Download PDF

South Africa Judgment

Supreme Court of Appeal

Herr v Innomet (Pty) Ltd Limited (394/2015) [2016] ZASCA 82 (31 May 2016)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The Supreme Court of Appeal held that the landlord, Innomet, failed in its obligation to provide the lessee, Herr, with peaceful and undisturbed occupation of the premises as required by the lease agreement. The planned major construction directly below the leased apartment rendered the premises uninhabitable, a fact conceded by the landlord's representative. The landlord did not respond to the lessee's notifications nor did it take steps to prevent the disturbance by invoking the body corporate's conduct rules. As a result, the lessee was justified in vacating the premises and entitled to repayment of the rental deposit. The landlord's counterclaim for contractual damages failed, as it was not entitled to compensation for lost rental income under these circumstances. The appeal was upheld, and the order of the court a quo was set aside and replaced with an order dismissing the appeal with costs.

Court disposition

Appeal upheld with costs; order of the court a quo set aside and substituted with dismissal of the appeal with costs.

Orders

  • The appeal is upheld with costs.
  • The order of the court a quo is set aside and in its stead the following order is substituted: 'The appeal is dismissed with costs.'

02

Material facts

Parties

Caine Jason Herr

Appellant Counsel: C J Bresler

Innomet Projects (Pty) Limited

Respondent Counsel: R H Wilson

Amounts and remedies

  • Rental Deposit: ZAR 64,000
  • Monthly Rental (original Lease): ZAR 32,000
  • Monthly Rental (mitigation Lease): ZAR 25,000
  • Counterclaim Damages Sought: ZAR 24,000

03

Procedural history

  1. Posture

    Civil Appeal / Appeal From Gauteng Local Division, Johannesburg

04

Questions and positions

Legal issues

Party arguments

Applicant
The appellant argued that the landlord failed to provide peaceful and undisturbed occupation as required by the lease, due to imminent major construction in the building directly below the leased premises. The appellant notified the landlord of the planned construction and the resultant uninhabitability, and vacated the premises after securing alternative accommodation. The appellant contended that the landlord was obliged to return the rental deposit and that any claim for damages was unfounded, as the landlord failed to take steps to prevent the disturbance or to invoke the body corporate's conduct rules.
Respondent
The respondent contended that the appellant breached the lease agreement and its addendum by giving premature notice and vacating the premises before the permitted date, constituting repudiation. The respondent claimed damages for lost rental income, arguing that the appellant's conduct caused premature termination of the lease. The respondent maintained that the deposit could be withheld and sought compensation for the difference between the original rental and the mitigated rental received from a new tenant.

05

Court’s reasoning

  1. 01

    BK Tooling (Edms) Bpk v Scope Precision Engineering (Edms) Bpk 1979 1 SA 391 (A)

    The principle of reciprocity in contract law recognizes that parties to a contract often intend an exchange of performances, and the exceptio non adimpleti contractus allows a defendant to resist a claim where the plaintiff has not performed or tendered to perform.

  2. 02

    Sishen Hotel (Edms) Bpk v Suid-Afrikaanse Yster en Staal Industriële Korporasie Bpk [1987] ZASCA 20; 1987 (2) SA 932 (A)

    A landlord is obliged to afford the lessee peaceful and undisturbed occupation and commodus usus of the leased premises. Breach of this obligation may entitle the lessee to cancel the lease and claim damages.

  3. 03

    Thompson v Scholtz [1998] ZASCA 87; 1999 (1) SA 232 (SCA)

    Where a lessee is deprived of or disturbed in the use or enjoyment of leased property, the obligation to pay rental may be abated or extinguished, depending on the extent of deprivation.

06

Ratio, limits and disposition

Ratio decidendi

The Supreme Court of Appeal held that the landlord, Innomet, failed in its obligation to provide the lessee, Herr, with peaceful and undisturbed occupation of the premises as required by the lease agreement. The planned major construction directly below the leased apartment rendered the premises uninhabitable, a fact conceded by the landlord's representative. The landlord did not respond to the lessee's notifications nor did it take steps to prevent the disturbance by invoking the body corporate's conduct rules. As a result, the lessee was justified in vacating the premises and entitled to repayment of the rental deposit. The landlord's counterclaim for contractual damages failed, as it was not entitled to compensation for lost rental income under these circumstances. The appeal was upheld, and the order of the court a quo was set aside and replaced with an order dismissing the appeal with costs.

Obiter and limits

  • The court noted that the landlord's failure to act upon the lessee's warnings and to invoke the body corporate's conduct rules contributed to the deprivation of peaceful occupation.
  • The magnitude of the construction and its impact on habitability were undisputed and supported by photographic evidence.
  • The landlord's representative conceded under cross-examination that the premises would have been unliveable from April onwards, validating the lessee's concerns.

