Jake Trading CC v Rambore (Pty) Ltd t/a Rambore Specialist Contractors and Another (11909/2017) [2019] ZAWCHC 27 (13 March 2019)

Jake Trading CC v Rambore (Pty) Ltd t/a Rambore Specialist Contractors and Another (11909/2017) [2019] ZAWCHC 27 (13 March 2019)

The court held that there is no cogent legal policy basis to extend a delictual duty of care to the second defendant in the circumstances of this case. The plaintiff could have protected itself contractually against the risk of pure economic loss arising from damage to cables, as the City of Cape Town did in its...

Source-derived case information.

Citation
[2019] ZAWCHC 27
Parties
Plaintiff: Jake Trading CC; Defendant: Rambore (Pty) Ltd t/a Rambore Specialist Contractors; Defendant: Lucca Developments CC t/a Drillwerx
Court
Western Cape High Court, Cape Town
Jurisdiction
South Africa
Case Number
11909/2017
Procedural Posture
Exception Application / Exception to Particulars of Claim; Interlocutory Stage
Outcome
Exception upheld; claim against second defendant struck out with costs; plaintiff granted leave to amend within 15 days, failing which the claim against the second defendant is deemed dismissed with costs.
Judges
Binns-Ward
Legal Topics
Pure Economic Loss, Exception to Particulars of Claim, Wrongfulness, Duty of Care, Subcontractor Liability
Delict Civil Procedure Pure Economic Loss Exception to Particulars of Claim Wrongfulness Duty of Care Subcontractor Liability

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Jake Trading CC

Plaintiff

Rambore (Pty) Ltd t/a Rambore Specialist Contractors

Defendant

Lucca Developments CC t/a Drillwerx

Defendant

Procedural Posture

Exception Application / Exception to Particulars of Claim; Interlocutory Stage

  1. 1 Does the plaintiff's particulars of claim disclose a cause of action in delict against the second defendant for pure economic loss?
  2. 2 Is there a sufficient legal policy basis to extend a delictual duty of care to a sub-subcontractor in these circumstances?
  3. 3 Should the exception be upheld and the claim against the second defendant be struck out?

Ratio Decidendi

The court held that there is no cogent legal policy basis to extend a delictual duty of care to the second defendant in the circumstances of this case. The plaintiff could have protected itself contractually against the risk of pure economic loss arising from damage to cables, as the City of Cape Town did in its contract with the plaintiff. The absence of contractual privity between the plaintiff and the second defendant does not justify the extension of a delictual remedy, especially where the plaintiff's vulnerability to risk could have been managed by stipulating for an indemnity in the sub-subcontract. The pleaded facts do not establish wrongfulness or a breach of a legal duty by the...

Court Disposition

Exception upheld; claim against second defendant struck out with costs; plaintiff granted leave to amend within 15 days, failing which the claim against the second defendant is deemed dismissed with costs.

Orders

  • The second defendant’s exception to the plaintiff’s particulars of claim is upheld with costs.
  • Paragraphs 7-11, paragraph 20.1 (as it relates to the second defendant), paragraph 22 (as it relates to the second defendant), paragraph 24 (as it refers to the second defendant), and the prayers for judgment against the second defendant jointly and severally with the first defendant are struck out from the...