Hawkins Hawkins & Osborn (South) (Pty) Ltd v Enviroserve Waste Management (3/2008) [2008] ZASCA 162; 2009 (4) SA 425 (SCA) ; [2009] 2 All SA 319 (SCA) (27 November 2008)
The Supreme Court of Appeal held that the contractor's letter of 8 September 1997 constituted a valid notice under clause 50(1) of the General Conditions of Contract. The letter provided sufficient detail regarding the nature and extent of the adverse physical conditions encountered and the additional work required, satisfying the requirements of the clause. The court rejected the appellant's argument that formal language or explicit reference to the clause was necessary, finding that the substance of the communication was sufficient. The court further held that the timing of the notice was immaterial, as clause 50(4) provided that work done prior to notice was covered by contract rates....
- Citation
- [2008] ZASCA 162
- Parties
- Appellant: Hawkins Hawkins & Osborn (South) (Pty) Ltd; Respondent: Enviroserve Waste Management
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 27 November 2008
- Case Number
- 3/2008
- Procedural Posture
- Civil Appeal / Appeal From Full Court of Eastern Cape Division, Which Reversed Trial Court's Dismissal of Respondent's Claim; Supreme Court of Appeal Judgment
- Outcome
- Appeal dismissed with costs, including costs of two counsel.
- Judges
- Mpati, Cameron, Mthiyane, Heher, Mhlantla
- Legal Topics
- Construction Contracts, Notice Requirements, Breach of Contract, Damages, Interpretation of Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Hawkins Hawkins & Osborn (South) (Pty) Ltd
Appellant
Enviroserve Waste Management
Respondent
Procedural Posture
Civil Appeal / Appeal From Full Court of Eastern Cape Division, Which Reversed Trial Court's Dismissal of Respondent's Claim; Supreme Court of Appeal Judgment
Legal Issues
- 1 Whether the contractor's letter of 8 September 1997 constituted proper notice under clause 50(1) of the General Conditions of Contract for Works of Civil Engineering Construction.
- 2 Whether the appellant breached its contractual obligations by failing to construe the contractor's communication as notice, thereby exposing the employer to liability for additional costs.
Ratio Decidendi
The Supreme Court of Appeal held that the contractor's letter of 8 September 1997 constituted a valid notice under clause 50(1) of the General Conditions of Contract. The letter provided sufficient detail regarding the nature and extent of the adverse physical conditions encountered and the additional work required, satisfying the requirements of the clause. The court rejected the appellant's argument that formal language or explicit reference to the clause was necessary, finding that the substance of the communication was sufficient. The court further held that the timing of the notice was immaterial, as clause 50(4) provided that work done prior to notice was covered by contract rates....
Court Disposition
Appeal dismissed with costs, including costs of two counsel.
Orders
- The appeal is dismissed with costs, which shall include the costs of two counsel.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment