Download PDF

South Africa Judgment

Kwazulu-Natal High Court, Durban

Indo Contractors CC v TFMC (Pty) Ltd and Others (8108/2009) [2009] ZAKZDHC 20 (12 June 2009)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the applicant failed to establish a prima facie right to the interim relief sought. The evidence indicated that the first respondent acted as principal and not as agent for the second respondent, and was not exercising public power or performing a public function under an empowering provision. The tender evaluation was conducted prior to the disputed email and was based on technical recommendations, not improper motive. The balance of convenience did not favour the applicant, as delays would jeopardize the completion of critical telecommunications infrastructure required for the Umhlanga area and the upcoming 2010 Fifa World Cup. The applicant's submissions regarding inconvenience were outweighed by the urgency and public interest in completing the project. Accordingly, interim relief was declined.

Court disposition

Interim relief declined; matter adjourned sine die with costs awarded against the applicant.

Orders

  • The application for interim relief is dismissed.
  • The matter is adjourned sine die.
  • The applicant is ordered to pay the costs of the application.

02

Material facts

Parties

Indo Contractors CC

Applicant Counsel: L B Broster SC

TFMC (Pty) Limited

Respondent Counsel: C J Pammenter SC

Telkom SA Limited

Respondent

GVK – Siya Zama

Respondent

Amounts and remedies

  • Tender Contract Value Threshold Referenced: ZAR 10,000,000

03

Procedural history

  1. Posture

    Urgent Application / Interim Interdict Pending Review

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant argued that the first respondent acted as agent for the second respondent, an organ of state performing a public function, and was therefore subject to the Promotion of Administrative Justice Act. The applicant contended that the tender conditions excluding the giving of reasons conflicted with the Act, and that the tender was not awarded to the applicant due to improper motive. It was submitted that the applicant had at least a prima facie right to interim relief and that the balance of convenience favoured the interdict as the site was only in the process of being handed over, causing little inconvenience.
Respondent
The first respondent denied acting as agent for the second respondent, asserting it was an independent company providing turnkey facilities to Telkom and acting as principal. It argued it was not exercising public power or performing a public function under an empowering provision, and thus not subject to the Promotion of Administrative Justice Act. The respondent provided evidence that the tender evaluation was conducted prior to the disputed email and based on technical recommendations, and that delays would jeopardize critical infrastructure deadlines, especially in light of the 2010 Fifa World Cup.

05

Court’s reasoning

  1. 01

    Setlogelo v Setlogelo 1914 AD 221

    For interim interdicts, the applicant must establish a prima facie right, a well-grounded apprehension of irreparable harm, that the balance of convenience favours the grant, and that no other satisfactory remedy exists.

  2. 02

    Promotion of Administrative Justice Act 3 of 2000

    Administrative action by a private entity is only reviewable under the Promotion of Administrative Justice Act if it exercises public power or performs a public function under an empowering provision.

  3. 03

    Logbro Properties CC v Bedderson NO and Others 2003 (2) SA 460 (SCA)

    Tender decisions must be rational and not motivated by improper reasons; however, technical evaluation and expert recommendations are valid bases for award.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the applicant failed to establish a prima facie right to the interim relief sought. The evidence indicated that the first respondent acted as principal and not as agent for the second respondent, and was not exercising public power or performing a public function under an empowering provision. The tender evaluation was conducted prior to the disputed email and was based on technical recommendations, not improper motive. The balance of convenience did not favour the applicant, as delays would jeopardize the completion of critical telecommunications infrastructure required for the Umhlanga area and the upcoming 2010 Fifa World Cup. The applicant's submissions regarding inconvenience were outweighed by the urgency and public interest in completing the project. Accordingly, interim relief was declined.

Obiter and limits

  • The court noted that instructions from counsel regarding the applicant's experience in projects exceeding R10 million could not be considered as they were not supported by the papers before the court.
  • The urgency of the matter was heightened by the impending deadlines for the completion of the Gateway exchange and the anticipated influx of visitors for the 2010 Fifa World Cup.

