Group Five Power International (Pty) Limited v Cenpower Generation Company Limited and Others (2008/41068) [2018] ZAGPJHC 663 (16 November 2018)

Group Five Power International (Pty) Limited v Cenpower Generation Company Limited and Others (2008/41068) [2018] ZAGPJHC 663 (16 November 2018)

The application failed because the applicant did not plead or establish a contractual prohibition against calling the retention bond for delay damages. The requirements for an interim interdict were not met, as the applicant did not show a prima facie right or irreparable harm, nor did it establish fraud or lack of...

Source-derived case information.

Citation
[2018] ZAGPJHC 663
Parties
Applicant: Group Five Power International (Pty) Limited; Respondent: Cenpower Generation Company Limited; Respondent: HSBC Bank PLC, Johannesburg Branch; Respondent: Standard Chartered Bank
Court
South Gauteng High Court, Johannesburg
Jurisdiction
South Africa
Case Number
2008/41068
Procedural Posture
Urgent Application / Application for Interim Interdict Pending Arbitration
Outcome
Application dismissed with costs, including costs of two counsel.
Judges
WHG van der Linde
Legal Topics
On Demand Bonds, Interim Interdict, Fraud Exception, Construction Contracts, Arbitration Referral, Balance of Convenience
Commercial and Corporate Civil Procedure Banking and Finance On Demand Bonds Interim Interdict Fraud Exception Construction Contracts Arbitration Referral +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Group Five Power International (Pty) Limited

Applicant

Cenpower Generation Company Limited

Respondent

HSBC Bank PLC, Johannesburg Branch

Respondent

Standard Chartered Bank

Respondent

Procedural Posture

Urgent Application / Application for Interim Interdict Pending Arbitration

  1. 1 Whether the owner was contractually prohibited from calling the retention bond for delay damages.
  2. 2 Whether the owner acted fraudulently or without honest belief in asserting breach by the contractor when calling the bonds.
  3. 3 Whether the requirements for an interim interdict pending arbitration are satisfied.

Ratio Decidendi

The application failed because the applicant did not plead or establish a contractual prohibition against calling the retention bond for delay damages. The requirements for an interim interdict were not met, as the applicant did not show a prima facie right or irreparable harm, nor did it establish fraud or lack of honest belief on the part of the owner in asserting breach. The disputes regarding extensions of time and readiness to commission were complex and not suitable for resolution on affidavit. The owner’s conduct did not meet the high threshold for fraud required to interdict payment under on-demand bonds. The balance of convenience did not favour the applicant, and the contractual...

Court Disposition

Application dismissed with costs, including costs of two counsel.

Orders

  • The application to amend the notice of motion is dismissed.
  • The main application for interim interdict is dismissed with costs, including the costs of two counsel.