Imprefed (Pty) Ltd. v National Transport Commission (13/91) [1993] ZASCA 36; 1993 (3) SA 94 (AD); [1993] 2 All SA 179 (A) (22 March 1993)
The Supreme Court of Appeal held that the appellant's claims for additional remuneration, loss of productivity, and overheads were not sustainable under the contract. The contract was a rate and measurement contract, and the agreed rates or contract rates governed all remuneration for work done, including variations and extra work. The appellant's attempt to claim additional compensation based on fairness, more onerous conditions, or the Engineer's recommendations was rejected, as the contract provided exclusive remedies and mechanisms for payment. The pleadings did not permit reliance on contract clauses not expressly pleaded, and the appellant failed to isolate and prove the effect of...
- Citation
- [1993] ZASCA 36
- Parties
- Appellant: Imprefed (Proprietary) Limited; Respondent: National Transport Commission
- Court
- Supreme Court of Appeal
- Jurisdiction
- South Africa
- Judgment Date
- 22 March 1993
- Case Number
- 13/91
- Procedural Posture
- Civil Appeal / Appeal From the Transvaal Provincial Division; Judgment Delivered After Hearing Cross Appeal and Appeal
- Outcome
- Appeal dismissed with costs; cross-appeal allowed with costs; absolution from the instance on all claims with costs, including costs of two counsel.
- Judges
- Joubert, E M Grosskopf, Kumleben, Nienaber, Van Coller
- Legal Topics
- Construction Contracts, Variation Orders, Remuneration Under Contract, Pleading Precision, Damages for Breach, Quantification of Claims
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Imprefed (Proprietary) Limited
Appellant
National Transport Commission
Respondent
Procedural Posture
Civil Appeal / Appeal From the Transvaal Provincial Division; Judgment Delivered After Hearing Cross Appeal and Appeal
Legal Issues
- 1 Whether the appellant is entitled to additional remuneration under the contract for delays and extra work.
- 2 Whether the contract rates or agreed rates apply to work done under variation or extra work orders.
- 3 Whether the pleadings permit reliance on specific contract clauses not expressly pleaded.
Ratio Decidendi
The Supreme Court of Appeal held that the appellant's claims for additional remuneration, loss of productivity, and overheads were not sustainable under the contract. The contract was a rate and measurement contract, and the agreed rates or contract rates governed all remuneration for work done, including variations and extra work. The appellant's attempt to claim additional compensation based on fairness, more onerous conditions, or the Engineer's recommendations was rejected, as the contract provided exclusive remedies and mechanisms for payment. The pleadings did not permit reliance on contract clauses not expressly pleaded, and the appellant failed to isolate and prove the effect of...
Court Disposition
Appeal dismissed with costs; cross-appeal allowed with costs; absolution from the instance on all claims with costs, including costs of two counsel.
Orders
- Absolution from the instance on all claims with costs, including costs occasioned by the employment of two counsel.
- The order of the court a quo is altered to reflect absolution from the instance on all claims.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment