Download PDF

South Africa Judgment

North Gauteng High Court, Pretoria

Growthpoint Properties Ltd v M Bay Specialist (Pty) Ltd and Another (62145/2019) [2020] ZAGPPHC 416 (21 August 2020)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the amended plea, although lacking detail regarding the representations and the fitness of the premises, sufficiently pleaded facts to constitute a defence. The obligation to provide beneficial occupation is reciprocal to the obligation to pay rent, and the defendants' reliance on the exceptio non adimpleti contractus is justified in this context. The plaintiff's argument that written notice and an opportunity to remedy breach were required before cancellation is a matter for replication, not exception. Regarding the counterclaim, the court held that it was deficient due to insufficient detail about the payment to the architect and the RAF penalty, and upheld the exception against the counterclaim, granting the first defendant leave to amend.

Court disposition

The exception against the defendants' plea is dismissed; the exception against the first defendant's counterclaim is upheld with leave to amend; each party to pay its own costs.

Orders

  • The exception against the defendants' plea is dismissed.
  • The exception against the first defendant's counterclaim is upheld and the first defendant is granted twenty court days to deliver a notice of amendment to the counterclaim, failing which the counterclaim shall be struck out.
  • Each party shall pay its own costs.

02

Material facts

Parties

Growthpoint Properties Ltd

Plaintiff Counsel: Adv. U Lottering

M Bay Specialist (Pty) Ltd

Defendant Counsel: Adv. S Nkuna

Pinto Omonge Kidige

Defendant Counsel: Adv. S Nkuna

Amounts and remedies

  • Architect's Fee Paid by First Defendant: ZAR 10,000
  • RAF Penalty Imposed on First Defendant: ZAR 174,000

03

Procedural history

  1. Posture

    Civil Procedure / Exception to Plea and Counterclaim

04

Questions and positions

Legal issues

Party arguments

Applicant
The plaintiff argued that the amended plea fails to disclose a defence as it does not specify the representations made or the fitness of the premises for the intended use. The plaintiff further contended that clause 5 of the lease agreement does not indicate any breach by the plaintiff and that the defendants impermissibly rely on the exceptio non adimpleti contractus, which is not applicable as the obligations are not reciprocal.
Respondent
The defendants argued that they did not repudiate the contract but cancelled it due to the plaintiff's failure to deliver beneficial occupation of the premises on the stipulated date. They relied on clause 5 of the agreement and maintained that the obligation to provide beneficial occupation is reciprocal to the obligation to pay rent, thus justifying their cancellation of the agreement.

05

Court’s reasoning

  1. 01

    Vermeulen v Goose Valley Investments (Pty) Ltd 2001(3) SA 986 (SCA); Trustees for the time being of the Bus Industry Restructuring Fund v Break Through Investments CC 2008(1) SA 67 (SCA)

    An exception alleging that a pleading lacks necessary averments aims to dispose of the need for evidence at trial and must address the root of the claim or defence.

  2. 02

    First National Bank of SA Ltd v Perry NO 2001(3) SA 960 (SCA)

    An exception is decided solely on the respondent's allegations and cannot resolve factual disputes.

  3. 03

    Harms, Amler’s Precedents of Pleadings, Fourth Edition at 201

    The obligation to provide beneficial occupation of leased premises is reciprocal to the obligation to pay rent, and failure to do so goes to the root of the contract, entitling the innocent party to cancel the agreement.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the amended plea, although lacking detail regarding the representations and the fitness of the premises, sufficiently pleaded facts to constitute a defence. The obligation to provide beneficial occupation is reciprocal to the obligation to pay rent, and the defendants' reliance on the exceptio non adimpleti contractus is justified in this context. The plaintiff's argument that written notice and an opportunity to remedy breach were required before cancellation is a matter for replication, not exception. Regarding the counterclaim, the court held that it was deficient due to insufficient detail about the payment to the architect and the RAF penalty, and upheld the exception against the counterclaim, granting the first defendant leave to amend.

Obiter and limits

  • It appears somewhat opportunistic for a plaintiff to claim damages for the full contract value of a lease that was never implemented, not even during the month of free rental.
  • Both parties were equally successful in having the exception upheld or discharged, justifying each party bearing its own costs.

Court disposition

The exception against the defendants' plea is dismissed; the exception against the first defendant's counterclaim is upheld with leave to amend; each party to pay its own costs.

  • The exception against the defendants' plea is dismissed.
  • The exception against the first defendant's counterclaim is upheld and the first defendant is granted twenty court days to deliver a notice of amendment to the counterclaim, failing which the counterclaim shall be struck out.
  • Each party shall pay its own costs.