Court disposition

Appeal upheld with costs; order of the court a quo set aside and substituted with dismissal of the appeal with costs.

  • The appeal is upheld with costs.
  • The order of the court a quo is set aside and in its stead the following order is substituted: 'The appeal is dismissed with costs.'

Source and reliance status

Supreme Court of Appeal

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Supreme Court of Appeal

Judgment

[2016] ZASCA 82

THE

SUPREME COURT OF APPEAL OF SOUTH AFRICA

JUDGMENT

Not reportable

Case no: 394/2015

In the matter between:

CAINE

JASON

HERR

APPELLANT

and

INNOMET PROJECTS (PTY)

LIMITED

RESPONDENT

Neutral citation: Herr v Innomet (Pty) Ltd (394/2015) [2016] ZASCA 82 (30 May 2016)

Bench:

Ponnan, Majiedt, Saldulker, Swain and Zondi JJA

Heard:

16 May 2016

Delivered: 30 May 2016

Summary:

Contract: Lease agreement – landlord and tenant – reciprocity of obligations – obligation on lessor to provide peaceful and undisturbed occupation in return for rental from lessee.

ORDER

On appeal from: Gauteng Local Division, Johannesburg (Makhanya J and Ndamase AJ sitting as court of appeal).

1. The appeal is upheld with costs.

2. The order of the court a quo is set aside and in its stead the following order is substituted:

‘The appeal is dismissed with costs.’

Saldulker JA (Ponnan, Majiedt, Swain and Zondi JJA concurring):

[1] The appellant, Mr Caine Jason Herr (the lessee, Herr) instituted proceedings in the Boksburg Magistrate’s Court against the respondent lessor, Innomet Projects (Pty) Ltd (Innomet) for payment in the sum of R64 000, being a rental deposit which he had paid to Innomet pursuant to a lease agreement entered into between them on 20 January 2010 (the lease). Innomet raised a special plea to the lessee’s claim, which is not relevant for present purposes. It also instituted a counterclaim against the lessee. To the extent here relevant the counterclaim provides:

‘19. In breach of the Agreement read together with the Addendum, the Plaintiff:

19.1 purported to give the Defendant written notice dated 5 December 2010 terminating the Agreement read together with the Addendum, which notice is annexe ‘D’ to the Particulars of Claim;

19.2 prematurely vacated the Premises on 28 February 2011.

20. The Plaintiff’s conduct constitutes a repudiation of the Agreement read together with the Addendum, which repudiation the Defendant has accepted alternatively accepts subject to its rights to recover any damages it suffers as a result of the Plaintiff’s

unlawful conduct from the Plaintiff.

21.1 At the time that the Addendum was concluded it was contemplated by the Plaintiff and Defendant that the Defendant would suffer damages in the event that the Plaintiff breached the Agreement read together with the Addendum.

21.2 In order to mitigate its damages the Defendant entered into a written lease agreement with a tenant for the premises for the period 1 April 2011 to 31 March 2012 at a monthly rental of R 25 000.00. A copy of that lease is annexed marked “P1”.

22. The Defendant has suffered damages as a result of the Plaintiff’s breach which caused the premature termination of the Agreement read together with the Addendum in the form of lost rental income in the amount of R24 000.00 calculated as follows:

22.1 rental income due in terms of the Agreement read together with the Addendum for the period 1 March to 30 November 2011 at R32 000 per month in the sum of R288 000;

22.2 less rental income received and to be received by the Defendant in mitigation at R25 000 per month for the period 1 April to 30 November 2011 in the sum of R200 000;

22.3 less the Deposit of R64 000.’

[2] The magistrate’s court found in favour of the lessee and the following order was made:

‘48.1 The special plea is dismissed with costs;

48.2 Defendant is to pay the amount of R 75 026,17 to plaintiff together with interest of 4.5% per annum from 26 June 2013 to date of payment;

48.3 The counterclaim is dismissed with costs;

48.4 Costs of suit including of costs of counsel.’

[3] Aggrieved by this decision, Innomet appealed to the Gauteng Local Division, Johannesburg. The appeal succeeded before Makhanya J (Ndamase AJ concurring), who set aside the magistrate’s court order and replaced it with the following order:

‘1. The appeal succeeds.

2. The order of the court a quo is set aside and replaced with the following order:

2.1 the appellant’s special plea is upheld;

2.2 the respondent’s claim in convention is dismissed with costs;

2.3 the appellant’s counterclaim against the respondent succeeds with costs;

2.4 The respondent is ordered to pay appellant the sum of R24 000-00 together with interest thereon at 15.5% per annum from 30 November 2011 to date of final payment;

2.5 Costs are to include the costs of counsel.’

The further appeal is with the special leave of this court.

