Download PDF

South Africa Judgment

Free State High Court, Bloemfontein

Investeach Lerekat (Pty) Ltd v Morobane (5052/2019) [2023] ZAFSHC 29 (8 February 2023)

On this page

Professional case brief

Research organized from the available case record

Source document

01

Holding and result

The court found that the parties had modified the original contract by jointly drafting and signing annexures 'A' and 'B', which governed the completion of the construction work for the balance of R334,966.42. The plaintiff admitted to signing these annexures and to the terms contained therein. The evidence established that the plaintiff did not have sufficient funds and relied on the defendant for financial assistance, which explained the willingness to conclude the annexures. The court held that the terms of the original agreement were superseded by the subsequent agreements and that the plaintiff's reliance on the original contract was not rejected, but rather modified. The court concluded that the grounds of appeal did not raise reasonable prospects of success and dismissed the application for leave to appeal with costs.

Court disposition

Application for leave to appeal dismissed with costs.

Orders

  • The application for leave to appeal is dismissed with costs.

02

Material facts

Parties

Investeach Lerekat (Pty) Ltd

Plaintiff Counsel: Adv. F Bester

Mathediso Anna Morobane

Defendant Counsel: Adv. R.J Nkhahle

Amounts and remedies

  • Amount Claimed by Plaintiff: ZAR 130,339.38
  • Settlement Offer by Defendant: ZAR 80,000

03

Procedural history

  1. Posture

    Leave to Appeal / Application for Leave to Appeal Following Judgment on Contractual Claim

04

Questions and positions

Legal issues

Party arguments

Applicant
The applicant contended that the court misdirected itself in finding the defendant liable for R130,339.38, arguing that the plaintiff's case was based on a written contract for R450,000. The defendant maintained that the agreement was for completion of the housework with R334,966.42, the balance in her home loan account, which the plaintiff denied. The applicant argued that the court rejected the plaintiff's version, failed to consider the plaintiff's non-compliance with the contract, and did not account for further expenses incurred by the defendant. The applicant also challenged the court's approach to quantum and the award of costs, asserting that the defendant had offered R80,000 in settlement, which was not accepted.
Respondent
The respondent argued that the parties regulated their contractual relationship by jointly drafting and signing annexures 'A' and 'B', relating to completion of construction work for R334,966.42. The plaintiff admitted to signing both annexures and initially contracted to do the roof. The defendant conceded that the plaintiff provided the engineer's roof certificate. The respondent maintained that the plaintiff did not have sufficient funds to complete the project and relied on the defendant for financial assistance, explaining the conclusion of the annexures. The respondent asserted that the terms of the original agreement were modified and that the appeal had no reasonable prospect of success.

05

Court’s reasoning

  1. 01

    Section 17(1)(a)(i) of the Superior Courts Act

    Leave to appeal may only be granted where the court is of the opinion that the appeal would have a reasonable prospect of success.

  2. 02

    General principles of contract law

    Contractual terms may be modified by subsequent written agreements between the parties.

06

Ratio, limits and disposition

Ratio decidendi

The court found that the parties had modified the original contract by jointly drafting and signing annexures 'A' and 'B', which governed the completion of the construction work for the balance of R334,966.42. The plaintiff admitted to signing these annexures and to the terms contained therein. The evidence established that the plaintiff did not have sufficient funds and relied on the defendant for financial assistance, which explained the willingness to conclude the annexures. The court held that the terms of the original agreement were superseded by the subsequent agreements and that the plaintiff's reliance on the original contract was not rejected, but rather modified. The court concluded that the grounds of appeal did not raise reasonable prospects of success and dismissed the application for leave to appeal with costs.

Obiter and limits

  • The plaintiff was overhasty in instituting a claim against the defendant, given the offer of settlement.
  • The bank's refusal to release funds due to changes in building plans explained the financial arrangements between the parties.

Court disposition

Application for leave to appeal dismissed with costs.

  • The application for leave to appeal is dismissed with costs.

Source and reliance status

Free State High Court, Bloemfontein

This page organises the available record for research. Confirm quotations, current status, and subsequent treatment against the official source before relying on the case.

Judgment reading view

Judgment text

The complete available source text.

Source document

Free State High Court, Bloemfontein

Judgment

[2023] ZAFSHC 29

IN THE HIGH COURT OF SOUTH AFRICA,

FREE STATE DIVISION, BLOEMFONTEIN

CASE NO: 5052/2019

Reportable: NO

Of Interest to other Judges: NO

Circulate to Magistrates: NO

In the matter between:

INVESTEACH LEREKAT (PTY) LTD

Plaintiff

And

MATHEDISO

ANNA MOROBANE

Defendant

APPLICATION

FOR LEAVE TO APPEAL

JUDGMENT BY: MHLAMBI,

J

DELIVERED ON: This judgment was handed down electronically by circulation to the parties’ legal representatives by email and released to SAFLI. The date and time for the hand-down are deemed to be 8h00 on 08 February 2023

[1] This an application for leave to appeal in terms of section 17(1)(a)(i) which provides that leave to appeal may only be given where the Judge or Judges concerned are of the opinion that the appeal would have a reasonable prospect of success.

