Ingerop South Africa (Pty) Ltd v Bloem Water and Another (4343/2021) [2025] ZAFSHC 80 (12 March 2025)

Ingerop South Africa (Pty) Ltd v Bloem Water and Another (4343/2021) [2025] ZAFSHC 80 (12 March 2025)

The court found that the review application concerning the legality of the contract between Sedibeng Water and Ingerop remains pending, as the lack of jurisdiction order did not dispose of the review but merely delayed its outcome. The application for transfer under section 27(1)(a) of the Superior Courts Act is...

Source-derived case information.

Citation
[2025] ZAFSHC 80
Parties
Applicant: Ingerop South Africa (Pty) Ltd; Respondent: Bloem Water; Respondent: The Minister of Water and Sanitation
Court
Free State High Court, Bloemfontein
Jurisdiction
South Africa
Case Number
4343/2021
Procedural Posture
Stay Application / Application for Stay Pending Review
Outcome
Application stayed pending final adjudication of the review application under case number 5403/2022.
Judges
Van Zyl
Legal Topics
Lis Pendens, Jurisdiction Transfer, Review of Administrative Action, Acknowledgement of Debt
Civil Procedure Administrative Law Lis Pendens Jurisdiction Transfer Review of Administrative Action Acknowledgement of Debt

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 11 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Ingerop South Africa (Pty) Ltd

Applicant

Bloem Water

Respondent

The Minister of Water and Sanitation

Respondent

Procedural Posture

Stay Application / Application for Stay Pending Review

  1. 1 Whether the application should be stayed on the basis of lis pendens due to a pending review application involving the same parties and subject matter.
  2. 2 Whether the lack of jurisdiction order in the review application constitutes a final outcome disposing of the review.
  3. 3 Whether the relief sought in the application is dependent on the outcome of the review regarding the legality of the contract.

Ratio Decidendi

The court found that the review application concerning the legality of the contract between Sedibeng Water and Ingerop remains pending, as the lack of jurisdiction order did not dispose of the review but merely delayed its outcome. The application for transfer under section 27(1)(a) of the Superior Courts Act is still to be adjudicated, and the review has not reached finality. The doctrine of lis pendens applies because the same parties and subject matter are involved in both the application and the review, and the relief sought in the application is directly affected by the review's outcome. To avoid conflicting judgments and ensure finality, the application must be stayed pending the...

Court Disposition

Application stayed pending final adjudication of the review application under case number 5403/2022.

Orders

  • The point in limine of lis pendens is upheld and the application is stayed pending the final adjudication of the review application issued under case number 5403/2022.
  • The costs of the application stand over for later adjudication.