Hawkins Hawkins & Osborn (South) (Pty) Ltd v Enviroserve Waste Management (3/2008) [2008] ZASCA 162; 2009 (4) SA 425 (SCA) ; [2009] 2 All SA 319 (SCA) (27 November 2008)

Hawkins Hawkins & Osborn (South) (Pty) Ltd v Enviroserve Waste Management (3/2008) [2008] ZASCA 162; 2009 (4) SA 425 (SCA) ; [2009] 2 All SA 319 (SCA) (27 November 2008)

The Supreme Court of Appeal held that the contractor's letter of 8 September 1997 constituted a valid notice under clause 50(1) of the General Conditions of Contract. The letter provided sufficient detail regarding the nature and extent of the adverse physical conditions encountered and the additional work required, satisfying the requirements of the clause. The court rejected the appellant's argument that formal language or explicit reference to the clause was necessary, finding that the substance of the communication was sufficient. The court further held that the timing of the notice was immaterial, as clause 50(4) provided that work done prior to notice was covered by contract rates....

Citation
[2008] ZASCA 162
Parties
Appellant: Hawkins Hawkins & Osborn (South) (Pty) Ltd; Respondent: Enviroserve Waste Management
Court
Supreme Court of Appeal
Jurisdiction
South Africa
Judgment Date
27 November 2008
Case Number
3/2008
Procedural Posture
Civil Appeal / Appeal From Full Court of Eastern Cape Division, Which Reversed Trial Court's Dismissal of Respondent's Claim; Supreme Court of Appeal Judgment
Outcome
Appeal dismissed with costs, including costs of two counsel.
Judges
Mpati, Cameron, Mthiyane, Heher, Mhlantla
Legal Topics
Construction Contracts, Notice Requirements, Breach of Contract, Damages, Interpretation of Contracts

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Hawkins Hawkins & Osborn (South) (Pty) Ltd

Appellant

Enviroserve Waste Management

Respondent

Procedural Posture

Civil Appeal / Appeal From Full Court of Eastern Cape Division, Which Reversed Trial Court's Dismissal of Respondent's Claim; Supreme Court of Appeal Judgment

  1. 1 Whether the contractor's letter of 8 September 1997 constituted proper notice under clause 50(1) of the General Conditions of Contract for Works of Civil Engineering Construction.
  2. 2 Whether the appellant breached its contractual obligations by failing to construe the contractor's communication as notice, thereby exposing the employer to liability for additional costs.

Ratio Decidendi

The Supreme Court of Appeal held that the contractor's letter of 8 September 1997 constituted a valid notice under clause 50(1) of the General Conditions of Contract. The letter provided sufficient detail regarding the nature and extent of the adverse physical conditions encountered and the additional work required, satisfying the requirements of the clause. The court rejected the appellant's argument that formal language or explicit reference to the clause was necessary, finding that the substance of the communication was sufficient. The court further held that the timing of the notice was immaterial, as clause 50(4) provided that work done prior to notice was covered by contract rates....

Court Disposition

Appeal dismissed with costs, including costs of two counsel.

Orders

  • The appeal is dismissed with costs, which shall include the costs of two counsel.