed occupation date if the electrical installation was not complete.[5] The applicant’s response at that stage was that occupation was dependant on Eskom electricity supply. The building contractor informed the developer that the final installation electricity supply was urgent. The applicant was aware in April 2017 that they would not meet the installation of installation of electrical supply to the unit by the agreed date of occupation. The respondent informed the contractor and developer in April 2017 that they were not able to take occupation due to the electrical supply not being in place and details which parts of the building works have not been completed. Moreover, the respondent placed on record that the delay was costing R 40 000 per month for rental. There is no basis to the argument that the respondent did not bring the breach to the attention of the applicant and the applicant was not required to act on it. The respondent clearly placed her position forward in correspondence dated 19 April 2017.[6]
[12] The submission that the respondent agreed to the new occupation date and thus waived their rights to claim damages ignores the respondent
communication to the applicant and contractor that they incurred losses as a result of the delay. The sale agreement and builder's
contract were interlinked and set out a reasonably agreed date for occupation. There was no need to place the applicant in mora. The respondent informed the applicant per correspondence that she suffered a loss as a result of the electricity not being installed
and not being able to take occupation per the agreement. The respondent demanded that the electricity be attended to, indicating
that they, she and Mr Orkin had been prejudiced, as a result of the electricity issue not being attended to until they demanded same and their unit was not habitable without electricity even though they agreed to a new date of occupation. The respondent pointedly
indicated the loss they incurred as a result of her not being able to take occupation per the agreed date and having to extend their rental amounting to R40 000[7] per month. The applicant’s view when the respondent raised the date of occupation was that they remain on at their residence. Their home had been sold and the respondent incurred costs as a result of the failure to move into the unit in Bellisimo. The applicant cannot waive away the respondent or her claim when the agreement made provision for occupation within a particular time frame. I am not persuaded that another court would find differently on the aspect of damages.
[13] It was also submitted that the court erred in failing to take into consideration the claim by the respondent against the contractor, which was alleged to be identical to the claim against the applicant. The aforementioned claim resulted in a settlement when the contractor gave the respondent occupation. The submission was that the respondent had compromised her claim against the applicant when she claimed against the contractor. Whilst the sale agreement and the building agreement were inextricably linked, the settlement agreement between the respondent and the contractor did not imply a settlement between the respondent and the developer. The applicant and contractor had different obligations. The once and for all rule is applicable between the same parties in the same litigation. The applicant did not prove that the respondent claimed for the same breach against the applicant and the contractor. The respondent’s claim is against different defendants for different breaches in terms of different agreements albeit to obtain occupation of the same unit. The settlement agreement between the contractor and the respondent makes provision for the respondent to pursue a developer debt and to pay the contractor and proportionate amount upon recovered. The respondents claim against the contractor is not subject to the once-and for-all rule against the developer. This is because the once-and-for-all rule is applicable in litigation between the same parties.
[14] Counsel submitted that the court erred in finding the applicant had no locus standi in respect of the counterclaim. The reason for finding there was no locus standi is adequately set out in the judgment. I elaborate no further and am of the view that there is no possibility a different conclusion will be reached. The applicant did not pursue this aspect substantially before me.
[15] On the issue of costs, counsel submitted that there was a reasonable possibility that another court would find that the respondent failed to make out her case and the claim should fail with costs. In addition, it was submitted that the counterclaim should succeed with costs. The reasons for granting a punitive costs order are set out in the judgment. I do not intend to elaborate further on the reasons.
[16] Having regard to the standard the applicant must satisfy to succeed I am not persuaded that there are reasonable prospects of success that another court will come to a different conclusion. There is no other compelling reason why the appeal should be heard.
[17] In the result, I grant the following order:
The application for leave to appeal is dismissed with costs.
SC, MIA
JUDGE OF THE HIGH
COURT
GAUTENG DIVISION,
JOHANNESBURG
APPEARANCES
Counsel for the Applicant: Adv. N Stathern
Instructed by:
Ulrich Roux and Associates
Counsel for the Respondent: Adv. D Vetten
Instructed by:
Witz Incorporated Attorneys
Date of Hearing:
14 June 2024
Date of Judgment:
22 July 2024
[1] Record, Caselines (CL) 001-6 - Particulars of claim, para 11,.
[2] ‘Leave to appeal (1) Leave to appeal may only be given where the judge or judges concerned are of the opinion that- (a) (i) the appeal would have a reasonable prospect of success; or (ii) there is some other compelling reason why the appeal should be heard, including conflicting judgments on the matter under
consideration.
[2] ‘Leave to appeal
(1) Leave to appeal may only be given where the judge or judges concerned are of the opinion that-
(a) (i) the appeal would have a reasonable prospect of success; or
(ii) there is some other compelling reason why the appeal should be heard, including conflicting judgments on the matter under
consideration.
[3] Caratco (Pty) Ltd v Independent Advisory (Pty) Ltd (Case no 982/18) [2020] ZASCA 17 (25 March 2020)
[4] Alfred McAlpine & Son (Pty) Ltd v Transvaal Provincial Administration 1974(3) SA 506 A at 531
[5] Caselines 004-499 Correspondence to Mr Parsons
[6] Caselines 004-506 Respondent’s correspondence to developer
[7] Ibid 004-507 Respondent’s correspondence to developer
Case-aware research
Ask AI about this case
The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.