Download PDF

South Africa Judgment

South Gauteng High Court, Johannesburg

Idola (Pty) Ltd and Another v The City of Johannesburg Metropolitan Municipality and Another (22/9258) [2022] ZAGPJHC 307 (26 April 2022)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The applicants failed to establish a prima facie right to the interim interdict sought, as they unilaterally ceased payment for municipal services consumed at the property since June 2021. The previous court order did not entitle them to stop paying for services, nor did the existence of disputes justify non-payment. While the municipality was not entitled to terminate services without providing the required pre-termination notice, the applicants' conduct in withholding all payments undermined their claim to interim relief. The balance of convenience did not favour the applicants, and the requirements for an interim interdict were not met. Accordingly, the application was dismissed.

Court disposition

Application dismissed. Each party to pay its own costs.

Orders

  • The application is dismissed.
  • Each party is ordered to pay its own costs of the application.

02

Material facts

Parties

Idola (Pty) Ltd

Applicant Counsel: Mr J A Venter

Twin City Realty (Pty) Ltd

Applicant Counsel: Ms A Craucamp

The City of Johannesburg Metropolitan Municipality

Respondent Counsel: Mr E Sithole

The Municipal Manager of the City of Johannesburg Metropolitan Municipality

Respondent Counsel: Mr E Sithole

Amounts and remedies

  • Previous Account Balance Arrears as at 31 December 2021: ZAR 3,202,578.17
  • Current Charges as at 9 December 2021: ZAR 1,036,349.7
  • Total Alleged Indebtedness as at March 2022: ZAR 5,170,046.82
  • Alleged Overcharge for Electricity as at 8 July 2021: ZAR 2,748,849.01
  • Amount in Dispute for Electricity: ZAR 1,828,542.54
  • Tendered Payment for Disputed Sewerage Charges: ZAR 1,600,000

03

Procedural history

  1. Posture

    Urgent Application / Interim Interdict Application Before Final Determination of Related Disputes

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicants argued that the municipality attempted to terminate electricity supply to the property without providing the required pre-termination notice, in violation of its by-laws and a previous court order. They claimed substantial prospects of success in the pending dispute and alleged that termination would result in riots, property damage, and loss of leases. They asserted a prima facie right to relief, contending that disputed charges and penalties are subject to ongoing litigation.
Respondent
The municipality conceded it could not terminate services in violation of the previous order or without proper notice. However, it argued that the applicants had not paid their municipal account since June 2021 and that this non-payment entitled the municipality to terminate services. The municipality maintained its right to receive payment for services consumed, regardless of the pending disputes.

05

Court’s reasoning

  1. 01

    Setlogelo v Setlogelo 1914 AD 221

    A party seeking an interim interdict must demonstrate a prima facie right to the relief sought, a well-grounded apprehension of irreparable harm, the balance of convenience favouring the grant, and the absence of an adequate alternative remedy.

  2. 02

    Local Government Municipal Systems Act 32 of 2000

    Non-payment for municipal services consumed entitles the municipality to terminate services, provided procedural requirements such as pre-termination notice are met.

  3. 03

    Order of Siwendu J (20 October 2020)

    A previous court order interdicting termination of services remains binding until finalisation of the dispute, but does not excuse non-payment for ongoing consumption.

06

Ratio, limits and disposition

Ratio decidendi

The applicants failed to establish a prima facie right to the interim interdict sought, as they unilaterally ceased payment for municipal services consumed at the property since June 2021. The previous court order did not entitle them to stop paying for services, nor did the existence of disputes justify non-payment. While the municipality was not entitled to terminate services without providing the required pre-termination notice, the applicants' conduct in withholding all payments undermined their claim to interim relief. The balance of convenience did not favour the applicants, and the requirements for an interim interdict were not met. Accordingly, the application was dismissed.

Obiter and limits

  • The municipality ought not to have attempted termination of services without giving appropriate pre-termination notice to the applicants.
  • Nothing in the previous order or the existence of disputes entitles the applicants to cease payment for services consumed.
  • Each party should bear its own costs, given the municipality's procedural lapse and the applicants' failure to pay.

Court disposition

Application dismissed. Each party to pay its own costs.

  • The application is dismissed.
  • Each party is ordered to pay its own costs of the application.

Source and reliance status

South Gauteng High Court, Johannesburg

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

South Gauteng High Court, Johannesburg

Judgment

[2022] ZAGPJHC 307

SAFLII Note: Certain personal/private details of parties or witnesses have been redacted from this document in compliance with the law and SAFLII Policy

IN THE HIGH COURT OF SOUTH AFRICA,

GAUTENG LOCAL DIVISION, JOHANNESBURG

CASE NO: 22/9258

REPORTABLE:

NO

OF INTEREST TO OTHER JUDGES: NO

REVISED.