Source and reliance status

North Gauteng High Court, Pretoria

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

North Gauteng High Court, Pretoria

Judgment

[2020] ZAGPPHC 416

HIGH

COURT OF SOUTH AFRICA

(GAUTENG DIVISION, PRETORIA)

(1) REPORTABLE: NO.

(2) OF INTEREST TO OTHER JUDGES: NO.

(3) REVISED: YES

CASE NO: 62145/2019

In the matters between:

GROWTHPOINT

PROPERTIES LTD

Plaintiff/Excipient

and

M BAY SPECIALIST (PTY) LTD

First Defendant/Respondent

PINTO

OMONGE KIDIGE

Second Defendant/Respondent

This exception has been heard in a virtual hearing via Microsoft Teams in terms of the Directives of the Judge President of this Division dated 25 March 2020, 24 April2020 and 11 May 2020. The judgment and orders are accordingly published and distributed electronically.

JUDGMENT

DAVIS, J

[1] Introduction

This is the judgment in an exception taken by a prospective landlord against the plea and counterclaim by its intended tenant and its surety.

[2] The background facts

The facts surrounding the litigation between the parties, as alleged by them, can be gleaned from the plaintiff’s particulars of claim read with the defendants’ initial plea and counterclaim and their amended plea and counterclaim. They are the following:

2.1 During approximately June 2019, the second defendant, Mr Kidige approached a property agent, Anvil Properties. He spoke to a certain “Dylan”. The discussions related to the rental of a property fit for the first defendant’s purposes. This would be a property being capable of accommodating or being able to be converted to such an extent that it would allow the first defendant to house and operate x-ray machines therein. Mr Kidige was told that one of Anvil’s clients, the

plaintiff, had such a property available for rent.

2.2 Based on what Anvil and Dylan had represented to the defendants, they contracted an architect to do the necessary planning and design to effect the installation of the x-ray machine according to specifications. The first defendant

paid the architect R 10 000,00 for this.

2.3 On 24 June 2019, the plaintiff and the first defendant signed the written agreement of lease for the premises in question. No rental would be payable for the first month but thereafter the monthly rental and costs exceeded R 20 00 per month. The lease period would commence on 1 July 2019 and run until 31 July 2022. A deposit was also payable. At the time of the signing of the lease agreement in Durban, the plaintiff was being represented by a Mr Worst. The property was situated in Umhlanga.

2.4 Shortly after the signing of the agreement, but before occupation, the plaintiff, then represented by one “Dave”, informed the defendants that the premises would not be able to accommodate the defendants’ x-ray machines and neither could alterations be made to the premises. The premises were to be used for administrative purposes only. Upon learning this, the defendants verbally cancelled the agreement. They followed this up with a written cancellation on 4 July 2019.

2.5 The plaintiff saw the cancellation as a repudiation of the contract which repudiation it accepted on 26 July 2019, thereby terminating the agreement.

2.6 Pursuant to the above, the plaintiff instituted action, claiming full rental and costs for the full period of the lease. It also seeks to hold Mr Kidige liable for the same amount based on a deed of suretyship which had somehow been signed on 18 June 2019, that is preceeding the lease agreement.

2.7 As a result of being without premises, the first defendant almost lost a contract it had with the RAF. It turns out that a penalty of some R 174 000,00 was imposed on it by the RAF, but it is not entirely clear on what basis.

2.8 The defendants filed an initial plea and counterclaim, but after some objections thereto and after giving formal notice, delivered an amended plea and counterclaim. The plaintiff, although not having objected to the amendment, now takes exception to the plea on the basis that it does not disclose a defence and to the counterclaim on the basis that it is vague and embarrassing or lacks necessary averments.

[3] The applicable legal principles

3.1 The purpose of an exception alleging that a pleading lacks averments that are necessary to sustain a defence or (counter) claim is to dispose of the leading of evidence at a trial. Such an exception must go to the root of the claim or defence. See: Vermeulen v Goose Valley Investments (Pty)Ltd 2001(3) SA 986 (SCA) and Trustees for the time being of the Bus Industry Restructuring Fund v Break Through Investments CC 2008(1) SA 67 (SCA).

3.2 An exception is decided on the allegations of the respondent/s thereto only and cannot be used to solve a factual dispute. See: First National Bank of SA Ltd v Perry NO 2001(3) SA 960 (SCA).