Court disposition

Interim relief declined; matter adjourned sine die with costs awarded against the applicant.

  • The application for interim relief is dismissed.
  • The matter is adjourned sine die.
  • The applicant is ordered to pay the costs of the application.

Source and reliance status

Kwazulu-Natal High Court, Durban

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Kwazulu-Natal High Court, Durban

Judgment

[2009] ZAKZDHC 20

IN THE HIGH COURT OF SOUTH AFRICA

KWAZULU-NATAL, DURBAN

CASE NO: 8108/2009

In the matter between:

INDO CONTRACTORS CC Applicant

and

TFMC (PTY) LIMITED First Respondent

TELKOM SA LIMITED Second Respondent

GVK – SIYA ZAMA Third Respondent

___ ___

REASONS FOR JUDGMENT

___ ___

SKINNER AJ:

[1] This matter was brought as an urgent application before me on 10 June 2009. The applicant sought an order pending the outcome of an application for review, interdicting inter alia the third respondent from commencing with the works necessary for the construction of a new telephone exchange at Gateway ATE. It was common cause or at least not disputed that the third respondent which was the successful tenderer in the tender in dispute, “would, in order to meet the tight deadlines which have been set in order to complete the contract timeously, have to commence establishment of the site commencing on Friday, 12 June 2009”. Accordingly, in view of the urgency of the matter I indicated that I would give a ruling on 12 June 2009 which I did with reasons to follow. I now set out my reasons for declining to grant interim relief.

[2] The applicant’s case was that the first respondent was acting as the second respondent’s agent, that the second respondent was an organ of state performing a public function and that the first respondent in effect by carrying out the functions it did as agent of the second respondent was subject to the Promotion of Administrative Justice Act 3 of 2000. It was accordingly submitted that the provisions inserted by the first respondent into the tender and into the conditions of contract that its decisions were not subject to the giving of reasons therefor was in conflict with the provisions of such Act. It was also submitted that there was an improper motive in not awarding the tender to the applicant. Finally it was submitted that the applicant had a prima facie right, if not a clear right, to the interim relief being sought and that the balance of convenience favoured the grant of the interdict because “the relevant site is only in the process of being handed over and accordingly there can be little inconvenience to all parties concerned”.

[3] The first respondent disputed that it was acting as an agent for the second respondent and averred that it was a wholly independent company which in terms of a contract concluded between it and the second respondent provided the second respondent with “turnkey facilities”. It submitted that in the present instance its brief was “to provide Telkom with a completed infrastructure facility according to Telkom’s specifications”. It contended that it acts as a principal and effectively “sells” the completed facility to Telkom. It therefore disputed that it was exercising a public power or performing a public function in terms of an empowering provision as required in order for the matter to fall under the Promotion of Administrative Justice Act.

[6] The submission was made that:

“the motive in not awarding the present contract to the applicant is an attempt on the part of the first respondent to get the applicant to waive the amounts which are legally due to it and until such time as the applicant does so, the applicant will not be considered in any tenders. I submit further that this is not a legitimate reason for withholding such work, particularly where the work involved is work of a public nature and for the public benefit utilising public funds provided by the second respondent. I submit that on that basis alone the decision taken by the first respondent is reviewable and has to be set aside”.

[7] The response to this in an affidavit delivered on behalf of the first respondent was that the e-mail in question had been sent on 16 March 2009. This had however been preceded by certain events. The deponent to the affidavit who was a quantity surveyor stated:

“TFMC has a process which it follows before awarding tenders. There is a tender committee which consists of representatives charged with evaluating tenders technically and commercially. I was involved in the technical evaluation of the tender. To assist in doing so, I instructed an independent practising architect, Mr Roger Colley. He considered the technical aspects of Indo’s bid in some detail and reported to me. As a result, I compiled a report which I signed on 12 March 2009… I may say that I trusted and relied on the architect’s recommendation that GVK’s bid should be preferred to that of Indo, due to his vast expertise and experience. It is significant, I submit, that the evaluation took place on 8 March 2009… and the report was signed by me on 12 March 2009. This was before the date of the e-mail which forms the cause of Indo’s complaint (which was 16 March 2009)”.