[2] The grounds of appeal are stated as follows:

1. The court misdirected itself in finding that the defendant is liable to pay the plaintiff the amount of R 130 339-38, regard being had on the following: -

1.1 The plaintiff’s case was based on the written contract in the amount of R 450 000-00.

1.2 The defendant’s case was that the agreement was that the plaintiff would complete the construction of the housework with the amount of R 334 966-42, which was the balance in her home loan account. The plaintiff vehemently denied any such agreement.

1.3 The court effectively rejected the plaintiff’s version in this regard.

2. The plaintiff failed to prove any amount, if any, owed to it by the defendant.

3. The court failed to take into account that the plaintiff did not comply with the terms of the very same contract he relies upon.

3.1 Mr Komako conceded under cross-examination that the plaintiff did not comply with the terms of clause 1 of the written contract between the parties, in that the plaintiff failed to provide and pay for all the material, tools, equipment and labour required to perform construction work required.

4. The court further failed to take into account the undisputed evidence of the defendant in respect of the further and or more expenses related to the construction of the house she incurred as further fortified by the transactions contained in her bank statements and which amounts were not covered in the plaintiff’s particulars of claim.

4.1 In this regard the court only focused on the deductions contained in the particulars of claim.

5. The court erroneously approached the quantum of the plaintiff’s case by simple method of deducting what was proven by the defendant as her own expenses instead of what the plaintiff could or could not prove as his damages.

6. The court erred in awarding the costs in favour of the plaintiff, regard been had of the following: -

6.1 The court effectively accepted that the intentions of the parties are covered in Exhibit “B”, which was introduced by the defendant and rejected the plaintiff’s version.

6.2 Although the court found that the defendant is indebted to the plaintiff that was not found on the basis of the plaintiff’s own evidence.

6.3 The undisputed evidence of the defendant, that she offered the amount of R 80 000-00, in settlement of the matter before it came to court and there was no evidence and or any plausible explanation why the offer was not accepted.

7. Therefore, leave to appeal to the full court of this Division stands to be granted in that the appeal would have reasonable prospects of success.

[3] In essence, the attack on the judgment is that the court accepted that the parties regulated their contractual relationship by jointly drafting and signing annexure “A” and “B” which related to the completion of the construction work for the balance of R 334 966.42 being the remainder of the bank loan extended to the respondent. Sight has been lost of the fact that the plaintiff testified that he would complete the work with that amount[1] and also admitted his signatures to both annexures “A” and “B”[2]. It was also not in dispute the plaintiff was initially contracted to do the roof as the house was only built up to the “Wall plate level”[3] and that the defendant conceded that the plaintiff did furnish her with the engineer’s roof certificate. The amount of R

334 966.42 was released to the defendant on 21 August 2019 and no payment whatsoever was made to the plaintiff.

[4] One of the grounds of appeal is a concession that the undisputed evidence is that the defendant made an offer in the amount of R 80 000.00 to the plaintiff in settlement of the matter. Despite the denial in her papers and in parts of her oral evidence that she did not owe the applicant anything, she testified that she did not refuse to pay the plaintiff. The plaintiff was overhasty to institute a claim against her.

[5] It was argued in the plaintiff’s written heads of argument that the plaintiff’s non-compliance with clause 1 of the original agreement was fatal as it militated against the sanctity and privity of contract. Furthermore, the court had rejected the plaintiff’s reliance on the agreement that was attached to the particulars of claim. The latter submission is misconceived as nowhere in the judgment was it stated that the plaintiff’s reliance on the agreement was rejected. What is clear from the judgment is that the terms of the agreement were modified by virtue of the conclusion of annexures “A” and “B” by the parties.

[6] It is common cause that the plaintiff did not have sufficient funds to complete the project and had to rely on the defendant for financial assistance. It is also undisputed that he had to alienate some of his assets to finance the project because the bank refused to release the money as it felt at risk because of the defendant having changed the building plans. This explained his willingness to conclude exhibits “A” and “B”.

[6] In the circumstances, I am of the opinion that this appeal does not have a reasonable prospect of success and should therefore fail.

[7] I therefore make the following order:

Order:

The application for leave to appeal is dismissed with costs.

MHLAMBI, J

On behalf of appellant:

Adv. F Bester

Instructed by:

Horn & Van Rensburg Attorneys

4 Nobel Street

Brandwag

Bloemfontein

On behalf of respondent: Adv. R.J Nkhahle

Instructed by:

Mavuya Attorneys Inc.

Suit 201

2nd Floor

Cuthberts Building

78 Charlotte Maxeke Street

[1] Paragraph 6 of the judgment.

[2] Paragraph 7 of the judgment.

[3] Paragraph 6 of the judgment.

Source wording is retained. Consult the source document for its original formatting and pagination.

Authorities

Authorities used by the court

Cases, legislation, regulations, and constitutional provisions identified in the available record.

Section 17(1)(a)(i) of the Superior Courts Act

Legislation

Legislation referenced in the available case record.

Case-aware research

Ask AI about this case

The judgment and available research above are public. New questions open in a separate private conversation grounded in this case.

About this LexChat collection

This page organizes the available case record for research. Verify quotations, current status, and subsequent treatment against the source document. Corrections can be reported to hello@esheria.ai.

Legal information, not legal advice. Research summaries do not replace the judgment.