[4] Evaluation

4.1 The amended plea does not set out the representations made to the defendants as referred to in paragraph 2.1 above, nor does it deal with the aspect that the premises were not fit for the first defendant’s use. It also does not address the contents of the agreement itself. I interpose to state that the agreement consists of 8 pages of small script, accompanied by a 26-page set of “Standard Terms and Conditions”.

4.2 What the amended plea does state however, is that the defendants did not repudiate the contract but cancelled it based on the plaintiff’s failure to “deliver” the leased premises on 1 July 2019. Reliance was also placed on clause 5 of the agreement wherein the commencement date of 1 July 2019 had been stipulated.

4.2 The plaintiff’s exception to the plea is based on two legs: it contends firstly that clause 5 does not contain a sufficient indication as to what obligation the plaintiff has breached and secondly that the defendants appear to

impermissibly rely on an exceptio non adimpleti contractus.

4.3 Regarding the first ground of exception: Clause 5 of the agreement indicates the date of commencement of the lease. It stipulates 1 July 2019 as being that date. The Standard Terms and Conditions imposes in clause 3 thereof an obligation on the plaintiff to provide the first defendant with beneficial occupation of the premises on the date specified in clause 1.3 thereof, being in turn a date specified in a schedule thereto. The agreement appears to be a “Schedule of Fundamental

Terms” if regard is had to what has been printed on the top right-hand corner of each page thereof. Upon a proper interpretation of the agreement as a whole, the date of beneficial occupation can only be that specified in Clause 5, being the clause on which the defendants rely.

4.4 As to the second ground of exception, the plaintiff contends that the exceptio non adimpleti contractus can only be relied on in a case where there exist reciprocal obligations. The plaintiff contends that is not the case here. I beg to differ. The obligation to provide beneficial occupation of leased premises is at the very least reciprocal to the obligation to pay rent. I say “at least” on the most beneficial interpretation for the plaintiff because generally, as in this case, the plaintiff’s obligation to provide beneficial occupation, precedes any obligation to pay rent. See: Harms, Amler’s Precedents of Pleadings, Fourth Edition at 201 and the cases quoted there. The failure to provide beneficial occupation goes to the root of the contract which would ordinarily entitle an innocent party to cancel the agreement. Although the defendants probably meant to plead facts in accordance with those set out at the commencement of this judgment, I find that what had been pleaded are sufficient to constitute a defence.

4.5 During argument of the matter, it was contented that despite the obligation to provide beneficial occupation going to the root of the contract, the defendants had been obliged to first give the plaintiff a written notice and 14 days’

opportunity to remedy its breach before they became entitled to cancel the agreement. I find that this is something that the plaintiff can deal with in a replication.

4.6 Regarding the counterclaim: there are simply too little information pleaded in the amended counterclaim regarding both the payment of the architect and the basis for the imposition of the fine by the RAF as well as why the plaintiff should be liable for these amounts. This pleading is deficient and this has been conceded on behalf of the defendants during the hearing of the matter. The exception against the counterclaim should be upheld and the customary order regarding an opportunity to rectify the deficiencies should follow.

[5] Costs

It does seem somewhat opportunistic for a plaintiff to claim as damages allegedly suffered, the full contract value of a contract which, although it came into existence on paper, was never implemented, not even during the month of free rental, but that is merely an obiter observation. What is of more importance is that both sets of parties have been equally successful in having the exception upheld or discharged. In the exercise of my discretion, it would therefore be fair if each party were to pay its own costs.

[6] Order:

1. The exception against the defendants’ plea is dismissed.

2. The exception against the first defendants’ counterclaim is upheld and the first defendant is granted a period of twenty court days within which to deliver a notice of amendment to the counterclaim, failing which the counterclaim shall be struck out.

3. Each party shall pay its own costs.

N DAVIS

Judge of the High Court

Gauteng Division, Pretoria

Date of Hearing: 11 August 2020

Judgment electronically delivered: 21 August 2020

APPEARANCES:

For the Plaintiff/ Excipient: Adv. U Lottering

Attorney for Plaintiff/Excipient: Eversheds Sutherland (KZN) Inc c/o Jacobson

& Levy, Pretoria

For the Defendants:

Adv. S Nkuna

Attorney for Defendants: Nhubunga Attorneys, Pretoria

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Vermeulen v Goose Valley Investments (Pty) Ltd 2001(3) SA 986 (SCA)

Case cited

Trustees for the time being of the Bus Industry Restructuring Fund v Break Through Investments CC 2008(1) SA 67 (SCA)

Case cited

First National Bank of SA Ltd v Perry NO 2001(3) SA 960 (SCA)

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.