[8] Another criticism of the decision to award the tender to the third respondent was that the architect in his report to the quantity surveyor previously referred to apparently indicated that he had reservations about the contractor (the applicant) not having undertaken projects of this magnitude where the contract value exceeded more than R10 million and therefore doubted whether the applicant would be able to carry out the works successfully. Mr Broster SC informed me from the bar that his instructions were that the applicant had carried out several projects in excess of the sum mentioned. While not disputing the instruction given to Mr Broster SC I clearly cannot have regard to it since it is not on the papers before me.

[9] The end result is that I am not persuaded that there are reasonable prospects that a review would succeed on the documentation before me at the time that I heard the application. From the passage set out in paragraph [7] of this judgment it would appear that if the first respondent were compelled to supply reasons for its award, it had reasons which on the face of it were valid and justified.

[10] The second aspect on which I was not satisfied is the balance of convenience. I have already set out the approach of the applicant in this regard.

[11] The deponent to the affidavit on behalf of the first respondent fairly indicated that while he had no personal knowledge of the position (in the light of the extremely limited time available to the first respondent to obtain opposing affidavits, I am prepared to accept that the relevant confirmatory affidavit would be forthcoming in due course), the position was that:

“the reasons for constructing the Gateway exchange is that current facilities in the Umhlanga area are “bursting at their seams”.

There has been considerable commercial and residential development in that area over the past few years and existing telecommunication

facilities cannot cope. In addition there is the looming problem of the 2010 Fifa World Cup. That event is anticipated to draw large numbers of players, officials and supporters in the Durban area, many of whom will find accommodation in Umhlanga. This influx of persons will require adequate telecommunication facilities in both landline and broadband. One can imagine the chaos which would be caused if soccer supporters were unable to make use of telephones and/or internet facilities. I do wish to stress however that the facilities not required only to service the 2010 Fifa World Cup. As I understand the matter, unless something is done urgently, there could be a breakdown in telecommunications and connectivity in the Umhlanga area which would seriously inhibit the ability to conduct business in that area. TFMC has undertaken to hand over the completed Gateway exchange to Telkom by 31 March 2010. Time schedules are extremely tight. Any delays could result in this deadline not being met”.

[12] It further appeared from the affidavits delivered on behalf of the first and third respondents that the third respondent had appointed a number of nominated sub paragraph-contractors in respect of electrical, standby power, mechanical, fire protection and technical security. Further, it had met with the proposed excavation contractor – the earthworks were a preliminary to most of the other work being undertaken. It was submitted that if the proposed sub paragraph-contractor could not gain access to the site and commence the earthworks it may well accept other work the consequence of which would be that it might be very difficult to obtain the services of a reputable and competent sub-contractor at a similar price to that currently being negotiated. This would cause a delay in the completion of the excavation works which would delay the entire contract.

[13] Taking the aforegoing into account I am not satisfied at this stage that the balance of convenience is in favour of the applicant.

[14] For these reasons then I declined to grant any interim relief and therefore merely adjourned the matter sine die with an appropriate order as to costs.

_______

SKINNER AJ

DATE OF HEARING 10 JUNE 2009

DATE OF JUDGMENT 12 JUNE 2009

DATE OF REASONS 17 JUNE 2009

APPLICANT’S COUNSEL MR L B BROSTER SC

APPLICANT’S ATTORNEYS GOODRICKES

ATTORNEYS

1ST RESPONDENTS’ COUNSEL MR C J PAMMENTER SC

1ST

RESPONDENTS ATTORNEYS SHEPSTONE AND WYLIE

2009Judgment Indo Contractors

2009Judgment

Indo Contractors

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Setlogelo v Setlogelo 1914 AD 221

Case cited

Logbro Properties CC v Bedderson NO and Others 2003 (2) SA 460 (SCA)

Case cited

Promotion of Administrative Justice Act 3 of 2000

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.