[4] Before us, counsel for Innomet conceded that there was no basis for it to have withheld the deposit, which Innomet had been obliged to repay to Herr together with interest in terms of the lease agreement. In the light of that concession, it follows that the magistrates’ court had correctly entered judgment against Innomet for payment of the amount of R 75 026.17 together with interest and there was accordingly no warrant for the high court to have overturned that order on appeal. That leaves Innomet’s counterclaim.

Background

[5] On 20 January 2010, Herr, entered into a written lease agreement with Innomet, duly represented by Mr Martin van Wijngaarden, for the rental of an apartment situated at Heron Waters, in Clifton, Cape Town (the premises). The parties agreed that the lease agreement would commence on 1 February 2010 and terminate on 30 November 2010. It was further agreed that the monthly rental for the premises would be R32 000, and a deposit of R64 000, to be paid by the lessee in terms of the agreement, would be repayable by the appellant to the respondent, subject to the lease agreement, within 14 days after termination of the lease.

[6] On 24 August 2010 an addendum to the lease agreement was signed by the parties, for the renewal of the agreement on the same terms and conditions for a further period of twelve months from 1 December 2010 until 30 November 2011. In terms of the addendum, should the lessee require early termination of the agreement, he would give Innomet four calendar months’ written notice which could only be given after 31 January 2011.

[7] However, during December 2010 Herr learnt that the owner of another unit in the same sectional title complex, Mr Gerald Goott, intended embarking on a major structural renovation of his unit in the complex, which was directly below Herr’s unit and which construction would commence in April 2011. Herr notified Innomet by e-mail on 5 December 2010 of Goott’s planned construction and informed Innomet that it would be impossible to live on the premises with a newborn baby during the construction. Herr gave notice that he and his wife would be moving out of the apartment not later than March 2011. There was no response to this e-mail.

[8] On 28 January 2011 Herr, represented by his wife, Meagan, informed Innomet by e-mail that he had secured alternative accommodation in the light of the planned construction project, and notified Innomet that he would vacate the premises on 28 February 2011, which he did.

[9] Pursuant to such notification, Innomet instructed its duly authorised agent to conduct an inspection of the premises and to collect the keys to the premises. On 1 March 2011 a final inspection was carried out on behalf of Innomet, which recorded that the apartment had been left in an excellent condition by the Herrs.

[10] Subsequent to the Herrs vacating the apartment, Innomet entered into a lease agreement with a new tenant, a Mr David Cook, at a rental of R25 000 per month for the period of 1 April 2011 to 31 March 2012.

Legal Principles

[11] In argument before us it was accepted that the lease agreement imposed reciprocal obligations on the parties. In R H Christie & GB Bradfield Christie’s The Law of Contract in South Africa 6 ed (2011) at 437, the authors state the following:

‘In BK Tooling (Edms) Bpk v Scope Precision Engineering (Edms) Bpk 1979 1 SA 391 (A) the Appellate Division reviewed in some detail the history and scope of what have come to be known as the principle of reciprocity and the exceptio non adimpleti contractus. The principle of reciprocity recognises the fact that in many contracts the common intention of the parties, expressed or unexpressed, is that there should be an exchange of performances, and the exceptio gives effect to the recognition of this fact by serving as a defence for the defendant who is sued on the contract by a plaintiff who has not yet performed or tendered to perform.’

[12] This court explained the duties of a landlord in Sishen Hotel (Edms) Bpk v Suid- Afrikaanse Yster en Staal Industriële Korporasie Bpk [1987] ZASCA 20; 1987 (2) SA 932 (A) where the facts were briefly as follows: the lessor let a hotel to the lessee for twenty years. When entering into the lease the lessee acquired the previous lessee’s interest in the building and the hotel business for a substantial sum (R350 000). At the same time the parties orally agreed that the lessee would construct additional accommodation and upgrade other facilities, upon which the lessee spent R360 000. The lessor conducted mining operations in the surrounding district and, to ensure that hotel accommodation of a high standard was available for visiting officials, the lease embodied provisions which obliged the lessee to conduct its business according to certain high standards. The lease prohibited the removal or transfer of the hotel liquor license

without the lessor’s written consent. The hotel was situated next to the national road between Kuruman and Upington and, because of its situation, attracted considerable custom. Eight years after the parties had entered into the lease the lessor, with the approval of the provincial administration, diverted the national road so that it could extend its mining operations. The diversion had an immediate impact on the profitability of the lessee’s hotel business. The hotel attracted considerably less custom than before, and its profits dropped - a thriving business changed into an unprofitable one and the lessee was eventually forced to close the hotel. The lessee sued the lessor for damages. The trial court non-suited the plaintiff.