26 April 2022

In the matter between:

Idola (PTY) LTD

(Registration No:2014/216003/07)

First Applicant

TWIN CITY REALITY (PTY) LTD

(Registration No: 2016/253832/07)

Second Applicant

and

THE

CITY OF JOHANNESBURG METROPOLITAN

MUNICIPALITY

` First Respondent

THE

MUNICIPAL MANAGER OF THE CITY OF

JOHANNESBURG

METROPOLITAN MUNICIPALITY Second Respondent

JUDGMENT

CRUTCHFIELD J:

[1] This application came before me urgently on 22 March 2022. The first applicant is Idola (Pty) Ltd and the second applicant is Twin City Realty (Pty) Ltd.

[2] The applicants sought an interim interdict prohibiting the first respondent, the City of Johannesburg Metropolitan Municipality, and the second respondent, the Municipal Manager of the City of Johannesburg Metropolitan Municipality, (jointly referred to as the “municipality”), from disconnecting or reducing the supply of municipal services to Erf [....], Halfway House Ext 127, Johannesburg (“the property”), pending finalisation and final determination of:

2.1 The pending dispute in terms of Section 102(2) read with Section 95(f) of the Local Government Municipal Systems Act, 32 of 2000 lodged in respect of account number [....]; and

2.2 The pending dispute in this Court under case number 59297/2021, and

2.3 Costs of this application on the scale as between attorney and client in the event of opposition to the relief sought.

[3] The applicants are the registered owners of the property. The applicants are responsible for payment of the municipality’s accounts.

[4] An existing order was granted by Siwendu J, by agreement between the parties, on 20 October 2020 under case number 18237/2020.

[5] This application deals with facts that arose subsequent to the granting of the order of Siwendu J.

[6] There is a longstanding dispute between the applicants and the municipality in respect of the municipality’s charges levied in respect of the property. The dispute includes issues in respect of the valuation roll and the scale of the charges levied by the municipality against the property, the municipality’s previous termination of services to the property and the applicants’ alleged illegal reconnection thereof.

[7] Siwendu J’s order provides inter alia that upon restoration of the municipal services to the property pursuant to the order, the municipality would be interdicted from disconnecting or limiting the municipal services to the property pending the outcome and finalisation of a meeting to be convened by the municipality with the applicants within thirty (30) days of Siwendu J’s order relating to the dispute, referred to therein and hereinafter as the ‘MSA dispute’. Furthermore, Siwendu J’s order provides that the municipality adjudicate and decide on the MSA dispute and advise the applicants of the outcome thereof, within thirty (30) days of the period after the meeting having lapsed.

[8] The applicants allege that finality as envisaged in the order of Siwendu J was not achieved and the applicants launched what they termed “comprehensive” proceedings, currently pending in this Court under case number 59297/2021, to resolve the MSA dispute and ancillary issues in respect of the municipality.

[9] The applicants allege that they have substantial prospects of success under case number 59297/2021 and thus that the balance of convenience favours them in this application.

[10] The MSA dispute and the parties’ compliance or otherwise with Siwendu J’s order is before this Court under case number 59297/2021.

[11] I do not intend dealing with the issues covered by the MSA dispute, the order of Siwendu J or the proceedings under case number 59297/2021, issued during December 2021. Those disputes are before this Court for adjudication under the stated case number.

[12] The municipality concedes that it is not entitled to terminate the municipal services to the property in violation of Siwendu J’s order. However, the applicants last paid their municipal account in June 2021 and the municipality argues that that fact entitles the municipality to terminate the municipal services to the property.

[13] The applicants allege that the municipality’s representatives or contractors on behalf of the municipality, attended at the property on 24 February 2022, intending to terminate the electricity supply to the property.

[14] The representatives and/or contractors on behalf of the municipality allegedly did not have a necessary key in their possession and left, alleging that they would return to the property with the key subsequently.

[15] The applicants allege that the municipality’s attempt to terminate the electricity supply on 24 February 2022 aforementioned violated the municipality’s by-laws in that a pre-termination notice was not given by the municipality to the applicants.

[16] The municipality concedes that it is not entitled to terminate the electricity supply to the property or indeed the municipal services without having fulfilled the applicable requirements for doing so.

[17] Over and above the order of Siwendu J and the alleged failure to provide the required pre-termination notice, the municipality relies on the non-payment by the applicants for municipal services consumed by the applicants at the point of supply, being the property.

[18] The applicants allege that in the event of a termination by the municipality of the electricity supply to the property, riots, damage to the property and the loss of leases will occur, effectively amounting to damage to the applicants as envisaged in the requirements for an interim interdict. In this regard, the applicants allege that on previous occasions when the municipality terminated the electricity supply to the property, damage such as that abovementioned occurred.

