Haasfontein Beleggings (Pty) Ltd v Minister of Water and Sanitation and Another (WT 245/03/2016) [2021] ZAWT 2 (15 March 2021)

Haasfontein Beleggings (Pty) Ltd v Minister of Water and Sanitation and Another (WT 245/03/2016) [2021] ZAWT 2 (15 March 2021)

The Tribunal found that the directive issued to the appellant was not void for vagueness. The appellant was fully aware of the complaint, investigation, and the specific water uses at issue, having participated in the process and responded in detail. The directive referenced the relevant property, investigation, and...

Source-derived case information.

Citation
[2021] ZAWT 2
Parties
Appellant: Haasfontein Beleggings (Pty) Ltd; Respondent: Minister of Water & Sanitation; Respondent: Provincial Head: Gauteng
Court
Water Tribunal
Jurisdiction
South Africa
Case Number
WT 245/03/2016
Procedural Posture
Civil Appeal / Appeal Decision
Outcome
Appeal dismissed; directive confirmed with amendments.
Judges
T Murombo
Legal Topics
National Water Act, General Authorisation, Administrative Action, Rectification of Contravention, Environmental Impact Assessment
Administrative Law Environmental Law National Water Act General Authorisation Administrative Action Rectification of Contravention Environmental Impact Assessment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2
Sign in to unlock

Parties

Haasfontein Beleggings (Pty) Ltd

Appellant

Minister of Water & Sanitation

Respondent

Provincial Head: Gauteng

Respondent

Procedural Posture

Civil Appeal / Appeal Decision

  1. 1 Whether the directive issued under section 53(1) of the National Water Act was void for vagueness.
  2. 2 Whether the appellant's water use activities were authorised under the General Authorisation in force.
  3. 3 Whether the appellant was a lawful water user or occupier for purposes of the directive.

Ratio Decidendi

The Tribunal found that the directive issued to the appellant was not void for vagueness. The appellant was fully aware of the complaint, investigation, and the specific water uses at issue, having participated in the process and responded in detail. The directive referenced the relevant property, investigation, and prior correspondence, providing reasonable certainty as required by law. On the merits, the Tribunal held that the appellant's water use activities, specifically the construction of in-stream walls and weirs, contravened the conditions of the General Authorisation. The general authorisation did not permit permanent structures that impede watercourses or adversely affect other...

Court Disposition

Appeal dismissed; directive confirmed with amendments.

Orders

  • The appeal is dismissed.
  • The directive issued by the Second Respondent on 12 February 2016 is confirmed, subject to amendments.