[13] The plaintiff appealed to the Appellate Division. The essence of the plaintiff’s cause of action was that by causing the diversion of the road, the lessor was in breach of a tacit term that it would not take any steps which would interfere with access to the hotel site and prevent the flow of custom to the hotel and therefore interfere with the plaintiff’s use of the premises. This court found that the lessor’s breach of contract was of such a serious and material nature that the lessee was entitled to cancel the lease. This court held further that the lessor had committed a breach of its common law obligation to afford the lessee the commodus usus of the leased premises. (See also Ashcor Secunda (Pty) Ltd v Sasol Synthetic Fuels (Pty) Ltd [2011] ZASCA 158; 2011 JDR 1208 (SCA)).

[14] In Thompson v Scholtz [1998] ZASCA 87; 1999 (1) SA 232 (SCA) at 247A-D, this court said the following:

‘Where a lessee is deprived of or disturbed in the use or enjoyment of leased property to which he is entitled in terms of the lease, either in whole or in part, he can in appropriate circumstances be relieved of the obligation to pay rental, either in whole or in part; the Court may abate the rental due by him pro rata to his own reduced enjoyment of the merx. This is true not only where the interference with the lessee's enjoyment of the leased property is the result of vis major or casus fortuitus but also where it is due to the lessor's breach of contract, e.g. because the leased property is not fit for the purpose for which it was leased or, as in this case, because the performance rendered by the lessor is incomplete or partial. . . The lessee would be entirely absolved from the obligation to pay rental if he were deprived of or did not receive any usage whatsoever.’

Conclusions

[15] Applying the legal principles to the facts it is clear that Innomet cannot succeed in its claim for contractual damages. As landlord, Innomet was obliged in terms of the lease to provide the Herrs with peaceful and undisturbed occupation. Innomet failed to respond to the e-mails sent by the lessee on 5 December 2010 and 28 January 2011. The e-mails gave a graphic account of the effect of the planned construction which would have deprived the Herrs of the use and enjoyment of the premises. Photographs handed in as exhibits during the hearing depict the magnitude of the construction which, inter alia required the use of a large crane, and a large construction crew would have required direct access to the building on a daily basis. Furthermore building ramps down to the pool area for concrete and equipment had to be installed for easy movement up and down on the construction site. All of this would have taken place directly below Herr’s apartment. The resultant noise and inconvenience would undisputedly render the premises uninhabitable. This was conceded under cross examination by Mr van Wijngaarden, who stated that had he been in a similar situation as Herr he would probably have found alternative accommodation and that the Herr’s concerns that the apartment would be ‘unliveable from April onwards’ were not baseless.

[16] Innomet had an obligation towards Herr to object to the planned construction by Goott, by raising it with the trustees of the

sectional title complex. The conduct rules of the body corporate of Heron Waters state that ‘an owner shall not make alterations to his section, which are likely to impair the stability of the building or the amenity of other sections or the common property’. Herr as lessee could not himself invoke these conduct rules. It was for Innomet to do so. That it failed to do even after the planned

construction had been brought to its attention by the Herrs. It follows that Innomet’s counterclaim had to fail.

[17] The following order is made:

1. The appeal is upheld with costs.

2. The order of the court a quo is set aside and in its stead the following order is substituted:

‘The appeal is dismissed with costs’

____

HK Saldulker

Judge of Appeal

APPEARANCES:

For Appellant

C J Bresler

Instructed by:

Smit Jones & Pratt Attorneys, Johannesburg

Symington & De Kok. Bloemfontein

For Respondent:

R H Wilson (Heads of argument prepared by E Fasser)

Instructed by:

Webber Wentzel Attorneys, Johannesburg

Honey Attorneys, Bloemfontein

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

BK Tooling (Edms) Bpk v Scope Precision Engineering (Edms) Bpk 1979 1 SA 391 (A)

Case cited

Sishen Hotel (Edms) Bpk v Suid-Afrikaanse Yster en Staal Industriële Korporasie Bpk [1987] ZASCA 20; 1987 (2) SA 932 (A)

Case cited

Ashcor Secunda (Pty) Ltd v Sasol Synthetic Fuels (Pty) Ltd [2011] ZASCA 158; 2011 JDR 1208 (SCA)

Case cited

Thompson v Scholtz [1998] ZASCA 87; 1999 (1) SA 232 (SCA)

Case cited

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.