[19] The applicants dispute that they are liable to the municipality for payment of municipal service charges, levies and a related penalty concerning the property and allege a prima facie right to the relief sought in the notice of motion, a prima facie right being the first requirement of an interim interdict.

[20] The issue of the penalty referred to immediately above relates to the MSA dispute and the applicants’ alleged prior unlawful reconnection of the electricity supply to the property.

[21] The existence of disputes between the applicants and the municipality however, does not permit the applicants to cease payment for the municipal services consumed at the property. Nor is there anything in the order of Siwendu J that permits the applicants to stop paying for the services consumed by it.

[22] Furthermore, the order of Siwendu J does not serve to protect the applicants against non-payment for consumption.

[23] The municipality ought not to have sought to terminate the electricity supply to the property 24 February 2022, without giving the appropriate pre-termination notice to the applicants and the applicants are entitled to an order to that extent.

[24] As to the applicants alleged prima facie right to the relief sought in the notice of motion, the applicants were indebted to the municipality in respect of arrears, the “previous account balance”, in the amount of R3 202 578.17, the due date of which was allegedly 31 December 2021. The applicants were indebted to the municipality as at 9 December 2021 in respect of current charges, in the amount of R1 036 349.70.

[25] Furthermore, the applicants were indebted allegedly to the municipality as at March 2022, in the amount of R5 170 046.82 in respect of electricity and water consumption, allegedly based on the actual reading of the electricity and water consumption meters. Part of that amount includes the disputed amounts referred to by the applicants hereunder. Even taking into account the disputed amounts regarding water and electricity consumption as at 20 October 2020, the date of Siwendu J’s order, the applicants remain indebted to the municipality, particularly but not only in respect of the period subsequent to Siwendu J’s order.

[26] The municipality is entitled to receive payment pending finalisation of the disputes between the parties and the applicants are not entitled to stop paying as they did, during June 2021.

[27] Whilst it appears that the applicants do enjoy prospects of success under the MSA dispute, they are not entitled to take the law into their own hands and simply stop paying for the services consumed at the property. This is notwithstanding the alleged overcharge by the municipality in the amount of R2 748 849.01 as at 8 July 2021 for electricity consumption that is common cause between the parties. An amount of R1 828 542.54 remains in dispute.

[28] As regards water and sewerage, the applicants tendered to pay an amount of R1 600 000.00 in respect of the disputed sewerage charges.

[29] Whilst the municipality is not entitled to terminate services to the property in violation of Siwendu J’s order and its own by-laws, including prior notice to the applicants, the applicants are not entitled to simply stop paying for all services consumed by it.

[30] Nothing entitles the applicants to the interim interdict sought by it in circumstances where it unilaterally elected to stop paying for the services consumed by it. This is notwithstanding the substantive disputes between the applicants and the municipality and the alleged overcharge by the municipality.

[31] At the very least, the applicants ought to have paid the amounts they contended were due for actual consumption at the property in respect of the municipal services, from June 2021. The applicants however failed to pay anything at all.

[32] In the circumstances, the applicants failed to show a prima facie right to the relief sought by them and the application stands to be dismissed.

[33] As regards the costs of the application, the municipality was not entitled to terminate electricity supply to the property without giving the applicant’s due notice thereof.

[34] In the circumstances, I am of the view that each party should pay its own costs of this application.

[35] By reason of the aforementioned, I grant the following order:

1. The application is dismissed;

2. Each party is ordered to pay its own costs of the application.

I hand down the judgment.

CRUTCHFIELD

J

JUDGE

OF THE HIGH COURT OF SOUTH AFRICA

GAUTENG

LOCAL DIVISION

JOHANNESBURG

Electronically submitted therefore unsigned

Delivered: This judgment was prepared and authored by the Judge whose name is reflected and is handed down electronically by circulation to the Parties / their legal representatives by email and by uploading it to the electronic file of this matter on CaseLines. The date of the judgment is deemed to be 26 April 2022.

COUNSEL FOR THE APPLICANTS:

Mr J A Venter &

Ms A Craucamp

INSTRUCTED BY:

Jacques Classen Inc

COUNSEL FOR THE RESPONDENTS:

Mr E Sithole

INSTRUCTED BY:

Motimele Masete Attorneys

DATE OF THE HEARING:

22 March 2022

DATE OF JUDGMENT:

26 April 2022

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Setlogelo v Setlogelo 1914 AD 221

Case cited

Order of Siwendu J (20 October 2020)

Case cited

Local Government Municipal Systems Act 32 of 2000

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.